Articles on Construction Litigation & Dispute Resolution by Division 1 of the ABA Forum on Construction Law
Wednesday, September 23, 2015
Attend D1's Lunch Program at the Fall Meeting: Technology Is Making Things Better, Right? A Litigator's Guide to Thriving in the Digital Age
To submit questions/topics in advance of the lunch presentation, please contact the Moderator or Panelists at the email addresses listed above. See you on October 8 at the #ADRSummit. #ABAConstruct #FCLAustin
Wednesday, September 9, 2015
Cross-Post From Division 12: Massachusetts Decision Limits Spearin Doctrine in CM-at-Risk Contracts on Public Projects
Below is the link to a post from our colleagues over at Division 12 regarding the September 2, 2015, decision of the Massachusetts Supreme Court in Coghlin Electrical Contractors, Inc. v. Gilbane Building Company, et al., SJC Docket No. SJC-11778.
http://abaconstructionforumdivision12.blogspot.com/2015/09/massachusetts-decision-limits-spearin.html
http://abaconstructionforumdivision12.blogspot.com/2015/09/massachusetts-decision-limits-spearin.html
* * *
On September 2, 2015, the Massachusetts Supreme Judicial
Court issued a long-awaited opinion in Coghlin Electrical Contractors, Inc. v. Gilbane Building
Company et al., SJC Docket No. SJC-11778. Among other issues
decided in the case, the Court held that the scope of a public-awarding
authority's implied warranty of adequacy and sufficiency of the plans and
specifications is more limited in the context of a
construction-management-at-risk contract than a traditional design-bid-build
contract.
This case represents the first time that the highest court
in Massachusetts has looked at the Spearin Doctrine in the context of the
CM-at-Risk delivery method under the state's relatively
new CM-at-Risk statute (M.G.L. c. 149A, Sections 1-13). Under this law,
public awarding authorities are permitted to retain construction managers early
during the project's design phase in order to involve them in project planning
and design development.
In Coughlin, the Court recognized the
relationship between the awarding authority and a construction manager at risk
is different from the traditional relationship in the design-bid-build context,
insomuch as a construction manager may be engaged to participate extensively in
the design phase and, therefore, has an opportunity to influence the final
plans and specifications. However, despite several noted differences
between CM-at-Risk and design-bid-build delivery, the Court was not persuaded
that the implied warranty should not apply. In construing the relevant
statutory language, the Court determined that "the legislative intent in
providing the construction management at risk alternative [to design-bid-build]
was to permit the [construction manager at risk] a greater consultative role
regarding the project's design, not to eliminate the owner's responsibility for
design defects." The Court concluded that the proper scope of
the implied warranty in the CM-at-Risk context should be limited to
instances where the construction manager acts in good faith and acts reasonably
in light of its design responsibilities. Therefore, on projects where the
construction manager's design responsibilities are greater, the construction
manager will have a higher burden to show that its reliance on the defective
design was reasonable.
Links to more information regarding this case, including the
text of the opinion, all appellate and amicus briefs, as well as video of the
oral argument, are below.
Wednesday, September 2, 2015
A Texas Hill Country Barbecue!
Do you like Barbecue?
Have you ever eaten Texas Barbecue?
If you like barbecue and you are coming to the ABA Forum on Construction Law's ADR Summit in Austin, Texas, then you need to come early enough to join Divisions 1 and 13 for some of the best barbecue Texas has to offer -- the world-renowned THE SALT LICK. Details are below.
This is expected to sell out quickly, so get in touch with Lisa Sumner Heard now to reserve your seat and find out where to send your money.
Thursday, August 27, 2015
Appeal of Arbitration -- answers to many "what if" scenarios will be provided
As part of the first day in at the Forum's #ADRSummit in Austin, John Bulman and Ben Wheatley
are offering a practical (and hopefully interactive) workshop on the
intersection between arbitration and appeals. Both Ben and John are
experienced construction attorneys and American Arbitration Association (AAA)
arbitrators. John was also a Board Member of the AAA for twelve years, is
currently a member of the Board of Governors of the American College of
Construction Lawyers (ACCL), and a fellow of the College of Commercial Arbitrators (CCA) -- all co-sponsors of the #ADRSummit.
During their hour discussion, Ben and John will consider many of
the burning “what if” questions that can arise in the context of appellate
arbitration and appealing an arbitrator’s decision to a court. Some of
the highlights include “what if the institutional provider appoints an
arbitrator that lacks necessary industry experience in the subject of the
claims?” and “what if a court stays your litigation pending arbitration but
applies the blue pencil approach to rewrite your arbitration agreement?”
John and Ben also will touch upon the “hidden appeal,” the availability of
discovery in a vacatur action, and whether manifest disregard is still viable
or past its prime.
If you haven't registered for the Fall Meeting yet, #FCLAustin, do so before August 31st to take advantage of the early bird pricing. Register here: http://bit.ly/1TodsIK.
Tuesday, August 25, 2015
The Construction ADR Summit, Plenary 6: In Defense of Lying
Is it ethical to lie in a mediation? Or, more to the point, how far should deceit or puffery really go?
Maybe the question should be how much truth must a party tell during a mediation. In fairness, most attorneys expect gamesmanship when they go to a mediation.
But, does the mediator have any ethical rules to follow?
Imagine the following scenario: you are a mediator trying to get a case settled. The case involves a lien that was filed in your state. After a brief review of the parties' mediation statements and document submissions, it becomes pretty clear to you that the party filing the lien has a fairly clear defect in its lien filing that makes it invalid.
When you get to the mediation, the parties make their initial presentations. You start in caucus with the owner to gauge the owner's interest in putting money on the table despite what seems to be the obviously invalid lien.
To your surprise, however, the project owner and its counsel apparently do not realize the problem with the lien's validity. In your first caucus session, the owner's representative says to you in confidence, "I think we have some problems here, and we need to settle this today."
As the mediator, do you say anything to the Owner about what appears to be the invalidity of the lien? Do you have any responsibility to say anything?
Former Division 1 chair Buzz Tarlow of Tarlow & Stonecipher, PLLC, in Bozeman, Montana, and Charles M. Sink of Farella, Braun + Martel LLP in San Francisco, California, will be discussing this issue, among others, in the final session of the Construction ADR Summit in Austin, Texas.
Buzz was kind enough to take a few minutes to talk to me about this presentation. He pointed out to me that, to date, neither he nor Mr. Sink have found a single reported case anywhere in the United States in which a mediator was found to have committed an ethical violation based on their conduct during the mediation.
Indeed, is there even a body of law or rules spelling out the ethics a mediator must follow? Do we as lawyers and advocates even want rules for mediators?
These topics -- and a discussion of the theory called consensual deception -- will feature prominently in the final Plenary session in Austin, as will the ability to obtain ethics CLE credit.
Maybe the question should be how much truth must a party tell during a mediation. In fairness, most attorneys expect gamesmanship when they go to a mediation.
But, does the mediator have any ethical rules to follow?
Imagine the following scenario: you are a mediator trying to get a case settled. The case involves a lien that was filed in your state. After a brief review of the parties' mediation statements and document submissions, it becomes pretty clear to you that the party filing the lien has a fairly clear defect in its lien filing that makes it invalid.
When you get to the mediation, the parties make their initial presentations. You start in caucus with the owner to gauge the owner's interest in putting money on the table despite what seems to be the obviously invalid lien.
To your surprise, however, the project owner and its counsel apparently do not realize the problem with the lien's validity. In your first caucus session, the owner's representative says to you in confidence, "I think we have some problems here, and we need to settle this today."
