Saturday, December 23, 2017

Suit Up: Fla. Supreme Court Holds Statutory Defect Notice is a "Suit" Under CGL Policy

https://www.getrefm.com/wp-content/uploads/2015/03/condo_construction.jpg
Recently, the 11th Circuit was presented with an appeal concerning a commercial general liability ("CGL") insurer's duty to defend a general contractor.  At issue was whether statutory-required notice from an owner to the general was a "suit" under the policy triggering the defense duty.

The 11th posed this certified question to the Florida Supreme Court:
Is the notice and repair process set forth in chapter 558, Florida Statutes, a “suit” within the meaning of the commercial general liability policy?
The Court, in Altman Contractors, Inc. v. Crum & Forster Specialty Ins. Co., No. SC16-1420, 2017 WL 6379535, at *1 (Fla. Dec. 14, 2017), answered yes, Chapter 558 defect notice is a suit for purposes of CGL coverage. As such there insurer had a duty to defend. The holding has potential implications for insurers in other states that subscribe to similar defect notice schemes or rights to repair. See, e.g., Cal. Civ. Code §§ 895 et seq.; Colo. Rev. Stat. § 13-20-801 et seq.; Tex. Prop. Code. Ann. §§ 27.001 et seq. There are upwards of 30 states nationwide.

First of all, what is Fla. Stat. chapter 558?  In Florida, before suit can be commenced by any owner claiming that a construction defect exists, the owner must follow a certain notice and response procedure. Basically the owner must give notice to the contractor or design professional of the alleged defect.  Then those receiving notice provide notice to any lower-tier subcontractors that may have responsibility for the defect in question and all recipients can respond to the owner.  If the owner does not receive adequate responses, it then can file suit.  The legislative findings specifically identified this process as an "alternative dispute resolution mechanism" such that the inspections involved and any findings or settlement offers made as a result of the inspections become inadmissible if there are future proceedings.

Under the CGL policy, the insurer has the "right and duty to defend the insured against any 'suit' seeking those damages [of personal or property damage]." The definition of a "suit" is a "civil proceeding in which damages . . . to which this insurance applies are alleged." It also includes "an arbitration proceeding . . . to which the insured must submit or does submit with our consent" or "any other alternative dispute resolution proceeding . . . to which the insured submits with our consent."

Therefore, the question was whether Fla. Stat. ch. 558 notice is a "suit."  The Court analogized the notice to "other alternative dispute resolution proceeding" (especially given the legislative history) and confirmed it was indeed a suit.  The issue of insurer "consent" was a hurdle that the Court did not need to cross in the decision.  The Court observed that "whether [the insurer] consented to [the general contractor's] participation in the chapter 558 process . . . is outside the scope of the certified question and an issue of fact disputed by the parties."

---------------------------------------
The author, Katharine Kohm, Esq. is a committee member for The Dispute Resolver.  She is an associate at Pierce Atwood, LLP in Providence, Rhode Island.  Katharine thanks Anthony Lehman, Esq. of Hudson Parrott Walker in Atlanta, Georgia for his input on this post.

Friday, April 7, 2017

Reallocation Actions and Settlement Agreements: What Did We Settle?

By Stacy L. La Scala, Esq.

The purpose of a settlement and release agreement is to fully and finally dispose of a disputed matter. However, more and more often, a dispute cannot be fully resolved where non-parties to the dispute have contributed defense and indemnity amounts on behalf of one or more of the parties and have reserved the right to seek recovery of those amounts in subsequent litigation. In particular, insurance carriers are typically not part of the action and are not signatories to the settlement agreement.

Who owns the right to pursue the claim?

An essential step in any settlement negotiation, and one that is often missed, is the determination of who owns the right to the claims being asserted. The question becomes complicated where the parties to a dispute have an underlying contractual relationship that includes a defense and indemnity obligation and an insurance carrier has agreed to defend. So if a party is being defended by an insurance carrier, does that party own the right to assert and recover those fees, or does the carrier that actually paid the fees own the right?

In many jurisdictions, in order for a party to pursue contractual damages in the form of defense fees, that party has to actually incur the fees. This concept pairs with the common law notion of subrogation, wherein a carrier is subrogated to the rights of its insured to the extent of its payments. A general liability insurer that has paid a claim to a third party on behalf of its insured may have an equitable right of subrogation against other parties who are legally liable to the insured for the harm suffered by the third party, including defense and indemnification agreements. These rights are derived from the contract of insurance and include its insured’s rights against tortfeasors principally responsible for the loss and contractual indemnitors.

So how can you limit potential reallocation actions?

