Articles on Construction Litigation & Dispute Resolution by Division 1 of the ABA Forum on Construction Law
Wednesday, May 20, 2020
Maybe Relief for Public Contractors Should Come from Thoughtful Legislation
On public projects, the short answer is maybe not until the government steps in. Construction lawyers are faced with the unfortunate reality that public sector contracts appear to preclude contractors from seeking adjustments to the contract price because these contracts commonly include (1) a clear “no-damages-for-delay” provision, (2) time as the sole remedy for “force majeure” delays, and (3) a “compliance with laws” provision that is silent as to which party bears the risk of a change in laws. These provisions help public owners properly protect the interests of the citizens by appropriately allocating their tax dollars to a construction project that follows a carefully thought-out contract. However, as a result of these well-intentioned owner-friendly provisions, public contracts can make it difficult for contractors to receive compensation for COVID-19-related costs.
One can draw a parallel between public contracts and some of the insurance industry’s business interruption coverage policies. Of course, every insurance policy is different and must be analyzed on a case-by-case basis; however, the business interruption policies at issue often (1) have a clear “virus” exclusion, (2) require “property damage” to trigger coverage, and (3) are silent as to the application of the “civil authority” exclusion when it comes to partially mandated shutdowns (i.e. when the case is that construction offices, but not jobsites, may have been required to shut down). As a result, policyholders’ business interruption claims arising from COVID-19 are facing blanket denials from insurance carriers.
However, the denials of claims in both the insurance and construction industries alike can have potentially crippling effects. With respect to insurance, the consensus is becoming somewhat clear: the federal and/or state governments may need to step in. In response, several states (including Massachusetts, Rhode Island, New York, and New Jersey) have sponsored bills to provide long-term reimbursement relief to insurance companies and even to create exceptions to the policies’ strict exclusions, like the “virus” exclusion. As follows, attorneys are advising policyholders to follow the old adage “a claim never made is a claim never paid.” Therefore, attorneys who want to help their clients suffer less should encourage strict compliance with the “prompt” notification mechanisms to preserve claims under their insurance policies.
Similarly, attorneys are encouraging contractors to comply with the claim procedures in their public contracts, despite the currently-present contractual roadblocks. This advice is perhaps motivated with the hope that relief will be provided, whether it comes from the owner or as a part of a government-sponsored relief scheme similar to that of the insurance industry. The good news is: over one-hundred and thirty-five members of Congress agree with this approach, at least when it comes to supporting State Departments of Transportation (DOTs). On May 11, 2020, Representatives Conor Lamb and Bob Gibbs led the House in calling on Speaker Pelosi and Leader McCarthy to support approximately $49.95 billion in federal funding for State DOTs in the next COVID-19 response package.1 The request explained how support of State DOTs can help ensure planned transportation projects proceed as planned, which in turn supports the economy by protecting the jobs of State DOT employees and construction workers. Comparably, the Under Secretary of Defense released a memorandum on March 30, 2020, with the subject “Managing Defense Contracts Impacts of the Novel Coronavirus,” stating that “Where the contracting officer directs changes in the terms of contract performance, which may include recognition of COVID-19 impacts on performance under that contract, the contractor may also be entitled to an equitable adjustment to contract price using the standard FAR changes clauses (e.g., FAR 52.243-1 or FAR 52.243-2).”2 This memorandum suggests that contracting officers may have the authority to treat COVID-19 impacts as compensable delays under the FAR Changes clause.
As a matter of public policy, government intervention in line with the above makes sense. Despite the general rules that deny contractor recovery in the face of (1) a clear “no damages for delay” provision,3 (2) time as the sole remedy,4 and (3) a silent compliance with law provision,5 these rules are unfair (and perhaps unlikely to be upheld) considering the ongoing global pandemic. For example, on lump sum and GMP projects in particular, it would be inequitable for a public owner to completely deny claims for additional costs – like those of COVID-19-required demobilization and remobilization – on the basis of (1) a clear “no damages for delay” provision, (2) time as the sole remedy, and (3) a silent compliance with law provision. What’s more, public contracts are often procured via competitive bidding, which naturally means that contractors cut as many costs as safely as possible, not pricing out a ‘just in case a global pandemic shuts down this project for a couple weeks’ cushion. In fact, because public owners want to ensure that workplaces, including construction jobsites, are operating safely and in full compliance with new COVID-19 safety measures, they have a competing interest when it comes to compensating COVID-19-related costs. Since their competing interest brings with it some additional costs that were in no way contemplated by contractors when they priced their jobs, they ought to have some skin in the efforts for recovery as it would be unfair for public owners to ask contractors to simply absorb COVID-19-related costs.
