
During construction operations, the project completion date was
adjusted through the issuance of twenty change orders which were all signed by the
Board, defendant, and plaintiff as required by the general contract. One of these, a comprehensive change order issued
on February 2, 2010, addressed all issues related to claims for the final
schedule and new completion date. A
final change order that incorporated punch list and closeout items was executed
in February 2012 with submission of the final application for payment shortly
thereafter. In May of 2012, the plaintiff forwarded an extended general
condition cost request from its electrical subcontractor that was dated March
2009. At the completion of the project,
the electrical subcontractor filed suit against the plaintiff claiming, among
other items, damages related to schedule delay. The plaintiff then filed a third-party
complaint against the Board seeking indemnity and contribution for delays
caused by the Board. The plaintiff also
filed a third-party complaint against the defendant alleging that it caused a project
delay by failing to properly prepare plans and specifications which would allow
for a timely issuance of a building permit.
The Board and defendant were both granted summary judgement by the trial
court, with the plaintiff conceding it should be granted the Board due to the project
record, and the trial court finding the lack of privity of contract between the
Plaintiff and Defendant as a bar to recovery. The plaintiff appealed summary
judgement granted to the defendant.
The Court of Appeals began its analysis of the case by reviewing the tort
of negligent misrepresentation within the context of construction projects in
Kentucky. The Court found that the
Kentucky Supreme Court had already found that Restatement of
Torts § 552 negligent misrepresentation
was available to third parties to a contract because, “duty, rather than
privity, is a fundamental element under modern tort law” and a plaintiff could
recover from a defendant for an “independent duty.”
The Court then looked other jurisdictions for an architect’s duties under
§ 552. The Court
quoted Davidson& Jones, Inc. v. New Hanover Cty.,41 N.C. App. 661, 666, 255 S.E.2d 580, 583-84 (1979) when it reviewed an
architect’s duty under § 552. The Davidson court stated:
“An
architect, in the performance of his contract with his employer, is required to
exercise the ability, skill, and care customarily used by architects upon such
projects…Where breach of such contract results in foreseeable injury, economic
or otherwise, to persons so situated by their economic relations, and community
of interests as to impose a duty of due care, we know of no reason why an
architect cannot be held liable for such injury. Liability arises from the
negligent breach of a common-law duty of care flowing from the parties' working
relationship.”
Accordingly,
the Court concluded that the trial court errored when it found that the defendant
did not owe a duty outside of the purely contractual ones owed
to the Board. Since the plaintiff
claimed it reasonably and foreseeably relied upon the plans prepared by the defendant,
and those plans were negligently prepared resulting in rejection by the
approving authority, which in turn caused project delays, the Court was not in
a position to say that the Plaintiff could not prove the elements of negligent misrepresentation.
The Court
next examined the defendant’s argument that even if the plaintiff had stated a
claim for negligent misrepresentation, it cannot recover damages because of the
economic loss rule. The Court examined the evolution of the economic loss rule
in Kentucky and ultimately concluded that since the economic loss rule is a
function of contract, and there is no privity between the parties, it would not
apply to a claim under § 552. The Court
stated:
“It is the
very purpose of the tort to compensate purely economic losses when there is no
contractual remedy available but there is a breach of the duty described in [§ 552]. To apply
the rule would essentially eviscerate the tort. We agree with the Court in
Bilt-Rite, 581 Pa. at 484, 866 A.2d at 288, that the result would simply be
"nonsensical." "[I]t would allow a party to pursue an action
only to hold that, once the elements of the cause of action are shown, the
party is unable to recover for its losses."”
Finally, the
Court examined the defendant’s claim that even if the plaintiff could proceed based
on negligent representation, the claim would be barred due to all claims for
delay damages were closed with the issuance of the February 2012 change order
and the acceptance of the application for final payment. The Court did not find this argument persuasive
because the defendant was not party to the contract between the Board and
plaintiff where the waiver of claims language was located. The Court also found
that the requirement that the defendant sign all change orders “did not
constitute a contract between [the plaintiff] and the [the defendant].”
The Court
reversed the granting of summary judgment for the defendant and remanded the
case for further proceedings.
----------------------------------
The author, Brendan Carter, is a contributor to The Dispute Resolver and a former Student Division Liaison to the Forum on Construction Law. He is an attorney and a Senior Consultant with Navigant’s Global Construction Practice based in Boston, MA. He may be contacted at 617.748.8311 or brendan.carter@navigant.com
----------------------------------
The author, Brendan Carter, is a contributor to The Dispute Resolver and a former Student Division Liaison to the Forum on Construction Law. He is an attorney and a Senior Consultant with Navigant’s Global Construction Practice based in Boston, MA. He may be contacted at 617.748.8311 or brendan.carter@navigant.com
No comments:
Post a Comment