In recognition of a non-party carrier’s putative rights, parties to the underlying litigation have responded with a number of strategies to expand the scope of the release agreement. For instance, the parties can:
  1. Include any carriers as part of the negotiations and add them as releasing entities to the settlement agreement;
  2. Include a requirement that the claimant defend and indemnify the settling parties as part of any settlement;
  3. Require a pre-settlement assignment of claims to the claimant and have the claimant release those claims as part of a settlement; and/ or
  4. Have the carrier intervene in the action or force the carrier into the action by way of a cross-complaint and include it in a global settlement.
Is counsel well-versed in these types of settlement agreements?

The pitfalls for the novice in negotiating the scope of a settlement agreement and release are plentiful. Counsel has to be conversant with not only the claims against her client, but also who owns the rights to those claims. Should there be known third-party claims, they have to be discussed, bargained for, and, if possible, included in the settlement agreement and release. Where the third-party claims are not part of the settlement, counsel needs to understand the potential for a subsequent action, advise her client on the risk, and negotiate release language to put the client in the best-possible position should subsequent litigation be filed. Of course, finding a neutral that understands non-party rights and the limitations in settlement negotiations can significantly contribute toward the successful resolution of the matter and substantially reduce the likelihood of future litigation.

Are unknown claims going to be released as part of the settlement?

Seeking a full and final resolution of the matter, which would eliminate any future litigation arising from the subject matter of the dispute, is a lofty goal. Typically, the parties must first acknowledge that a general release does not release all known and unknown claims (pursuant to public policy, common law, or statute). As such, the parties to the negotiation must negotiate and specifically waive any limitations for unknown claims. For instance, in California and many other jurisdictions, to obtain the broadest form of release, the parties must set forth the limitations contained in California Civil Code Section 1542 and specifically waive those provisions. While including and waiving this provision in a settlement agreement is a good step toward obtaining a full and final settlement among the signatories to the agreement, it does not necessarily resolve claims of non-parties to the action. In particular, a carrier’s potential rights against its insureds and its derivative rights against third parties can provide the basis upon which a subsequent action can be maintained against the settling parties. As such, the parties to the release, the scope of the release, and third-party rights need serious consideration by counsel when negotiating a settlement and drafting the terms of the settlement and release agreement.

Stacy L. La Scala, Esq. is a mediator and arbitrator with JAMS based in Orange, Calif. His practice focuses on a wide array of disputes, including construction, insurance, business/commercial and professional liability matters.  He can be reached at slascala@jamsadr.com. 


Friday, January 20, 2017

Part of Contractor's Settlement Payment Covered by Insurer under the Duty to Defend

The California Court of Appeals in Navigators Specialty Insurance Co. v. Moorefield Construction, Inc. concluded that a general contractor's general liability (CGL) insurer must pay the general contractor for at least part of its settlement obligation notwithstanding there was no coverage.

The general contractor entered into a contract with the owner to construct a Best Buy store.  Years after the project was completed, the owner of the building sued the general contractor (and others) for breach of contract and negligence based on "claims the flooring had failed." The insurer accepted tender of defense from the general contractor with a  reservation of rights.

During the litigation it was revealed that the "flooring tiles had been installed on top of a concrete slab that emitted moisture vapor in excess of specifications." Worse, evidence came out that the general contractor knew about the excessive moisture vapors, but had directed its subcontractor to install the flooring anyway. The cost to repair the floor was $377,404.  The general contractor settled for $1,310,000. The insurer contributed the policy limits of $1 million and then filed suit that it had no duty under the policies to defend or indemnify the general contractor.

After a non-jury trial, the court agreed with the insurer and ordered the general contractor to reimburse the insurer for the entire $1 million that the insurer paid. The general contractor appealed and the Court of Appeals reversed in part.

The Court was faced with two questions - was the floor failure an "occurrence" giving rise to coverage? And did the supplementary payments provision of the policies require the insurer to still pay a part of the settlement?


For the first question, the Court answered "no" because "occurrence" under the policies was defined as an "accident." There could be no accident from the general contractor's deliberate act. As such: the insurer had no duty to indemnify the general contractor for damages and "was entitled to recoup that portion of the $1 million paid toward settlement that was attributable to damages."

As for the second question, however, the Court held that the standard CGL provision--"with respect to any claim . . . or any `suit' against an insured we defend," the insurer will pay "all costs taxed against the insured"--did require the insurer to pay for settlement "costs" and that those costs includes attorneys' fees when there, as here, was a "prevailing party attorney fees under a contract."  The Court concluded that the insurer's "duty [to defend] was not extinguished by the determination that [the insurer] had no duty to indemnify" for the damages the insured caused. The case was remanded "for a new trial limited to the issue of the amount of the $1 million paid by [the insured] that is attributable to damages, not attorney fees and costs of suit under the supplementary payments provision."
--------------------------------------------------
The author, Katharine Kohm, is a committee member for The Dispute Resolver. Katharine practices construction law and commercial litigation in Rhode Island and Massachusetts. She is an associate at Pierce Atwood, LLP in Providence, Rhode Island. She may be contacted at 401-490-3407 or kkohm@PierceAtwood.com.