Indeed, the ramifications of allowing owners (and insurers) to benefit from such harsh claim denials could have detrimental effects on the entire construction industry. Consider the alarming fact that if contractors continue to be denied compensation for COVID-19-related costs, then numerous contractors, subcontractors, and suppliers will inevitably goes out of business, thereby crumbling the industry and, likewise, the economy. While public owners and insurance companies may suffer in the short-term in light of legislation that requires exceptions to their contracts, they are in a much more stable position to weather this storm over the long-term. In other words, at present, they are not the string that will make the sweater unravel. After all, the greater suffering ought to be borne by the owner anyway, even if it is the state. One can reason that even though neither the owner nor the contractor could have ever predicted COVID-19, it is the owner – not the contractor – who remains the ultimate beneficiary of the project. As follows, maybe relief for public contractors should come from thoughtful legislation, like that already pending for the benefit of the insurance industry.
1 https://www.agc.org/sites/default/files/State%20DOT%20House%20Support%20Letter_Signed.pdf↩
2 https://federalconstruction.phslegal.com/2020/04/articles/contractor-information-sources/delays-resulting-from-coronavirus-may-be-both-excusable-and-compensable/; https://www.nationaldefensemagazine.org/articles/2020/3/16/industry-may-find-relief-for-coronavirus-delays; https://www.jdsupra.com/legalnews/delays-resulting-from-coronavirus-may-58448/↩
3 Although a contract has a clear “no damages for delay” clause, the contractor is not necessarily foreclosed from recovery if there exist other avenues for recovery within the contract. In fact, in many jurisdictions, “no damages for delay” clauses are not enforced where the delay for which recovery is sought was not reasonably contemplated by both parties at the time of contracting. JWP/Hyre Elec. Co. v. Mentor Village Sch. Dist., 968 F. Supp. 356, 360 (N.D. Ohio 1996); see Corinno Civetta Const. Corp. v. City of New York, 493 N.E.2d 905, 910 (N.Y. 1986). That is not necessarily the case in Massachusetts; however, there exist other ways a contractor can avoid the harsh effects of a “no damage for delay” clause. Joel Lewin & Eric Eisenberg, Delays, Suspensions and interruptions—No damage for delay clauses—Exceptions, Massachusetts Practice Series on Construction Law § 6:22 (2018). For example, a contractor may point to other contract provisions that provide relief. Id. (citing Stone/Congress v. Town of Andover, 6 Mass. L. Rptr. 330, 1997 WL 11737 (Mass. Super. Ct. 1997) (denying a summary judgment motion in favor of a contractor that argued that its damages were not for delays, but rather for changes in the work for which it was entitled to compensation under the changes clauses in the general contract). A closer look into the specific contract language is necessary in order to determine whether there exist other avenues for recovery.↩
4 Despite the fact that the sole remedy is time, there may still be room for a claim for additional compensation if contractor has a separate delay claim. “Force majeure” events, like abnormally bad weather and presumably the COVID-19-related costs at issue here, normally entitle the contractor to time, but not money. However, similar to the idea above that a contractor can avoid the harsh effects of a “no damage for delay” clause by pointing to other contract provisions, a contractor may recover for “force majeure” events when they are coupled with other compensable delay events. See id.; Philip J. Bruner & Patrick J. O’Connor, Jr., §3.7.2—Contractor’s Compliance with Law, Bruner & O’Connor on Construction Law, § 5:80 (Jan. 2020 Update). For example, in Appeals of Bechtel Environmental, Inc., a contractor was adversely affected by weather when a government-caused design delay pushed toxic waste landfill remediation activities into the hotter summer months, resulting in lower efficiency. Philip J. Bruner & Patrick J. O’Connor, Jr., §15.1.6.2—Weather delays, Bruner & O’Connor on Construction Law, § 5:80 (Jan. 2020 Update) (citing Appeals of Bechtel Environmental, Inc., E.N.G.B.C.A. No. 6137, E.N.G.B.C.A. No. 6166, 97-1 B.C.A. (CCH) ¶ 28640, 1996 WL 686423 (Corps Eng'rs B.C.A. 1996)). Perhaps the express language in the AIA A201-2017’s § 8.3.3 provides the support for this: “This Section 8.3 does not preclude recovery of damages for delay by either party under other provisions of the Contract Documents.”↩
5 As a general rule, if the contractor agrees to perform the work for a stipulated sum and further agrees to comply with all laws and regulations governing the performance of the work, then, in the absence of any contractual provision permitting relief, it bears the risk. Philip J. Bruner & Patrick J. O’Connor, Jr., Bruner & O’Connor on Construction Law, § 5:80 (Jan. 2020 Update) (citing DiCara v. Jomatt Const. Corp., 52 Misc. 2d 543, 276 N.Y.S.2d 11 (Dist. Ct. 1966) (contractor who agreed to sell a house at a specified price bore a responsibility for increased costs due to a 2% sales tax made applicable to the sale after the parties had reached agreement); Edwards v. United States, 19 Cl. Ct. 663 (1990) (government contract's “permits and responsibilities” clause obligated the contractor to comply with all local laws and regulations regardless of whether they became effective before or during the term of the contract and applied to zoning changes affecting the work)).↩
Author Lexie R. Pereira is a J.D./M.B.A. student at Boston College Law School, studying to become a litigator, with a specialty in construction law. At school, Lexie is the President of the Real Estate Law Society and the President of the Eagle-to-Eagle Mentoring Program. Outside of school, she is a legal intern at Consigli Construction Co., Inc. and is on the Editorial Team of the ABA’s Forum on Construction Law’s Dispute Resolver blog. This summer, she was invited to rejoin Hinckley Allen as a Summer Associate with a focus in the Construction and Public Contracts group. Lexie earned her B.A. and a varsity letter from Boston College in 2017.