As the mediator, do you say anything to the Owner about what appears to be the invalidity of the lien? Do you have any responsibility to say anything?
Former Division 1 chair Buzz Tarlow of Tarlow & Stonecipher, PLLC, in Bozeman, Montana, and Charles M. Sink of Farella, Braun + Martel LLP in San Francisco, California, will be discussing this issue, among others, in the final session of the Construction ADR Summit in Austin, Texas.
Buzz was kind enough to take a few minutes to talk to me about this presentation. He pointed out to me that, to date, neither he nor Mr. Sink have found a single reported case anywhere in the United States in which a mediator was found to have committed an ethical violation based on their conduct during the mediation.
Indeed, is there even a body of law or rules spelling out the ethics a mediator must follow? Do we as lawyers and advocates even want rules for mediators?
These topics -- and a discussion of the theory called consensual deception -- will feature prominently in the final Plenary session in Austin, as will the ability to obtain ethics CLE credit.
Monday, August 24, 2015
Forum ADR Summit, Plenary V: The View from the Tower: New Perspectives on ADR
In my post a few weeks ago, I urged young construction lawyers to attend the upcoming Forum Construction Law ADR Summit on October 8-9, 2015, in Austin, Texas because young lawyers have unique ideas, experiences, and perspectives regarding practicality, reasonableness, and cost-effectiveness that will undoubtedly shape ADR’s future.
Plenary V at the Summit will provide additional insight from the best and brightest in academia. Tom Stipanowich, Acadamic Director of Pepperdine University School of Law’s Straus Institute for Dispute Resolution, will present compelling new data on ADR trends: What does the industry expect from ADR? Has ADR delivered on its promise? How will the recent past shape the future?
Next, Stan Sklar, Executive Director of DePaul University College of Law’s Center for Dispute Resolution, will discuss the unique nature of arbitration, how lawyers have hijacked the process and eroded its effectiveness, and how to debunk arbitration myths to get it back.
Finally, Dean Thompson will present up-to-date nationwide survey data from arbitrators on their general preferences and the application of the most commonly used arbitration rules.
Wednesday, August 19, 2015
Discounted Early Bird Pricing for the Forum's Fall Meeting #ADRSummit (10/8-9) Ends August 31, 2015
Register today: http://bit.ly/1TodsIK
Brochure:http://www.americanbar.org/content/dam/aba/administrative/construction_industry/Fall%202015/cifall-brochure-fall_Online.authcheckdam.pdf
Join the best construction lawyers in the land at the Forum's Fall Meeting for the Construction ADR Summit in Austin, Texas on October 8 - 9, 2015.
This program will convene renowned practitioners, top service providers, leading academics, and major stakeholders in Construction ADR for an in-depth look at the past, present and future of ADR in the construction industry.
The program also features:
• Accommodations at the Hilton Austin in downtown Austin, Texas;
• Convenient access to Austin's famed Sixth Street music scene, the University of Texas, the LBJ Presidential Library, and other highlights of the capital of Texas; and
• Opportunity to attend the Austin City Limits Music Festival, one of the largest music festivals in the country, occurring on the weekends before and after the meeting.
While the program will offer much for the construction advocate, it will also appeal to both transactional lawyers and current or aspiring neutrals.
This program is co-sponsored by over a dozen ADR industry participants. Stay in touch with announcements and updates with the Forum's application and on social media (@ABAConstruction, #FCLAustin).
Brochure:http://www.americanbar.org/content/dam/aba/administrative/construction_industry/Fall%202015/cifall-brochure-fall_Online.authcheckdam.pdf
Join the best construction lawyers in the land at the Forum's Fall Meeting for the Construction ADR Summit in Austin, Texas on October 8 - 9, 2015.
This program will convene renowned practitioners, top service providers, leading academics, and major stakeholders in Construction ADR for an in-depth look at the past, present and future of ADR in the construction industry.
The program also features:
• Accommodations at the Hilton Austin in downtown Austin, Texas;
• Convenient access to Austin's famed Sixth Street music scene, the University of Texas, the LBJ Presidential Library, and other highlights of the capital of Texas; and
• Opportunity to attend the Austin City Limits Music Festival, one of the largest music festivals in the country, occurring on the weekends before and after the meeting.
While the program will offer much for the construction advocate, it will also appeal to both transactional lawyers and current or aspiring neutrals.
This program is co-sponsored by over a dozen ADR industry participants. Stay in touch with announcements and updates with the Forum's application and on social media (@ABAConstruction, #FCLAustin).
Thursday, August 13, 2015
The Masked Attorney Unveiled: Full Disclosure Required for Ghostwriting Pleadings in Rhode Island
The carpenter calls back saying that he just needs the lien paperwork filled out and he will handle all the filings including filing the action in Court.
He says "I don't want you to appear for me, I don't need an attorney to talk for me, I don't need a mask. I do want the mechanic's lien paperwork done per the statute, which frankly I don't understand."
Can you do what the client is asking under the applicable civil rules of procedure and rules of professional responsibility?
The issue of attorney ghostwriting for pro se litigants was recently decided by the Rhode Island Supreme Court in FIA Card Services, N.A. v. Pichette, Nos. 2012-272-Appeal, 2013-156-Appeal, 2013-157-Appeal (R.I. June 8, 2015). The Court consolidated three cases where three different attorneys had been sanctioned by the trial court for ghostwriting pro se litigants' pleadings. There were two issues considered by the Supreme Court:
- "[W]hether an attorney who engages in ghostwriting -- providing drafting assistance to a pro se litigant without disclosing his or her identity to the court either by signing the pleading or entering his or her appearance -- violates Rule 11." FIA Card Services, at *12.
- "[W]hether 'ghostwriting' is permitted under Article V, Rule 1.2(c) of the Supreme Court Rules of Professional Conduct [which expressly permits limited scope representation]."
Following a line of federal court cases that condemn ghostwriting as a violation of Rule 11, the Trial Court issued sanctions against two of the attorney appellants because such conduct violated the purpose of the rule. Construing the language of Rhode Island Superior Court Rule of Procedure, Rule 11 (based off of the 1983 version of Fed. R. Civ. P. R. 11), one of the hearing justices wrote:
While this language might be read to suggest that a non-signing attorney cannot be sanctioned under Rule 11, the [c]ourt finds that this reading runs contrary to the clear intent of Rule 11, which is to enforce an attorney's ethical obligations of candor and honesty in interactions with the tribunal.FIA Card Services, at *14. While the Supreme Court agreed with the policy findings of the trial justice, it disagreed with the "expansive interpretation of Rule 11 in the ghostwriting context." FIA Card Services, at *14. The Court explained:
[T]he linchpin of Rule 11 is its signature requirement. This signature provides the vehicle through which courts may reach attorneys or litigants to impose sanctions, if necessary, for misconduct in the submission of signed papers during the litigation process.FIA Card Services, at *14. Thus, because each of the appellant attorneys did not sign the pleadings presented by the pro se litigants, the Supreme Court vacated the Rule 11 sanctions issued against the three attorneys.
Undisclosed Ghostwriting Is Prohibited In RI (but check your state)
Limited attorney client engagements are permitted in Rhode Island by Rule of Professional Conduct Rule 1.2(c). Mirrored after the ABA's Model Rules of Professional Conduct, Rule 1.2(c) "allows that '[a] lawyer may limit the scope of the representation if the limitation is reasonable under the circumstances and the client gives informed consent.'" FIA Card Services, at *19.
