With moderator I'Ashea Myles-Dihigo guiding the discussion, an esteemed panel of Ed Everitt of Aptim; Dr. Norma Mattei, Dean of the University of New Orleans Civil and Enivronmental Engineering Department; David Kurtz, Baker, Donelson, Bearman Caldwell & Berkowitz; and Cynthia Dubberly, Trapolin Peer Architects & an adjunct professor at Tulane University analyzed the broad impacts of and reactions to super storms from the building code-based technical side and the claims-based litigation side.






Thursday, April 12, 2018

Michael D. Tarullo Honored with 2018 Cornerstone Award


The Cornerstone Award, honoring a member of the Forum who has rendered long-term exceptional service to the construction industry, to the public and to the legal profession, was presented to Michael D. Tarullo at the Construction Forum’s 2018 Annual Meeting in New Orleans, LA on April 12, 2018.  The Cornerstone Award is the highest award presented by the Forum on Construction Law.

Division 1 Practicum - Delay Claims

Handling delay claims can be one of the most confounding topics for construction litigators. During today's practicum, the experienced faculty consisting of Kelsey Kornick Funes, Robert D'Onofrio, Deborah Mastin, and Anthony Meagher reviewed the issues and strategy for handling delay claims from analyzing your client’s claims of delay to putting together a case that will convince your fact finder. The practicum provided those new to construction law with the tools needed to understand delay claims and provided an opportunity to learn from faculty with substantial trial experience in schedule delay claims as counsel, expert, and arbitrator. Attendees gained insight from observing faculty try a delay fact pattern, and the opportunity to practice on their own using a simple fact pattern.
 

Sunday, April 8, 2018

Warner Construction Consultants Reaction to I'Ashea Myles-Dihigo's Post: "Cost-Plus Contract and the Disorganized Contractor."


Warner had sent me a reaction to I'Ashea's post concerning cost-plus contracts and I thought I would pass it along.  Great dialogue and contribution.  Thank you!
-----------------------------------------------------------------------------------------------
This article is a response to compliment the excellent blog article of the Division I Dispute Resolver, written by I’Ashea Myles-Dihigo of the Leitner, Williams, Dooley & Napolitan, PLLC firm in Nashville, Tennessee, “Cost-Plus Contract and the Disorganized Contractor.”  Ms. Myles-Dihigo’s article in reference to Cost-Plus Contract project delivery and a Contractor’s exposure as a result of inadequate cost record keeping and accounting is on point. The article specifically references risk of non-payment and non-entitlement in the event of inadequate cost records as support for payment.

In addition to the article’s focus is the concept that: there is no such thing as a cost-plus Contract. This is in the sense that the Contractor thinks it can spend “whatever it costs” to execute a project, and expect payment in kind – i.e. “Hey, it’s a Cost-Plus Contract…”

Typically, Cost-Plus engagements are often much sought after and prized by Contractors due to the perception of a “softer” method of procurement and delivery. This is a typical, but mistaken approach on the part of some Contractors. They anticipate a project with less demand on tight/controlled management, supervision, and efficient execution. This is because there are not productivity targets necessary to achieve profitability and virtually no risk of financial loss, since costs will be paid as expended – efficient or not.

Nothing could be further from the truth.

In contrast to Cost-Plus contracts, is Stipulated Sum contract project delivery. Under this system the Contractor has a finite price for which to execute and deliver the project. As such, costs must be tightly managed and controlled in order for the Contractor to financially survive. Much can be (and has been) written and debated as to the merits of different Contract delivery systems, and most all of them uniquely depend upon specific project factors and variables. This includes the position that Cost-Plus is appropriate where project scope is not well defined and Stipulated Sum where project scope is well defined and detailed.

However limited project scope definition and Cost-Plus contract does not translate to no need for establishment of budgeted scope, quantitative, and cost targets, even if based on conceptual or schematic project definition.

In fact, Cost-Plus Contracts and project delivery arguably place, if not more, then equal pressure on the Contractor to tightly plan, execute, and account for the cost of the work. While cost-plus delivery implies unlimited budget, Contractors be warned that every project has a budget, and thereby funding limit. This is true whether the project is for a public entity or a wealthy private Owner/Client with implied unlimited funds and apparently little attention to cost. Cost-Plus delivery typically has more to do with limited project scope definition that it does ample available funds.

Uncontrolled execution of the work and cost expenditure will at some point catch the attention of the Client. At that point not only will the manner of cost management and record-keeping be brought into question, but attention will turn to overall project planning and execution in general. In all, this would be a very bad situation for a Contractor to find itself, and one that could be devastating to its reputation.

The subject article focuses on the demand for proper cost accounting and payment entitlement under a Cost-Plus Contract structure. However, proper cost management and accounting is also in the best interest of the Contractor’s financial performance, success, and survival. Proper, effective, and disciplined cost management and accounting, along with efficient work planning and productivity, is a necessary element of profitability, and therefore viability. Proper cost management also serves as the basis for the Contractor’s cost estimation and its ability to competitively procure work in an ever-more-competitive construction contracting market.

At the end of the day, a disciplined contractor’s cost management systems, processes, procedures, and controls should be established and implemented according to best practices regardless of Contract delivery method. Those systems can then be properly and credibly adapted and adjusted to different Contract requirements and processes across its portfolio of work. 

Myles-Dihigo , I. (2017, September 09). “Cost-Plus Contract and the Disorganized Contractor”. Retrieved November 15, 2017, from http://abaconstructionforumdivision1.blogspot.com/search?q=Cost-Plus%2BContract%2Band%2Bthe%2BDisorganized%2BContractor%E2%80%9D


-------------------------------------------------------------------------------------------------------------------------

The author, Tony Manning, Vice President, Program and Project Management Group at Warner Construction Consultants, Inc., may be contacted at 301.670.9020 or tmanning@warnercon.com.