Contact Information: pereirle@bc.edu ; https://www.linkedin.com/in/lexie-pereira/
Tuesday, May 19, 2020
Force Majeure Provisions in Construction Contracts and Supply Chain Disruption During the COVID-19 Pandemic
The ABA Forum on Construction Law held the sixth session in the Leadership Roundtable Series on the impacts of COVID-19 on the construction industry on May 12, 2020, with panelists from different practice areas to discuss force majeure clauses and their application to construction industry clients. The panel was moderated by Chris Beirise, of the Kenrich Group, LLC, in Las Vegas, NV. The panelists included Kristen Sherwin, of Winstead P.C. in Dallas, TX, who represents owners and developers; Tracy Steedman, of Adelberg Rudow Dorf & Handler, LLC in Baltimore, MD, who represents subcontractors and general contractors; Rhonda Caviedes, senior corporate counsel with Jacobs Engineering Group, Inc. in Dallas, TX, and Anthony Gonzales, Managing Principal of Spire Consulting Group in Austin, TX.
A “force majeure” clause is a provision in a contract that excuses a party’s performance under the contract if a failure to perform is due to unforeseen or extreme circumstances outside the party’s control. These clauses are often used in all kinds of commercial contracts to allocate risk. Ms. Caviedes noted that many clients prefer to use custom contracts that they created themselves, but counsel should consider using form contract documents that are well-established in the industry instead. Form documents such as the AIA contracts or ConsensusDOCS can provide uniformity and certainty to clients, without counsel needing to interpret and revise clients’ custom contracts numerous times.
Force majeure provisions vary by contract. Often in construction contracts, a force majeure provision will be included in a delay provision. Some contracts include force majeure provisions, and some do not. Some have incredibly specific force majeure provisions, and some have very broad provisions. Some contracts have provisions that are functional equivalents of force majeure provisions but do not mention the phrase “force majeure.” Some examples of force majeure events are “acts of God,” economic conditions or financial hardship, pandemics or epidemics, floods, hurricanes and other weather-related events, labor strikes and performance delays, and government action.
Force majeure provisions are generally enforceable in all states and typically are narrowly construed. Not all states interpret force majeure provisions the same way, however. In Texas, as Ms. Sherwin noted, a force majeure event must have been unforeseen. The time of contract making is highly relevant to foreseeability. For instance, if a contract was formed in late March 2020, then events related to COVID-19 were almost certainly foreseeable at that time. Under Texas law, only an objective impossibility – that is, a complete inability to perform – will excuse a breach of contract. Ms. Sherwin cautions attorneys to pay close attention to choice of law provisions in contracts, and evaluate the chosen state’s treatment of frustration of purpose, impossibility, and foreseeability.
Ms. Caviedes noted that force majeure provisions are often heavily negotiated, and careful drafting is very important. Often, a force majeure provisions will include a “catch-all” provision, and the placement of the catch-all language is key to the force majeure provision’s interpretation. Courts typically interpret a catch-all provision at the end of the list as being one that relates back to the items that have been identified in the immediately preceding text. Courts find that if a general meaning had been intended, then specific listed events would not have been included. “[W]here the parties have themselves defined the contours of force majeure in their agreement, those contours dictate the application, effect, and scope of force majeure" (Belgium v. Mateo Prods., Inc., 29 N.Y.S.3d 312, 315 (1st Dep't 2016) (quoting Route 6 Outparcels, LLC v. Ruby Tuesday, Inc., 931 N.Y.S.2d 436, 438 (3d Dep't 2011)). Again, numerous jurisdictions have interpreted catch-all language following specific lists, so it is critical to evaluate the chosen state’s case law on this point when drafting contracts and consulting clients during construction and at the claims phase.
On the immediate effects of COVID-19 on clients, the panelists shared their experiences, which offer useful advice to practitioners. Ms. Steedman explained that subcontractors are sending notices to general contractors and submitting requests for change orders, both related to supply chain disruptions. Suppliers are not delivering materials on time. Subcontractors need to acquire more vehicles to comply with social distancing guidelines and to rearrange schedules to ensure that various trades are not working too much at the same time.