The Court engaged in a thoughtful analysis of whether an attorney providing ghostwriting services is dishonest (MRCP R. 8.2) and/or violates the duty of candor to the tribunal/opposing party. It cited repeatedly the ABA's Formal Opinion 07-446, Undisclosed Legal Assistance to Pro Se Litigants (May 5, 2007), which surveyed different jurisdictions and concluded "that there is no prohibition in the Model Rules of Professional Conduct against undisclosed assistance to pro se litigants, as long as the lawyer does not do so in a manner that violates rules that otherwise would apply to the lawyer's conduct." ABA Formal Opinion 07-446, p. 4.
The Court noted different paths taken by jurisdictions:
- California: Permits complete nondisclosure of attorney assistance. FIA Card Services, at *20, citing Cal. Rules of Court Title 3, chapter 3, Rules 3.35, 3.37.
- Massachusetts, New Hampshire, Connecticut: Requires a written disclosure in a pleading that legal assistance was provided in the preparation of the document, but permits anonymity. FIA Card Services, at *20, citing Mass. Sup. Jud. Ct., Order In Re: Limited Assistance Representation (2009). [Note that these are the bordering states of Rhode Island.]
- Colorado: Requires the attorney's name assisting with the drafting to be disclosed on the document. FIA Card Services, at *20, citing Colo. R. Prof. Cond. 1.2; Colo. R. Civ. P. 11(b).
- An attorney may provide legal assistance to litigants appearing pro se before courts, provided the scope of the attorney's representation is reasonable and the litigant gives informed consent. See Rule 1.2(c).
- Such consent shall be in writing and shall set forth the nature and extent of the attorney-client relationship.
- An attorney, however, shall not assist a pro se litigant with the preparation of pleadings, motions, or other written submissions unless the attorney signs the document and discloses thereon his or her identity and the nature and extent of the assistance that he or she is providing to the tribunal and to all parties to the litigation.
- The attorney shall also indicate on the written document, if applicable, that his or her signature does not constitute an entry of appearance."
Conclusion
The answer to the initial questions raised in the scenario above, of course, is "it depends." What if you are in a state that has not decided the issue? While the Rhode Island Supreme Court heavily cited the ABA Formal Opinion, it chose not to follow it.
As demand increases to grow for limited-scope or "un-bundled" representation, these issues should become more uniform across state-lines. Until then, it is particularly important to consult the rules of each state in which you practice before agreeing to be the man or woman behind the mask.
-----
The author, Tom Dunn, is one of The Dispute Resolver's Co-Editors. Tom practices construction law and complex business litigation in Rhode Island and Massachusetts. He is a partner at Pierce Atwood, LLP. He also serves on the Steering Committee for Division 1 of the Forum on Construction Law, the Associate Editor of Under Construction, the Forum on Construction Law's newsletter, and is involved in the Forum's Publications and Membership Committees. Tom can be contacted at 401-490-3418 or rtdunn@PierceAtwood.com.
Monday, July 27, 2015
YOUNG CONSTRUCTION LAWYERS: THE FORUM’S CONSTRUCTION LAW ADR SUMMIT NEEDS YOUR IDEAS AND PARTICIPATION
We have all seen the recent articles and the blogs
reflecting that clients are yearning for more planned, thoughtful, holistic approaches
to dispute resolution. As construction litigators, I like to think we are a bit
ahead of the curve because we have always attempted to resolve disputes in the
same planned and thoughtful ways our clients approach their projects -
particularly, with the key objective to collaborate with our clients, opposing
parties, and opposing counsel to resolve construction disputes in the most
beneficial, efficient, and cost-effective manner. ADR offers several opportunities
and tools toward that goal. The Forum’s Construction Law ADR Summit on October
7-9, 2015, in Austin, Texas, offers a unique opportunity for like-minded
professionals from multiple disciplines to discuss their viewpoints and
appreciate the viewpoints of others to advance the ball together to define and
sculpt how ADR will serve construction attorneys and their various clients.
We often fail to recognize that, even before receiving
mentoring from seasoned construction lawyers, “younger” construction attorneys
and professionals (e.g., “millennials”) share our collective goal of efficient
and reasonable dispute resolution, so we should encourage them to transfer
their insights across the generational gaps that sometimes hinder collaborative
progress. On Wednesday, October 7, from
2 p.m. to 5 p.m., the Summit will include a Young Lawyers Construction
Practicum regarding advocacy in mediation. If you work with young lawyers,
please encourage them to attend. And if you are a young lawyer, we encourage
you to attend not only the Practicum, but the entire Summit, to sharpen your
own skills to better serve your clients but also to provide your unique ideas,
experiences, and perspectives to help develop and identify the practical,
reasonable, and cost-effective tools and ideas that will shape ADR in the
future.
For more information about the Young Lawyers Construction
Practicum and the program generally, here is the
link to the Forum’s Construction Law ADR Summit Brochure.
Tuesday, July 21, 2015
Please Take This Survey About Email -- Results Presented During D1 Lunch in Austin, TX
http://svy.mk/1MFUpWk
Division 1's Lunch Program at the Fall Meeting in Austin, Texas (10/8/2015) will focus on technology and the practice of construction law.
One aspect of the program will be about law practice management -- specifically email.
How do Division 1 members manage/process/preserve their emails? Do we have it under control? Or, are we overwhelmed by email?
From avoiding losses in productivity to preservation/safely securing client communications, we will have an open dialogue regarding strategies that that we will be able to employ when we get back home from the meeting to reduce the stress involved with email.
Please take this 10-question survey - http://svy.mk/1MFUpWk.
If I receive sufficient number of responses, we will share the results at our lunch meeting in Austin.
Thanks for your assistance and looking forward to seeing everyone in Austin!
Tom Dunn
Division 1 Steering Committee Member
Monday, July 20, 2015
CLE Tip: The ABA's Free CLE Series
Why be a member of the ABA? What value comes from it?
Not all members of the Forum on Construction Law or Division 1 are able to be active members. For these members, the above questions may arise from time to time, why be a member of the ABA? Sometimes these questions may be asked by your law firm management.
One answer is the Free CLE series provided by ABA.
I (Tom Dunn) regularly attend these free CLEs. While they are often on topics outside of my litigation / construction law practice, I find them well done and I ultimately come away with some good information. I tend to sign-up for them upon receipt of the announcement email. If I can participate, great! If not, there is no loss.
One of these free CLEs is scheduled for this afternoon at 1PM. It is on Driverless Cars in the Fast Lane: Legality, Safety, and Liability on the Road Ahead. At the very least, I am sure I will come away from this webinar with some interesting networking talking points.
Next month's Free CLE is Representing Clients in Mediation: A Master Class in Mediation Advocacy. This topic fits squarely within Division 1's focus on advocacy.
So . . . the next time you (or your firm) think you are not getting enough out of the ABA, consider attending these Free CLEs which could get you up to 18 CLE credits each year!
Friday, July 17, 2015
ADR Tip: Voiding "Sham" Arbitration Agreements
ADR Tip -- If a client presents you with an arbitration clause that identifies rules or an administrator that are unknown or unfamiliar, the arbitration agreement could be void.
Check out the article written by P. Jean Baker, Young Lawyers: Recognizing "Sham" Agreements to Arbitrate, for the ABA Section of Litigation's Alternative Dispute Resolution's E-Newsletter.
Ms. Baker describes two cases that refused to enforce arbitration agreements contained within high interest loan transactions which specified that disputes "shall be conducted by the Cheyenne River Sioux Tribal Nation by an authorized representative in accordance with its consumer dispute rules." Inetianbor v. CashCall, Inc., 768 F.3d 1346 (11th Cir. 2014), cert. denied (S. Ct. Apr. 6, 2015); Jackson v. Payday Financial, LLC, 764 F.3d 765 (7th Cir. 2014).
