Tuesday, October 28, 2014

California General Contractors May Prospectively Waive Lien Claims

Christopher Ng recently posted an interesting article concerning the waiver of a general contractor's priority for its mechanic's lien rights through a subordination agreement with the project lender under California law.

California General Contractors May Prospectively Waive Lien Claims


General contractors are often asked (or required) to subordinate their lien claims by owners and lenders before commencing work on a construction project. It may not come as a surprise to these contractors that such a subordination agreement may be enforceable in most states. In California, however, where the mechanics lien is a constitutional right under the California Constitution, the question of enforceability of such a subordination agreement against a general contractor was not as certain.

In Moorefield Construction, Inc. v. Intervest-Mortgage Investment Company (September 30, 2014), the California Court of Appeals held that, despite the constitutional protection and priority rights accorded to mechanics liens, a general contractor could waive its mechanics lien rights through a subordination agreement with a construction lender.

[...]

No comments:

Post a Comment