Ms. Sherwin offered an owner’s perspective, stating that subcontractor notices should be as specific as possible. Owners pass these notices along to investors or lenders, but owners prefer not a vague notice that a supply chain disruption has occurred or is imminent. Instead, owners desire to know what the actual supply chain impact is, as soon as it is known, so that a large claim for an extreme increase in cost is not a surprise down the road. Owners are also looking for general contractors to work with suppliers directly to find alternatives to obtaining similar supplies. The circumstances related to COVID-19 are sure to cause delays and cost increases, so it is even more important that all parties on projects work together to share relevant information on a timely basis.
Another component of force majeure provisions is mitigation of damages. Mr. Gonzales noted that contractors should itemize all damages related to COVID-19 in notices of claims. Additionally, it is important to analyze whether a duty to mitigate applies, and what mitigation measures should be taken and when. Given the complexity and sophistication of the global supply chain, even under the strain of COVID-19, there are often options to obtain labor, raw materials, or other supplies from alternative sources, as well as other solutions, to avoid time and money impacts.
As always, but especially in the time of COVID-19, it is critical for clients and counsel to understand their construction contracts, to comply strictly with all notice requirements to other parties, lenders, and insurers, and to evaluate whether a force majeure provision might be used offensively or defensively.
Author Megan B. Burnett is an attorney in the Baltimore office of Miles & Stockbridge P.C., with offices in Maryland, Washington, D.C., and Virginia. She practices in the areas of commercial and business litigation, with a focus on construction law and commercial real estate disputes.
Thursday, May 7, 2020
Join The Covid-19 Leadership Roundtable Discussion on Force Majeure, Supply Chain Disruption, Delays and Claims - May 12 at 4 pm EDT
In order to serve and provide resources to our Forum members, the greater ABA, and the general public, the ABA Forum on Construction Law and strategic partners have developed a multi-part webinar series exploring how the COVID-19 pandemic is impacting construction and design and identifying options for response and risk management/mitigation. In these free, non-CLE webinars, industry leaders and attendees will have the opportunity to exchange information, learn from one another, raise questions, and offer options for addressing the deepening effects of the crisis. If you are a company leader or legal counsel, we invite you to join our conversation.
manage and prepare for the impact of COVID-19
PROGRAM DETAILS:
Format: Webinar, Expert Round Table Panel Discussion
FREE 90 Minute PROGRAM.
This program is for information sharing only, and not submitted for CLE.
May 12, 2020 | 4:00 to 5:30 P.M.ET
Multi-part Webinar Series Schedule
• 5/12: Force Majeure, Supply Chain Disruption, Delays And Claims
• 5/19: Post-Crisis Industry Impact – Expediting Use Of Technology; Virtual Depositions, Mediation/Arbitration; and Replacing In-Person Collaboration
Contact LaShaunda.Williams@americanbar.org or Tamara.Harrington@americanbar.org for more information.
Register Now
Tuesday, April 28, 2020
"Pay-When-Paid": Is there a "Reasonable Time" for Subcontractors to Wait for Payment Once Contractor-Owner Litigation Ensues?
Obviously, subcontractors prefer to be paid within a reasonable time, but the issue of what constitutes a “reasonable time” has been a conundrum many states have tackled over the years. From “pay-if-paid” to “pay-when-paid” provisions, states have either adopted one, both, or neither of these commonly controversial, heavily negotiated provisions. Recently, the California Court of Appeals has ruled on a “pay-when-paid” provision that might set the groundwork for subcontractors in other states arguing that “paid-when-paid” provisions should be against public policy.
Distinguishing Between Provisions
Both “pay-if-paid” to “pay-when-paid” provisions ultimately determine who will bear the financial risk of a construction contract. A “pay-if-paid” provision makes “payment by the owner to the general contractor a condition precedent to the general contractor’s obligation to pay the subcontractor for the work the subcontractor has performed.”1 Under a “pay-if-paid” provision, the risk of non-payment falls on the subcontractor if the owner refuses to pay the general contractor. Many states, including California, have concluded that “pay-if-paid” provisions are unenforceable because they indirectly waive or forfeit the subcontractor’s mechanic’s lien rights in the event of nonpayment by the owner.2
Under a “pay-when-paid” provision, the general contractor agrees to pay the subcontractor within a period of time after the general contractor is paid by the owner.3 Thus, under a “pay-when-paid” provision, the risk of non-payment falls on the general contractor. While a “pay-when-paid” provision is not a condition precedent, there is an implied understanding that the subcontractor has an unconditional right to payment within a reasonable time. While many states depart as to whether “pay-when-paid” provisions are enforceable, the underlining issue for a “pay-when-paid” provision is what constitutes a “reasonable time.”