The arbitration agreements were not enforced because there were lack of arbitration rules and procedures in place to conduct a fair arbitration process.
The link to the Article is http://apps.americanbar.org/litigation/committees/adr/articles/spring2015-0515-young-lawyers-recognizing-sham-agreements.html.
Thursday, July 16, 2015
Under Construction Newsletter -- Call for Construction Law Articles
Last month, I was asked to serve as the Associate Editor of the Forum on Construction Law's newsletter, Under Construction. I had the confidence to apply for the position because of the work I have done on The Dispute Resolver in collaboration with our co-editors. I am excited to introduce some of the experiments of The Dispute Resolver to Under Construction. I want feedback from Division 1 members and Forum members on what you all would like to see in Under Construction and how The Dispute Resolver (and other division publications) could collaborate with Under Construction.
As always, fabulous and interesting content is essential to any publication. I sent out the email below to a number of my friends from the Forum and construction law colleagues soliciting input and articles.
If you want to be published or know an attorney (or summer associate) in your office that is interested in a publication opportunity, please share this invitation.
Thanks for getting involved and contributing to Division 1 and the Forum on Construction Law!
Tom Dunn, rtdunn@PierceAtwood.com
Friends and Colleagues:
With my recent
post as Associate Editor of Under
Construction (ABA Forum
on Construction Law’s newsletter), one of my jobs is to seek out
interesting construction law articles along with Under Construction’s Editor,
Jayne Czik.
Consider
submitting an article for consideration. The cool thing is that Under
Construction is going back to paper (while also keeping an online
component) so it is a great opportunity to be published and speak directly to
the Forum’s 6,000+ members. We are also increasing our use of the Forum’s
social media accounts (LinkedIn,
Facebook, Twitter) to further distribute #ABAUnderConstruction
articles. The more Forum members engage in the Forum’s social media
pages, the more we will be able to send out the Forum’s message so make sure to
join the Forum’s LinkedIn
groups, like the Forum’s page on Facebook, and follow the
Forum on Twitter.
If you are
interested in submitting an article or have an article ready to submit, please
email Jayne and myself. We are looking for articles around 1500 words
(although we have not yet finalized the paper design) that provide a practical
approach/guidance to issues impacting the practice of construction law.
Click here
for the rules and procedures for submissions.
If you are
not familiar with the newsletter, look at the most recent online edition: http://www.americanbar.org/publications/under_construction/2015/july2015.html.
In addition
to articles, we are looking for innovative / creative ideas that feature the
best attributes of the Forum’s membership such as member features /
construction project features / case recaps (war story case studies, lessons
learned). Something with interesting graphics or photos. Let us
know if you have any ideas for this type of submission.
Please spread
the word that Under Construction is accepting articles to your Divisions, Forum
friends, and construction colleagues.
Even if we
are not able to use your submission for Under Construction, we will likely find
a home for your article/topic with other Forum publications such as The
Construction Lawyer, The Dispute Resolver
(Division 1’s Blog), The Owner’s
Authority (Division 12’s Blog), The Division 4 Triclinium,
Division 7’s newsletter, Division 10’s newsletter, Forum’s social media pages,
concepts book, etc.
Thank you and
we look forward to reading/editing/publishing your articles!
Tom Dunn
Associate
Editor, Under Construction
Tuesday, July 7, 2015
How New AAA Construction Arbitration Rules and Mediation Procedures Are Enacted
As you may
have heard, on July 1, 2015, the American Arbitration Association announced the
release of updated Construction Arbitration Rules. Briefly, those changes include:
- an automatic referral to mediation for all cases with claims exceeding $100,000 (though each party has the ability to opt out of this process);
- time limits and additional filing requirements for consolidation and joinder to limit the use of these time-consuming processes to delay proceedings;
- increased arbitrator control over the exchange of information, particularly electronic documents;
- new preliminary hearing rules providing detailed guidance to all involved parties and arbitrators as to what issues should be considered at the preliminary hearing;
- emergency relief rules for contracts entered on or after July 1, 2015, to appoint an emergency arbitrator within one day of filing the demand for emergency relief; and,
- additional authority for arbitrators to respond to parties refusing to comply with the Rules and/or the arbitrator’s orders.
To read more about these rule changes, go to the Construction
Industry Arbitration Rules and Mediation Procedures page on the AAA's website.
I had the opportunity to speak with John Bulman of
Pierce Atwood LLP about these rule changes. John has been a construction lawyer
for over twenty-five years and, in that time, has served frequently as a
mediator and arbitrator through the AAA.
He is a past member of the AAA Board and has been involved in the AAA
rulemaking process for over a decade.
For this most recent revision of the rules, John served as
the American College of Construction Lawyers liaison to the National
Construction Dispute Resolution Committee (NCDRC), an organization founded
in 1966 by the AAA and other industry and trade organizations. Currently, thirty different industry
organizations including the Forum are represented in the NCDRC. It is tasked with analyzing proposed rule
changes to the AAA Construction Arbitration Rules in addition to creating and
providing input on program content and faculty for proposed neutral training
and in recruiting qualified neutrals.
The way that rules are changed involves a multi-year
process. The AAA is always gathering
comments, feedback, objections, and insight about the rules. On a periodic basis, the AAA will consider
whether to revise its commercial arbitration rules or one of the industry
specific rule sets. In addition, the NCDRC intermittently provides its own
comments or proposals for possible rule changes.
With respect to this particular set of changes, the rule
changes were adopted previously by the AAA for the Commercial Arbitration
Rules. From there, the NCDRC was tasked
with determining whether to adopt similar rules for the Construction Industry.
In making this determination, the AAA Vice Presidents held eighteen different
focus groups across the country to discuss the rule changes and seek
input.
After receiving input from these
focus groups and incorporating comments accordingly, the NCDRC developed and
vetted the rules in December of 2014. From
there, the Chair of the AAA’s Practice Committee reviewed and approved the
changes. Once that approval was received, the AAA’s senior counsel and staff
review the rules to ensure that they are acceptable and consistent with AAA
policies and procedures. After that, the
rules were released to the public.
With regard to the current changes, John believes that the
checklist for preliminary hearings set forth in Preliminary Hearing Procedures
Rule P-2 are extremely important in keeping a particular arbitration proceeding
on schedule. Reviewing this checklist, one can see what John means – the
checklist is attempting to bring the parties to as early an agreement as
possible regarding the key procedural issues in the case.
It combines the most important parts of an early conference
of counsel in federal court – such as dealing with ESI at the beginning of the
case – and of a pretrial conference – discussing witnesses, exhibits, the forms
of testimony to be provided, and the form of the award. As John stated to me, failing to address
these issues at the beginning of the case only leads to problems and delays
down the road.
John also highlighted how important the consolidation
provisions are. Too often, he has seen parties wait until late in the
proceedings to try to join new parties to an arbitration or to consolidate one
arbitration with another. That procedural decision causes a separate arbitrator
to be appointed to determine whether consolidation is appropriate – a “Rule 7
arbitrator” – and waiting until late in the process to seek consolidation only
serves to delay proceedings. To address
this issue, the Rules have been revised to provide a cutoff date by which the
parties must seek consolidation and still get the benefit of having a Rule 7
arbitrator appointed to determine if consolidation is appropriate. Otherwise,
if the request comes later in the process, the arbitrators called the “Merits
Arbitrators” – the panel appointed to decide the case – will make the
determination on consolidation.
