More and more public owners have come to the realization that their general conditions and “front-end” documents are inadequately protecting them. Here is a checklist of clauses for owners to consider including in contracts for protection against potential construction issues. The following, in no particular order of importance, are brief summaries of some of the key clauses that owners should consider including in their contracts.
Notice
Provisions –
These provisions require the contractor to provide the owner with prompt notice
of an alleged change, delay, claim for additional compensation, or differing
site condition. A well-drafted clause will strive to bar claims that did not
comply with the notice provisions because the owner can argue that there was a
lack of notice to be able to respond. The purpose of such provisions is to give
the owner an opportunity to adequately investigate the situation in order to
verify (or rebut) the contractor’s contention and to actively participate in
the resolution and monitoring of the work. In the case of an alleged differing
site condition, the notice requirement should be one of immediate notice, since
an owner investigation is likely essential to protect evidence of the condition
and to determine how the affected work will proceed.
Differing
Site Conditions – It is important to define what a differing site condition
is and how it will be treated should one be encountered during
construction. This clause is
particularly important in projects involving significant earthwork, tunneling,
work in highly developed areas or renovation projects due to the increased
likelihood of encountering susceptible conditions unknown to the designer and
bidders.
Scheduling
Requirements – Owners must take a more active role in monitoring the
contractor’s schedule submittals in order to protect against potential improper
schedule manipulation which could lead to inflated delay claims. In order to achieve this, owners must first
have a solid specification with a mandate that requires the contractor to
submit regular and meaningful schedule data.
The areas which the specification should cover include, at a minimum:
· Technical requirements for the
initial baseline submittal and updates
· Review/acceptance procedures and
timeframes
· Updating and revisions requirements
· Treatment of “early completion”
schedules
· Inclusion of submittals and
procurement activities in the overall schedule
· Means of submitting requests for time
extensions, i.e., fragnets
Audit
Provisions –
An owner can obtain extremely valuable information for evaluating or rebutting
a contractor’s change orders and claims by gaining access to the full volume of
the contractor’s records, including all cost records and correspondence with
subcontractors. General contractors
almost always have access to the public owner’s records by virtue of public
records statutes, but often an owner can only get access to a contractor’s
records after a formal litigation process has been initiated. A well-drafted audit or access to records
clause can provide the owner with the contractual right to have access to all
the contractor’s and subcontractors’ records at all stages of construction,
thereby giving the owner much more information to utilize when assessing a
request for change order or a claim demand.
Defined
Mark-ups –
Many disputes arise because contract provisions are not clear as to what is or
what is not included within a contractor’s and subcontractor’s mark-ups and
what is allowable under the contract.
Better defined provisions will take away the guesswork and arguments
associated with this common problem and will decrease the chances that an owner
pays for “double-dipped” overhead on extra or changed work.
Escrow
of Bid Documents – This is a procedure used on large projects whereby the
contractor is required to place all of its bid preparation materials into an
escrow. Then, if a change order or claim
arises that brings the contractor’s bid or original plan of performance into
question, the owner and contractor can jointly review the bid documents to
determine whether they support the contractor’s performance.
Claim
Submittal Requirements – Often, owners are frustrated at the end of a project when
the contractor submits a disjointed omnibus claim or a claim with too sparse
details that it is virtually “non-analyzable”. The addition of a claim
submittal clause can formally specify the format, content and level of back-up
documentation that is required within the contractor’s claim to be valid; otherwise,
it will be rejected until it meets the contract requirements.
Liquidated
vs. Actual Delay Damages – When drafting contracts, owners are faced with a choice in
deciding how they are going to address the possibility of contractor-caused
delays that extend a project completion date. The Owner can elect to include a
liquidated damages provision which is a pre-determined amount included in the
bid documents that “fixes” the contractor’s daily exposure or liability for
contractor-cause delays. The other option is for the owner’s contract to be
silent regarding the amount of damages that the contractor would be liable for
in the event of a delay. In that case,
the owner could claim all reasonable, foreseeable damages caused by the
contractor’s delay.
Limitations
on “Early Completion” Damages – Another damages-related area where
an owner can protect itself is in limiting the types of damages a contractor
can claim in the event of owner-caused delays or disruptions. One type of claim that is quite prevalent is
“early completion” whereby the contractor alleges that it would have finished
the project earlier than the required contract completion, but the owner caused
the delay, so the contractor is thereby entitled to the extended overhead
costs. Owners can include clauses in their contracts that prohibit the recovery
of damages based on missed early completion dates, forcing bidders to accept
language that specifically acknowledges this premise. A contractor may argue that in the public
sector such a clause is rendered unenforceable under certain state-enacted
statutes, which essentially makes wholesale no-damages-for-delay clauses
difficult to sustain. However, the distinction that the clause only limits a
contractor’s right to claim for early completion delays is not a wholesale
denial of liability for all owner-caused delay similar to most typical no-delay-for-damages
clauses. Like any contract provision
that restricts a contractor’s ability to recover, the mere potential for disagreement
should not hinder an owner from including such a clause in its contracts.
Defining
Submittal Review Times – An area of frequent dispute and delay allegations involves
the time taken by owner’s representatives to review required contractor
submittals. When a contract is silent
about how long an owner’s representative has to review submittals, there is
often a difference of opinion as to what a reasonable review period is. This
can result in protracted arguments and even claims. An easy way to address this from the outset
is to simply specify in the bid documents the timeframe, (e.g., 20 calendar
days) that the owner has to review submittals.
This forces the contractor to schedule its work accordingly based on the
assumption that the owner contractually has “X” number of days for review. Consideration should also be given in the
specifications as to whether the review “clock” fully or partially starts over
when a submittal is properly rejected and has to be resubmitted/re-reviewed. In addition, owners should consider
prohibiting the transmission of a large number of submittals simultaneously which
could effectively overwhelm the owner’s project staff.
Estimating Requests for Information (RFI) Times and Volume – Often, claims by contractors include allegations devoted to “untimely responses” or “excessive volume” of RFIs. Both of these subjects can be addressed by the owner in the contract. The first, dealing with turnaround time, can be resolved by simply specifying a contractual turnaround time. Many owners accuse contractors of failing to plan their work ahead and then demand instantaneous responses to RFIs. To fairly set the turnaround time, the owner must take into consideration the complexity and duration of the project. With regard to the volume of RFIs, a clause can be put into the contract stating that the contractor should expect “X” number of RFIs. This way, the owner can establish a reasonable baseline for denying “excessive” RFI-related claims and establish a baseline for contractor expectation. The owner must also be on the lookout for contractors that may submit unnecessary RFIs to circumvent the baseline.
The contract provisions discussed in this article are only a handful of the key clauses that an owner should consider to help protect against untimely or inflated claims. Because each project brings a different set of circumstances and complexities, it is always advised that owners engage a construction claims expert as early as possible to resolve potential issues arising on a project.
Mark Guevara, Esq., CFCC, PSP, PMP is a Principal Claims Analyst with ARCADIS and has over 35 years of experience in the areas of construction dispute and claims analysis and resolution. He has appeared before dispute review boards, panels, mediations, trial and appellate courts, and has testified as an expert witness. He served as Chairman of the Certified Forensic Claims Consultant (CFCC) Certification Board, AACE International (AACEi) and currently serves as Chairman (Elect) of the Construction Law Section, Orange County Bar Association.