Crosno Construction, Inc. v. Travelers Casualty & Surety Co. of America
On April 17, 2020, the California Fourth Appellate District Court of Appeals ruled against enforcing a “pay-when-paid” provision that would postpone the plaintiff’s right to recover under a payment bond for an indefinite time period. The underlining issue was whether a surety may defend a public works payment bond action by invoking an expansive “pay-when-paid” provision in a construction subcontract that defers payment for an indefinite period of time.4
North Edwards Water District (District) selected Clark Bros., Inc. (Clark) as its general contractor on a public works project to build an arsenic removal water treatment plant. Clark hired subcontractor Crosno Construction (Crosno) to build and coat two steel reservoir tanks.5 The subcontract contained a “pay-when-paid” provision that stated:
“If Owner or other responsible party delays in making any payment to Contractor from which payment to Subcontractor is to be made, Contractor and its sureties shall have a reasonable time to make payment to Subcontractor. ‘Reasonable time’ shall be determined according to the relevant circumstances, but in no event shall be less than the time Contractor and Subcontractor require to pursue to conclusion their legal remedies against Owner or other responsible party to obtain payment, including (but not limited to) mechanics’ lien remedies.”6
A dispute arose between Clark and District halting the project. Crosno sought to recover payment owned under the public works payment bond that Clark had obtained for the project.
The Court focused on whether postponing Crosno’s right to recover under the payment bond until Clark’s litigation against the District concluded would result in an unreasonable impairment of Crosno’s statutory payment bond remedy. Crosno never executed a waiver and release required to validly “waive, affect, or impair” its payment bond rights. Applying precedent, the court reiterated that postponing payments:
“. . . earned by a subcontractor, itself without fault, until a dispute between the contractor and the owner is resolved, perhaps months or even years later … gives no reasonable assurance that such a dispute would ever be resolved. If the contractor lost the dispute, the contractor would be required to pay his subcontractor creditor from other funds. If the contractor won the dispute, the contractor would be required to apply all or a substantial part of the money he receives toward his subcontract obligations. . . the contractor’s interest would seem more likely to benefit from avoidance of any settlement with the owner.”7
A “reasonable time,” in this case, would include an indefinite timeframe. In fact, the litigation between Clark and District had already reached the two-year mark prior to this ruling. For many subcontractors, managing business in the wake of the COVID-19 crisis is difficult enough. If subcontractors were to be forced to wait until contractor-owner litigation were resolved prior to receiving payment, most subcontractors would fail to survive.
Conclusion
Crosno reminds lawyers representing subcontractors that the purpose behind a public works payment bond is to provide subcontractors a sufficient means of payment. This distinct remedy to public works subcontractors is in addition to the protection payment bonds provide in the event of a defaulting contractor. Moreover, Crosno provides a subtle reminder of the importance of drafting specific waiver and releases. Generally, a waiver and release of payment bond rights can be enforceable to the detriment of the subcontractor. While many states differ on their enforcement of “pay-if-paid” and “pay-when-paid” provisions, arguing the element of reasonableness to protect otherwise disadvantaged subcontractors caught in-between contractor-owner litigation might be your best option.
1 Wm. R. Clarke Corp. v. Safeco Ins. Co., 15 Cal. 4th 882, 885 (1997).↩
2 Id. at 886.↩
3 Chapman Excavating Co. v. Fortney & Weygandt, Inc., 2004-Ohio-3867, ¶ 22 (Ct. App.).↩
4 Crosno Constr., Inc. v. Travelers Cas. & Sur. Co. of Am., Nos. D075561, D075562, 2020 Cal. App.at *8-9 (Ct. App. Apr. 17, 2020).↩
5 Id. at 1-2.↩
6 Id. at 4-5.↩
7 Id. at 17-18 (citing Yamanishi v. Bleily & Collishaw, Inc., 29 Cal. App. 3d 457, 463 (1972).↩
Author Christopher M. Wise is an attorney and the Managing Member of Wise Law, LLC in Louisville, Kentucky. He focuses on contractor-subcontractor litigation and property law.
Thursday, April 23, 2020
What the 1918 Flu Can Teach Us About COVID-19
State Restrictions on Construction Activity Vary
Some states have enacted significant limitations on construction projects. One of the most stringent is Pennsylvania, which on March 19, 2020, issued an executive order forcing the closure of any business not deemed “life-sustaining,” including a state-wide prohibition on construction activity. Days later, the executive order was amended to deem the construction of medical facilities and emergency repairs as “life sustaining.” On March 27, 2020, except for the construction of medical facilities and emergency repair, nearly all construction work state-wide was closed. On a case-by-case basis, the Pennsylvania Department of Community and Economic Development has granted some waivers/exemptions.
While Pennsylvania closed nearly all construction projects, both New York and New Jersey initially considered construction an “essential” business. However, as the fight against COVID-19 intensified, these states restricted their definitions of essential to be project-specific, e.g. medical facilities, infrastructure, and affordable housing. Now, New York is threatening fines of up to $10,000 against teams found working on non-essential or non-emergency construction projects. While New York has a robust and responsive waiver process, New Jersey has not instituted a formal waiver process. In some jurisdictions, municipalities responding to the COVID-19 with their own rules. Presently, there are several major metropolitan areas with significant restrictions on construction activities, including Boston and San Francisco.