As John noted, the AAA continues to seek feedback regarding its rules and any improvements that you might have. To that end, Michael A. Marra, who is a Vice President with AAA in Philadelphia, welcomes your telephone calls to discuss any rules issue you might have. He can be reached at (215) 731-6136.
As John noted, the AAA continues to seek feedback regarding its rules and any improvements that you might have. To that end, Michael A. Marra, who is a Vice President with AAA in Philadelphia, welcomes your telephone calls to discuss any rules issue you might have. He can be reached at (215) 731-6136.
Tuesday, June 30, 2015
Supreme Court of Pennsylvania Holds Contractor and Subcontractor Payment Act Inapplicable to Public Works Projects
Thomas J. Madigan, Partner, Pepper Hamilton LLP
Kristopher Berr, Associate , Pepper Hamilton LLP
Kristopher Berr, Associate
Clipper Pipe & Service,
Inc. v. The Ohio Cas. Ins. Co., 2015 Pa. LEXIS 1275 (PA June 15, 2015)
The Supreme Court of
Pennsylvania held that the Contractor and Subcontractor Payment Act (“CASPA”),
73 P.S. §§501-516, “does not apply to a construction project where the owner is
a governmental entity.” This decision
once and for all resolved the issue of whether CASPA applies to payment
disputes between prime contractors and subcontractors on public works
projects, either instead of or in addition to the prompt payment
provisions of the Commonwealth Procurement Code, 62 Pa.C.S. §§ 3931-3939 (commonly
referred to as “the Prompt Payment Act”).
The decision is in line with
what most practitioners already understood: that the Pennsylvania General
Assembly intended to establish two separate statutory payment schemes governing
public and private projects, respectively. As argued by the appellants in
Clipper, it would seem untenable that both CASPA and the Prompt Payment
Act would apply to payment disputes on public construction projects, given that
there are substantial differences in the required notice, the rate of interest
on delayed payments and the burden of proof associated with penalty and
attorneys’ fee awards under those statutes. Despite this seeming
incongruence, subcontractors on public projects who hoped to access the more
advantageous provisions of CASPA have, to this point, seized on its somewhat
imprecise definition of “owner” to argue that CASPA could be read to apply to
payment disputes between prime and subcontractors on public projects.
After Clipper, there is no longer any question that CASPA does not apply
to such disputes, which are governed exclusively by the Prompt Payment Act.
The case arose from a project
for certain improvements to the Navy/Marine Corps Reserve Training Center in
Pennsylvania’s Lehigh Valley. In furtherance of the project, the United States
Department of the Navy contracted with Contracting Systems, Inc. (“CSI”) as
general contractor. In turn, CSI subcontracted with Clipper Pipe &
Service, Inc. (“Clipper”) to perform certain heating, ventilation and air
conditioning work . Eventually, Clipper filed suit against CSI and its
surety in the United States District Court for the Eastern District of
Pennsylvania, alleging that CSI had failed to pay Clipper sums that were due
under the parties’ subcontract. Clipper further asserted a claim against
CSI under CASPA.
CSI moved for summary
judgment on Clipper’s CASPA claim, arguing that CASPA did not apply in the
context of a public works project. The District Court denied the motion
and, ultimately, Clipper prevailed on its CASPA claim after the subsequent jury
trial. CSI then appealed to the Court of Appeals for the Third
Circuit. The Third Circuit applied to the Supreme Court of Pennsylvania
for certification of a question of law: “does [CASPA] apply to a project where
the owner is a governmental entity, such as the federal government in this
case?” The Supreme Court granted certification.
At the outset of its
analysis, the Supreme Court noted that CASPA establishes rights and duties
among “owners”, “contractors”, and “subcontractors” as it relates to
“construction contracts.” To the Court, the definition of “owner” is
crucial to determining CASPA’s scope because the term “owner” is used throughout
the statute. For example, as the Court pointed out, CASPA defines
“contractor” as a “person authorized or engaged by an owner” to make certain
improvements to property. 73 P.S. § 502. Thus, unless there is an “owner”
within the meaning of CASPA, there can be no “contractor.”
Accordingly, as it relates to
a public works project, the central question was whether or not the government
could be deemed an “owner.” The Supreme Court held that it could not.
CASPA defines “owner” to mean
a “person who has an interest in the real property that is improved and who
ordered the improvement to be made.” 73 P.S. § 502. In turn,
“person” refers to a “corporation, partnership, business trust, other
association, estate, trust foundation or a natural individual.” Id.
The Court determined, under the doctrine of ejusdem generis, the government could not possibly be an “other
association” within the meaning of CASPA because the term “other association”
must take its meaning from the terms that precede it. In this case,
“other association” could not be read to encompass the government because
the government is “dissimilar to a ‘corporation,’ ‘partnership,’ ‘business
trust,’ ‘estate,’ ‘trust foundation,’ and ‘natural individual,’ among which the
term ‘association’ appears.”
The Court further observed that
“statutes in derogation of sovereignty should be construed strictly in favor of
the sovereign.” This approach is derived from the common law principle of
sovereign immunity and is further “grounded on the assumption that non-specific
statutes are most often directed to the affairs of the citizenry.”
Consequently, in the absence of express textual authority, the Court declined
to construe “association” or “owner” to refer to the government ..
After concluding that the
government is not an “owner” as that term is used in CASPA, the Supreme Court
turned to the question of whether CASPA would nonetheless apply to a dispute
between a contractor and subcontractor on a public project if the dispute did not
directly involve the government. Holding in the negative, the Court
recognized the existence of the dual statutory schemes established by CASPA and
the Prompt Payment Act, and noted that the timing and penalty provisions for
late payment under the Prompt Payment Act differed from those under
CASPA. The Court concluded that “the Legislature simply did not
design CASPA to apply independently to subcontracts in scenarios in which the
foundational contract resides outside its boundaries” (i.e., where the contract
between the owner and general contractor was governed by the Prompt Payment
Act). Thus, the Court held that, even though CASPA’s policy of protecting
contractors and subcontractors would be promoted if it were applied to the case
before it, “such application is too disharmonious with the statutory mechanics
to support the extension.”
Article originally posted June 25, 2015 on Constructlaw, an update and discussion of recent trends in construction law and construction, maintained and edited by Pepper Hamilton's Construction Law Practice Group.
Monday, June 29, 2015
What Useful Construction Litigation Data Are We Missing?
Frank Sommers’ wrote a thought-provoking article
for the recent June 2015 issue of Litigation News in which he explored the data
that civil litigants might attempt to access to prove their case, including GPS
data, Event Data Recorder (“EDR”) data, and cell tower “ping” data. At the end
of the article, he identifies now-popular home sensor technology as a possible location
of evidentiary data.
While not the primary focus of Mr. Sommers’ article, he
makes an excellent recommendation for construction lawyers. With the
proliferation of “smart” commercial building design and technology aimed at
greener and more convenient construction, maintenance, and use, what useful
data do our buildings hold for use in construction disputes? Could a Nest or
similar thermostat provide data that consultants can use to identify the cause
of moisture intrusion and mold in buildings? Do smartphones or devices that
might be installed during construction store data that can be accessed to
identify the number of workers present in a project area to track and/or defend
delay and productivity claims? By way of example, linked here
is Nest’s Privacy Statement for Nest Products and Services, which identifies
some of the data that its products collect.