On the other hand, many states including Texas and Florida have relied on federal guidance from the U.S Department of Homeland Security’s Cybersecurity and Infrastructure Security Agency (CISA). CISA deems nearly all construction projects as essential, e.g. residential construction is essential “to combat the nation’s existing housing supply shortage.” California has also permitted most construction projects to continue.
In either case, COVID-19 has likely impacted the workforce and supply of readily available labor to work on any given construction project.
Lessons from the 1918 Flu
As clients continue to struggle with the full implications of the ongoing emergency, some experts suggest analyzing a similar pandemic from 100 years ago. As soldiers returned home from the battlefields of World War One, a global pandemic of influenza cast a pale over victory celebrations. The so-called “Spanish Flu” took over 50 million lives, about twice as many as the Great War itself. In the United States, it is estimated a staggering 29 million people contracted the 1918 Flu. Approximately 675,000 Americans lost their lives.
The 1918 Flu pandemic shares some parallels with COVID-19, but there are also a few important differences. Whereas COVID-19 seems particularly dangerous for older demographics, the 1918 Flu seems to have attacked younger people between the ages of 20 and 40.1 As a result, historians believe a greater proportion of construction workers likely fell ill. In fact, one study from Toronto indicated construction workers had one of the highest mortality rates.2
The government response to the 1918 Flu was also less consistent. While some state and local governments acted aggressively to help fight the spread of the virus, there seems to have been less of a response at the federal level. Many of the local government responses were similar to today, such as mandating the use of masks in public, banning public gatherings, and encouraging social distancing. Many local businesses were ordered to close. On the other hand, mandatory shelter in place orders were uncommon 1918. Although some of the data is anecdotal, there is general agreement the 1918 pandemic caused a sharp, but short economic contraction.3 Labor shortages caused delays, shortages, and rising wages.4 Unlike the COVID-19 pandemic, which to date has included significant and ongoing economic stimulus, the 1918 pandemic did not result in any significant government stimulus. Thus, even before accounting for “work from home” or “remote work” capabilities, a direct economic comparison may prove difficult.
Available case law indicates courts reached inconsistent conclusions regarding delays and interruptions arising from the 1918 Flu. Courts seem to have generally upheld the power of local governments to enact quarantines. Soap Co. v. Peet Bros. Mfg. Co., 50 Cal. App. 246, 194 P. 715 (Cal. Ct. App. 1920). Additionally, the “contingency or delay in performance” provision in a contract was triggered by an enforcement of a local quarantine order and excused the supplier’s delayed performance. Id.
Other courts facing contract issues arising from the 1918 Flu pandemic reached the opposite conclusion. Napier v. Trace Fork Mining Co., 193 Ky. 291, 235 S.W. 766 (1921). The plaintiff entered into an agreement to complete grading as part of a railroad sidetrack construction project. Due to the 1918 Flu pandemic, the plaintiff was unable to find enough labor needed to qualify for an early completion bonus. The court refused to apply an unforeseen circumstances analysis because, “defendant accepted the work as soon as it was completed and offered to pay plaintiff therefor in exact accordance with the plain and unambiguous terms of the contract.” Id. at 767. The court found plaintiff merely showed timely completion was more difficult and expensive, not that it was impossible.
The lesson from history is that these cases are fact-sensitive even during times of pandemic. In that regard, best practices include well-tailored requests for time or additional money, supporting documents and materials to demonstrate entitlement at the claim level, and prompt notice. Much like the contractor in Napier, parties cannot risk overplaying or overstating the impact of COVID-19 on contractual performance. It appears the divergence of judicial analysis resulting from the 1918 Flu may be on the verge of repetition 100 years later.
Conclusion
The current patchwork of government restrictions on construction activity has generated a plethora of legal issues. Some of these include force majeure clauses, excusable delay, change orders, cash flow problems, employment and supply chain issues, and business interruption coverage. Although the 1918 Flu may be an imperfect comparison, it suggests COVID-19 will likely have a significant, although hopefully transitory, economic impact on the construction industry.
1 “1918 Pandemic (H1N1 Virus),” Centers for Disease Control and Prevention, https://www.cdc.gov/flu/pandemic-resources/1918-pandemic-h1n1.html (last visited April 22, 2020).↩
2 Peter Kenter, ‘”Unsung Heroes”: Toronto Construction Workers and The Spanish Flu Epidemic,” Daily Commercial News, https://canada.constructconnect.com/dcn/news/labour/2020/03/unsung-heroes-toronto-construction-workers-and-the-spanish-flu-epidemic (last visited April 22, 2020).↩
3 Thomas A. Garrett, “Economic Effects of the 1918 Influenza Pandemic: Implications for a Modern-day Pandemic,” at 9, (Federal Reserve Band of St. Louis) https://www.stlouisfed.org/~/media/files/pdfs/community-development/research-reports/pandemic_flu_report.pdf (last visited April 22, 2020).↩
4 Id. at 21.↩
Co-authors Gaetano Piccirilli, partner and Patrick McKnight, associate, are members of the Litigation Department at Klehr Harrison Harvey Branzburg LLP in Philadelphia, Pennsylvania and serve on the Klehr Harrison Coronavirus Task Force.