We do not yet know the answers to the questions above,
but we should be asking those and similar questions to our clients and witnesses,
and perhaps even to opposing parties in formal discovery. In fact, arguments
could be made that we are obligated to inquire about, instruct our clients to
preserve, and produce such devices and their stored data in litigation. But
regardless of whether the inquiries are formal or informal, we will not know
what data is available until we know what devices are installed that might hold
that data.
Wednesday, June 24, 2015
Discovery Denied in ICC Arbitration over Panama Canal
As many people are aware, the Panama Canal expansion is one of the largest "megaprojects" going on in the world today. In January of 2014, the joint-venture contractor called GUPC (which stands for Grupo Unidos Por El Canal, S.A.) announced that cost overruns required $1.6 billion in additional money to be paid to it by the Panamanian government. Then, in December of 2014, the GUPC consortium stated that it had additional claims totaling $737 million.
Of course, in the world of the international construction lawyer, this means arbitration. GUPC filed its arbitration in December of 2013 under the International Chamber of Commerce ("ICC") rules in Miami, Florida, in accordance with the contractual dispute resolution clause. Discovery in the case is being conducted under the International Bar Association Rules on the Taking of Evidence in International Commercial Arbitration -- the IBA Rules.
In that arbitration, GUPC seeks compensation for its cost overruns and other damages from Autoridad del Canal de Panama -- the Panama Canal Authority, or ACP. ACP contracted with CH2M Hill Panama, S. de R.L., for CH2M Hill-Panama to serve as ACP's program manager for the Canal expansion.
GUPC believed that CH2M Hill-Panama would have documents necessary for its arbitration with GUPC and served a request for production of documents under 28 U.S.C. § 1782 on CH2M Hill-USA in Colorado as a result. CH2M Hill-USA refused to provide the documents.
The result of that subpoena ended up in a battle in the United States District Court for the District of Colorado. In re Application of Grupo Unidos Por El Canal, S.A., Civil Action No. 14-mc-00226-MSK-KMT (D. Colo. April 17, 2015). Bear in mind that this opinion is a magistrate's recommendation to the District Court, so this is by no means a final decision.
CH2M Hill-USA made five major arguments. First, CH2M Hill-USA argued that the ICC arbitration was not a tribunal as that term is defined under §1782. Second, CH2M Hill-USA claimed that the ICC arbitration is not a "foreign or international tribunal" as is required by § 1782. Third, CH2M Hill-USA stated that they do not have possession or control of the documents -- CH2M Hill-Panama does -- and, further, that the documents are located outside the United States. Fourth, CH2M Hill-USA argued that the subpoena was unduly burdensome and intrusive. Finally, CH2M Hill argued that the subpoena in federal court was an attempt to circumvent discovery limitations imposed in the ICC arbitration.
In the end, the magistrate agreed with CH2M Hill-USA on all of its arguments. First, the ICC arbitration was not a "tribunal" because it arose out of a private agreement to decide claims using certain rules. Even though those rules may lend the appearance of being a quasi-judicial proceeding, the court was not persuaded that voluntarily agreeing to those rules created a "tribunal" for purposes of §1782.
Second, the court held that private arbitration does not fall under the meaning of "foreign or international tribunal" under §1782. The distinction drawn is that arbitral proceedings that are the product of contractual agreements differ from state-sponsored proceedings in foreign courts. The magistrate was persuaded that enforcing the subpoena "would defeat the timeliness and cost-effectiveness of arbitration, and would place a heavy burden on the federal courts to determine discovery requests." Slip Op. at 16. Further, the magistrate was not persuaded that this was an international arbitration because it was being held in the United States, but she did not rule on the issue because it was not necessary to do so.
Third, as to the location of the documents, the magistrate cited to the fact that Congress likely meant for the reach of §1782 to apply only to evidence located inside the United States. After all, it would be outside the Court's jurisdictional reach to compel CH2M Hill-USA to produce documents physically located in Panama.
Fourth, in analyzing the burden issue on CH2M Hill-USA, the magistrate considered the factors set forth in Intel Corp. v. Advanced Micro Devices, Inc., 542 U.S. 241 (2004). Even though the magistrate was not required to reach these factors, the court noted that if the statutory requirements under §1782 had been met, she still would have denied production. Under Intel, certain discretionary factors such as burden come into play. Here, production would have required CH2M-Panama to produce 89 boxes of paper and 1.6575 terabytes of information -- which works out to approximately 80,000 boxes of documents. Thus, the magistrate held that on that fact alone, it is likely that the requests were too broad.
Finally, the magistrate agreed that the subpoena was an effort to circumvent the ICC panel's authority related to discovery. GUPC neither sought nor received approval from the arbitration panel to obtain the information requested. This fact led the magistrate to believe that the delay associated with such a "grandiose document production" would not be well received by the Panel. As such, for every reason possible -- both statutory and those within the court's discretion -- the request for the subpoena to be enforced was denied.
Of course, in the world of the international construction lawyer, this means arbitration. GUPC filed its arbitration in December of 2013 under the International Chamber of Commerce ("ICC") rules in Miami, Florida, in accordance with the contractual dispute resolution clause. Discovery in the case is being conducted under the International Bar Association Rules on the Taking of Evidence in International Commercial Arbitration -- the IBA Rules.
In that arbitration, GUPC seeks compensation for its cost overruns and other damages from Autoridad del Canal de Panama -- the Panama Canal Authority, or ACP. ACP contracted with CH2M Hill Panama, S. de R.L., for CH2M Hill-Panama to serve as ACP's program manager for the Canal expansion.
GUPC believed that CH2M Hill-Panama would have documents necessary for its arbitration with GUPC and served a request for production of documents under 28 U.S.C. § 1782 on CH2M Hill-USA in Colorado as a result. CH2M Hill-USA refused to provide the documents.
The result of that subpoena ended up in a battle in the United States District Court for the District of Colorado. In re Application of Grupo Unidos Por El Canal, S.A., Civil Action No. 14-mc-00226-MSK-KMT (D. Colo. April 17, 2015). Bear in mind that this opinion is a magistrate's recommendation to the District Court, so this is by no means a final decision.
CH2M Hill-USA made five major arguments. First, CH2M Hill-USA argued that the ICC arbitration was not a tribunal as that term is defined under §1782. Second, CH2M Hill-USA claimed that the ICC arbitration is not a "foreign or international tribunal" as is required by § 1782. Third, CH2M Hill-USA stated that they do not have possession or control of the documents -- CH2M Hill-Panama does -- and, further, that the documents are located outside the United States. Fourth, CH2M Hill-USA argued that the subpoena was unduly burdensome and intrusive. Finally, CH2M Hill argued that the subpoena in federal court was an attempt to circumvent discovery limitations imposed in the ICC arbitration.
In the end, the magistrate agreed with CH2M Hill-USA on all of its arguments. First, the ICC arbitration was not a "tribunal" because it arose out of a private agreement to decide claims using certain rules. Even though those rules may lend the appearance of being a quasi-judicial proceeding, the court was not persuaded that voluntarily agreeing to those rules created a "tribunal" for purposes of §1782.
Second, the court held that private arbitration does not fall under the meaning of "foreign or international tribunal" under §1782. The distinction drawn is that arbitral proceedings that are the product of contractual agreements differ from state-sponsored proceedings in foreign courts. The magistrate was persuaded that enforcing the subpoena "would defeat the timeliness and cost-effectiveness of arbitration, and would place a heavy burden on the federal courts to determine discovery requests." Slip Op. at 16. Further, the magistrate was not persuaded that this was an international arbitration because it was being held in the United States, but she did not rule on the issue because it was not necessary to do so.
Third, as to the location of the documents, the magistrate cited to the fact that Congress likely meant for the reach of §1782 to apply only to evidence located inside the United States. After all, it would be outside the Court's jurisdictional reach to compel CH2M Hill-USA to produce documents physically located in Panama.
Fourth, in analyzing the burden issue on CH2M Hill-USA, the magistrate considered the factors set forth in Intel Corp. v. Advanced Micro Devices, Inc., 542 U.S. 241 (2004). Even though the magistrate was not required to reach these factors, the court noted that if the statutory requirements under §1782 had been met, she still would have denied production. Under Intel, certain discretionary factors such as burden come into play. Here, production would have required CH2M-Panama to produce 89 boxes of paper and 1.6575 terabytes of information -- which works out to approximately 80,000 boxes of documents. Thus, the magistrate held that on that fact alone, it is likely that the requests were too broad.
Finally, the magistrate agreed that the subpoena was an effort to circumvent the ICC panel's authority related to discovery. GUPC neither sought nor received approval from the arbitration panel to obtain the information requested. This fact led the magistrate to believe that the delay associated with such a "grandiose document production" would not be well received by the Panel. As such, for every reason possible -- both statutory and those within the court's discretion -- the request for the subpoena to be enforced was denied.
Tuesday, June 23, 2015
Hawaii Finds Arbitration Agreement With “Severe Limitations on Discovery” is Unconscionable, By Liz Kramer*
Hawaii issued a bold arbitration decision this month. It applied its state contract law to conclude that the parties did not form a clear arbitration agreement, but even if they did, it was unconscionable because it prohibited both discovery and punitive damages. Narayan v. The Ritz-Carlton Dev. Co., Inc., __ P.3d __, 2015 WL 3539805 (Haw. June 3, 2015).
The plaintiffs purchased the first condos in a development in Kapalua Bay. The developer defaulted on loans, however, and it or its agent withdrew over a million dollars from the association’s operating fund. The plaintiffs sued for breach of fiduciary duty and other claims.
In response, the developer moved to compel arbitration. It argued that the plaintiffs’ purchase agreements incorporated the condominium declaration, which had an arbitration clause. The trial court denied the motion to compel, but the intermediate court of appeals reversed. The Hawaii Supreme Court found the intermediate court gravely erred and the plaintiffs did not have to arbitrate their claims.
Under Section 2 of the FAA, the Hawaii Supreme Court applied state law to decide whether an arbitration agreement existed and whether it was valid.
On the first question, the Hawaii Supreme Court found the parties did not form an agreement to arbitrate, because the purchase agreement was ambiguous regarding the parties’ intent to arbitrate. Notably the purchase agreements themselves did not mention arbitration and instead stated that the venue for any action shall be in Hawaii state court. The arbitration clause was only included in the separate condominium declaration. The court found “it is facially ambiguous whether those disputes would be consigned to arbitration in Honolulu pursuant to the condominium declaration or the [state court] pursuant to the purchase agreement.” The court’s analysis applied Hawaii case law that appears to create different (and higher) standards for proving the existence of an arbitration agreement than the standards required to prove other contracts. But, Hawaii avoided any FAA preemption problem by offering up a second, independent basis for its refusal to enforce the arbitration clause: unconscionability.
The court also found the arbitration agreement unconscionable under Hawaii law. It found it was procedurally unconscionable because the plaintiffs could not negotiate it, it was “buried in an auxiliary document,” and it was ambiguous. With respect to substantive unconscionability, the court focused on three provisions of the arbitration agreement. The arbitration agreement provided that the arbitrator could order the parties to exchange copies of “nonrebuttable exhibits” and witness lists, but “the arbitrator shall have no other power to order discovery or depositions unless and then only to the extent that all parties otherwise agree in writing.” The arbitration agreement also precluded parties from “disclos[ing] the facts of the underlying dispute…without prior written consent of all parties.” The Hawaii Supreme Court concluded that “if the arbitration clause were enforced as written, the [plaintiffs] would have virtually no ability to investigate their claims, and thus, would be deprived of an adequate alternative forum.” Furthermore, the arbitration agreement precluded punitive damages, which the court found “substantively unconscionable” in a contract of adhesion.
If there is a continuum of state arbitration decisions, varying from hostile to arbitration on one end to rubber-stamping of arbitration on the other end, I think Hawaii just situated itself on the very hostile end, even further than California and Missouri. But, this case offers a reminder of two important rules for drafters of arbitration clauses: make the agreement to arbitrate very clear and easy to find; and do not overreach when inserting arbitration provisions that favor your client.
------------------------
* Liz Kramer is a partner at Stinson Leonard Street LLP where she handles complex commercial disputes, often in the construction and franchise contexts. After litigating arbitrability on many occasions, Liz began blogging about arbitration law at www.arbitrationnation.com in addition to her law practice in 2011. Her blog has been recognized as one of the best in the nation by the ABA Journal for the past three years and educates thousands of lawyers each month about the Federal Arbitration Act and its interpretation.
| Kapalua Bay Beach |
In response, the developer moved to compel arbitration. It argued that the plaintiffs’ purchase agreements incorporated the condominium declaration, which had an arbitration clause. The trial court denied the motion to compel, but the intermediate court of appeals reversed. The Hawaii Supreme Court found the intermediate court gravely erred and the plaintiffs did not have to arbitrate their claims.
Under Section 2 of the FAA, the Hawaii Supreme Court applied state law to decide whether an arbitration agreement existed and whether it was valid.
On the first question, the Hawaii Supreme Court found the parties did not form an agreement to arbitrate, because the purchase agreement was ambiguous regarding the parties’ intent to arbitrate. Notably the purchase agreements themselves did not mention arbitration and instead stated that the venue for any action shall be in Hawaii state court. The arbitration clause was only included in the separate condominium declaration. The court found “it is facially ambiguous whether those disputes would be consigned to arbitration in Honolulu pursuant to the condominium declaration or the [state court] pursuant to the purchase agreement.” The court’s analysis applied Hawaii case law that appears to create different (and higher) standards for proving the existence of an arbitration agreement than the standards required to prove other contracts. But, Hawaii avoided any FAA preemption problem by offering up a second, independent basis for its refusal to enforce the arbitration clause: unconscionability.
The court also found the arbitration agreement unconscionable under Hawaii law. It found it was procedurally unconscionable because the plaintiffs could not negotiate it, it was “buried in an auxiliary document,” and it was ambiguous. With respect to substantive unconscionability, the court focused on three provisions of the arbitration agreement. The arbitration agreement provided that the arbitrator could order the parties to exchange copies of “nonrebuttable exhibits” and witness lists, but “the arbitrator shall have no other power to order discovery or depositions unless and then only to the extent that all parties otherwise agree in writing.” The arbitration agreement also precluded parties from “disclos[ing] the facts of the underlying dispute…without prior written consent of all parties.” The Hawaii Supreme Court concluded that “if the arbitration clause were enforced as written, the [plaintiffs] would have virtually no ability to investigate their claims, and thus, would be deprived of an adequate alternative forum.” Furthermore, the arbitration agreement precluded punitive damages, which the court found “substantively unconscionable” in a contract of adhesion.
If there is a continuum of state arbitration decisions, varying from hostile to arbitration on one end to rubber-stamping of arbitration on the other end, I think Hawaii just situated itself on the very hostile end, even further than California and Missouri. But, this case offers a reminder of two important rules for drafters of arbitration clauses: make the agreement to arbitrate very clear and easy to find; and do not overreach when inserting arbitration provisions that favor your client.