Tuesday, April 21, 2020
INSIGHT: Best Practices for Conducting Remote Arbitration Hearings
*********
Most businesses must now connect virtually, due to the coronavirus pandemic, and arbitration hearings are no exception. We were one week into a two-week arbitration hearing when New York City shut down, forcing the hearing to conclude via video. Video hearings may be the future of arbitration—at least in the short term.
Attorneys need to think about important considerations and best practices for conducting a hearing via video. This article also addresses applicable arbitral institution rules (or lack thereof) and discusses why this area is ripe for consideration by these institutions.
Technology Considerations
• Zoom vs. Alternatives: Zoom, a highly-popular video conference platform, is an inexpensive and effective means of conducting virtual hearings. It allows many individuals to participate, and the arbitral tribunal and speakers are visible to all participants. Screen sharing can be used to display exhibits, demonstratives, and PowerPoint presentations. Note, however, that the party initiating the meeting must have an upgraded Zoom account to utilize many features, included organizing extended meetings and virtual break-out rooms. Moreover, there have been security and privacy concerns about Zoom that are currently being investigated. Many court reporting services offer alternative platforms that provide similar features, but are generally more expensive than Zoom subscriptions.
• Transcription Services: Most court reporting services can provide transcription services via an online platform, including access to live transcription during the hearing for a daily fee.
• Translation Issues: One potentially complicating factor when conducting remote hearings is the need for translation. While many translators can provide services remotely, such translation would likely need to be sequential rather than simultaneous and would require speakers to be particularly careful not to speak over each other.
• Test the Technology: To ensure a smooth first day of the hearing, the parties, witnesses, tribunal, and court reporter should test the technology in advance. Witnesses will need to ensure they have cameras on their computers. Most importantly, everyone will need strong and reliable internet connections—particularly the tribunal, witnesses, court reporter, attorneys, and client representatives directly involved in the proceedings.
Agreed-Upon Protocol
• Implement a Written Protocol: Parties can minimize potential disputes by reaching an agreement on a detailed written protocol, including details about the schedule, exchange of exhibits, pre- and post-hearing deadlines, and other logistical matters.
• Exchange of Exhibits: The parties should outline how and when they will exchange documents and demonstratives in the written protocol, including the means for providing exhibits to be used during cross-examination to witnesses, opposing counsel, the tribunal, and the court reporter. It may be easier to exchange documents electronically, particularly during the coronavirus pandemic when many firms and document vendors have reduced onsite staffing.
• Reliability of Testimony: Possible safeguards to ensure the reliability of testimony include requiring witnesses to be alone when they testify and to affirm that they will not look at email or smartphones during the examination. If hard copy documents are sent to witnesses before they testify, the documents can be sealed in a box wrapped in colored tape that the witness must open on camera in the presence of opposing counsel and the tribunal immediately before testifying. Additional safeguards can be put in place by not providing cross examination bundles to opposing counsel until about 30 minutes before an examination is set to begin.
Presentation Considerations
• Displaying Documents: It is important to make sure the online platform chosen to host the video hearing includes a mechanism to display documents on the screen so all participants can see them. Most online video platforms, including Zoom, have this feature. It is helpful to pinpoint specific pages or sections of documents so that the process is as seamless as possible.
• Effective Cross Exam: The obvious difference when conducting a cross-examination via video is the loss of in-person, face-to-face contact with the witness, the tribunal, and opposing counsel. The witness should be positioned close enough to the camera to gauge facial expressions and other silent cues.
Arbitral Institution Rules
Most of the various arbitral institutions do not have rules in place specifically addressing videoconference hearings, or more generally, addressing what to do in times of local, national, or global crises.
For example, both the American Arbitration Association’s construction and commercial rules provide that an arbitrator may “allow for the presentation of evidence by alternative means including video conferencing.”
Similarly, pursuant to the JAMS arbitration rules, “[t]he Hearing, or any portion thereof, may be conducted telephonically or videographically with the agreement of the Parties or at the discretion of the Arbitrator.”
The International Institute for Conflict Prevention & Resolution is silent about videoconference hearings, providing only that unless the parties agree on the place for the arbitration, the tribunal shall decide “based upon the contentions of the parties and the circumstances of the arbitration.”
Rules promulgated by the International Chamber of Commerce , the London Court of International Arbitration, and the Singapore International Arbitration Centre provide for videoconferencing for emergency procedures. But none of these institutions appear to contemplate full merits hearings by video, much less provide specific rules for how such video hearings should proceed.
Although arbitral rules are aimed at providing individual arbitrators and parties significant control over hearing procedures, it would be helpful to have specific, consistent guidance from these institutions on how virtual hearings should be conducted.
More generally, parties would benefit from institutional guidance about how matters should proceed in the face of natural disasters or catastrophes. The Covid-19 pandemic hit the U.S. hard and fast. With many hearings already in progress, arbitrators, lawyers, and clients alike were faced with difficult decisions about whether to continue in-progress hearings in person or whether to adjourn hearings without any idea about when a live hearing could resume and no existing rules or protocols in place for continuing by video.
Although arbitrators generally have discretion to conduct a merits hearing as they see fit, explicit guidance about adjourning hearings during a global health crisis, national disaster, or other widespread catastrophe would be valuable for parties and arbitrators alike.
*This article previously appeared in Bloomberg Law.
Author Information
Jessica Sabbath is a senior attorney in King & Spalding LLP’s Trial and Global Disputes practice in Atlanta. She focuses on construction-related disputes, particularly those arising from large energy projects. She also has extensive commercial litigation experience in state and federal courts at the trial and appellate levels, as well as domestic and international arbitration experience.
Brianna E. Kostecka is a senior associate in King & Spalding’s International Arbitration practice in New York. She focuses on domestic and international litigation and arbitration of construction disputes involving large-scale projects primarily in the energy, oil and gas, and manufacturing industries. She has also represented clients in complex matters involving commercial agreements.
Saturday, February 1, 2020
Recent Decisions Clarify Statute of Repose
- What constitutes substantial completion sufficient to trigger the statute?
- To which claims does the statute apply?
Large projects often involve multiple phases. In D’Allesandro v. Lennar Hingham Holdings, LLC, 2019 WL 5550629, at *3 (D. Mass. 2019), a 150-unit condominium project in Massachusetts was completed over 24 phases. Several owners brought a suit for construction deficiencies and code violations involving the common areas of their buildings. The suit was filed two and half years after completion of the project.
The United States District Court for the District of Massachusetts agreed with plaintiff’s argument that the statute did not run from the time the architect signed off on substantial completion. Instead, it held Massachusetts’s six-year statute of repose was triggered only after the entire project was completed.
The court determined that while plaintiff’s claims for negligence and breach of implied warranty were subject to the statute, it did not apply to claims for intentional misrepresentation, negligent misrepresentation, violation of Massachusetts’ unfair business practices statute, and breach of fiduciary duty.
Ambiguity in Georgia
This case may be on its way to the Georgia Supreme Court for clarification. All parties to existing warranty agreements are watching closely to determine whether their contracts remain enforceable.
Building owners are concerned because the long-term warranties they bargained for suddenly appear in jeopardy. Contractors are apprehensive because they may no longer have the ability to incentivize construction of high-quality long-term improvements.
Contracts Covered in Ohio
The Supreme Court of Ohio confirmed the Buckeye State’s 10-year statute of repose applies to both tort and contract claims. In New Riegel Local School District Board of Education vs. Buehrer Group Architecture and Engineering, Inc.,157 Ohio St.3d 164 (Ohio 2019), the court clarified any lingering questions about the scope of the law.
In New Riegel, the Supreme Court of Ohio found the statute applies to “all causes of action,” that seek “to recover damages for bodily injury, an injury to real or personal property, or wrongful death, that arises out of a defective and unsafe condition of an improvement to real property *** against a person who performed services for the improvement to real property or a person who furnished the design, planning, supervision of construction, or construction of the improvement to real property.”
Conclusion
Regardless of how broadly these rulings are interpreted, clients contemplating claims involving improvements to real property should avoid unnecessary delay in bringing those claims. Although the broad contours of the statute of repose may seem consistent, essential details continue to be clarified in state courts.
------------------------------------
Friday, March 1, 2019
But What About My Machines Just Sitting There? Fed Court Rules Only Some Idle Equipment Costs are Allowable in a Payment Bond Claim
Thursday, January 31, 2019
Midwinter Meeting Lunch Presentation: Los Angeles Rams Stadium
Monday, January 21, 2019
Economic Loss Doctrine - New from Rhode Island
Monday, January 14, 2019
Register Now: the 2019 Midwinter Advocacy Practicum
Federal Circuit, Citing the Christian Doctrine, Holds That Performance and Payment Bonds Are Required for All Construction Contracts, Even When the Bonding Requirement Is Not Expressly Stated in the Contract
Wednesday, November 21, 2018
Contractor Submits $4.5M Claim for Differing Site Conditions, Fed Court Rejects and then Imposes Liquidated Damages for $400K
- “Due to contamination in situ and the Contractor’s excavation processes, [the Government] cannot state that excavated material will meet…requirements. The Contractor is required to meet the embankment specification regardless of the source of the embankment material.”
- “Question: Will removal and disposal of any unsatisfactory material from the existing levee embankment be paid as a separate item, as it is unknown how much material will be unsuitable for use in the new embankment? Government Response: No.”
Saturday, November 10, 2018
Ohio Supreme Court: Subcontractor Defective Work Not an "Occurence"
-------------------
Katharine Kohm, Esq. is a committee member for The Dispute Resolver. She practices construction law at Pierce Atwood, LLP in Providence, Rhode Island.