------------------------
* Liz Kramer is a partner at Stinson Leonard Street LLP where she handles complex commercial disputes, often in the construction and franchise contexts. After litigating arbitrability on many occasions, Liz began blogging about arbitration law at www.arbitrationnation.com in addition to her law practice in 2011. Her blog has been recognized as one of the best in the nation by the ABA Journal for the past three years and educates thousands of lawyers each month about the Federal Arbitration Act and its interpretation.
Monday, June 22, 2015
Sub Wins Against Owner -- It Was A Strategic Decision Not To Sue The GC
In South County Post & Beam, Inc. v. Brian T. McMahon, et al. ("McMahon"), the Rhode Island Supreme Court affirmed an "unjust enrichment" claim by a subcontractor against an owner. The case is a cautionary tale for owners and will likely become a frequently cited case for subcontractors seeking multiple avenues for payment.
To avoid a "surprise" unjust enrichment cause of action by subcontractors, and particularly following this case, some takeaways for owners include:
Contractors, whether a general contractor or a subcontractor, who deal with difficult owners could possibly lay the groundwork for such a quasi contract claim by engaging in these activities and direct owner/subcontractor communications. The case creates precedent for the proposition that it is not necessarily inequitable for a general contractor and a subcontractor to purposefully collaborate to avoid lawsuits between themselves so that the sub/general business relationship remains strong.
The Facts: A family buys undeveloped property on Block Island, Rhode Island with the intention to build a house. Family hires general contractor. General contractor hires a roofing subcontractor. During construction, the family decides to build a "barn" for their children and, later on, a roof deck on the house. No change order was issued for the roof deck. Subcontractor received three payments -- one of which was a direct payment from the family (at the request of the general contractor). There was also some email correspondence between subcontractor and the family regarding subcontractor's billings.
Lawsuit Against the Family: Subcontractor sued family for breach of contract (express and implied) and unjust enrichment. Subcontractor did not sue general contractor because it did not want to disrupt the existing business relationship. (The family didn't file a third party indemnification claim against the general contractor.)
Contract Cause of Action -- Family Wins: Trial Justice found there was no express or implied contract, and therefore, entered judgment for the family.
Unjust Enrichment -- Subcontractor Wins: Despite the absence of a contract and the subcontractor's strategic decision not to sue the general contractor, the Trial Justice found that it was equitable to enter judgment for subcontractor against the family on the unjust enrichment claim.
On appeal, the Rhode Island Supreme Court first set forth the elements of a claim for unjust enrichment:
The Supreme Court framed the issue as "whether [the family] would be unjustly enriched if they did not have to compensate [subcontractor] for the value of the services rendered, and not whether it would actually be proper for [the family] to retain the benefit of plaintiff's work on their new house and barn." McMahon, at *10. Despite precedent stating that "'[s]imply conferring a benefit upon a landowner by a subcontractor is not sufficient to establish a claim for unjust enrichment[,]" McMahon, at *11, quoting Emond Plumbing & Heating, Inc. v. BankNewport, 105 A.3d 85, 90 (R.I. 2014), the Court "balanced the equities" to determine whether subcontractor could recover directly from the family. The following were the facts considered by the Court:
Facts Weighing Against A Claim For Unjust Enrichment
Facts Weighing In Favor Of A Claim Of Unjust Enrichment
To avoid a "surprise" unjust enrichment cause of action by subcontractors, and particularly following this case, some takeaways for owners include:
- Do communicate solely through your general contractor.
- Don't issue direct payment to subcontractors as a courtesy to the general contractor.
- Don't negotiate directly with subcontractors regarding billing/commercial terms.
- **Be careful about direct email communications with subcontractors**
Contractors, whether a general contractor or a subcontractor, who deal with difficult owners could possibly lay the groundwork for such a quasi contract claim by engaging in these activities and direct owner/subcontractor communications. The case creates precedent for the proposition that it is not necessarily inequitable for a general contractor and a subcontractor to purposefully collaborate to avoid lawsuits between themselves so that the sub/general business relationship remains strong.
The Facts: A family buys undeveloped property on Block Island, Rhode Island with the intention to build a house. Family hires general contractor. General contractor hires a roofing subcontractor. During construction, the family decides to build a "barn" for their children and, later on, a roof deck on the house. No change order was issued for the roof deck. Subcontractor received three payments -- one of which was a direct payment from the family (at the request of the general contractor). There was also some email correspondence between subcontractor and the family regarding subcontractor's billings.
Lawsuit Against the Family: Subcontractor sued family for breach of contract (express and implied) and unjust enrichment. Subcontractor did not sue general contractor because it did not want to disrupt the existing business relationship. (The family didn't file a third party indemnification claim against the general contractor.)
Contract Cause of Action -- Family Wins: Trial Justice found there was no express or implied contract, and therefore, entered judgment for the family.
Unjust Enrichment -- Subcontractor Wins: Despite the absence of a contract and the subcontractor's strategic decision not to sue the general contractor, the Trial Justice found that it was equitable to enter judgment for subcontractor against the family on the unjust enrichment claim.
On appeal, the Rhode Island Supreme Court first set forth the elements of a claim for unjust enrichment:
It is well settled in our state that, '[t]o recover for unjust enrichment, a claimant must prove: (1) that he or she conferred a benefit upon the party from whom relief is sought; (2) that the recipient appreciated the benefit; and (3) that the recipient accepted the benefit under such circumstances that it would be inequitable for [the recipient] to retain the benefit without paying the value thereof.'McMahon, at *8, quoting Emond Plumbing & Heating, Inc. v. BankNewport, 105 A.3d 85, 90 (R.I. 2014) (emphasis added). Next, the Court explained that, under Rhode Island law, the causes of action for unjust enrichment and quantum meriut were essentially the same. "'While unjust enrichment focuses on the propriety of a payee or beneficiary retaining funds or a benefit, quantum meruit's primary focus is on the value of services rendered.'" McMahon, at *8, citing Process Engineers & Constructors, Inc. v.DiGregorio, 93 A.3d 1047, 1052 (R.I. 2014). (Presumably, the Court engaged in this discussion because the proof of damages related the value of the services rendered rather than the "benefit" conferred on the family by the subcontractor's work.)
The Supreme Court framed the issue as "whether [the family] would be unjustly enriched if they did not have to compensate [subcontractor] for the value of the services rendered, and not whether it would actually be proper for [the family] to retain the benefit of plaintiff's work on their new house and barn." McMahon, at *10. Despite precedent stating that "'[s]imply conferring a benefit upon a landowner by a subcontractor is not sufficient to establish a claim for unjust enrichment[,]" McMahon, at *11, quoting Emond Plumbing & Heating, Inc. v. BankNewport, 105 A.3d 85, 90 (R.I. 2014), the Court "balanced the equities" to determine whether subcontractor could recover directly from the family. The following were the facts considered by the Court:
Facts Weighing Against A Claim For Unjust Enrichment
- Existence of a Subcontract and lack of contract (even implied) with the family. This was a "factor that weigh[ed] against [subcontractor] recovering the value of its work from [the family." McMahon, at *11.
- Not pursuing recovery against General Contractor. This fact should strongly make an unjust enrichment claim against the family unsuccessful. Here, subcontractor surprisingly admitted to the Trial Justice that the subcontractor "had made a strategic decision not to include [the General Contractor] as a defendant in its civil action because it wanted to continue working with [the General Contractor] in the future." McMahon, at *12, fn. 2.
Facts Weighing In Favor Of A Claim Of Unjust Enrichment
- Family made one $60,100 payment to subcontractor. It was undisputed that this was done as a courtesy to the general contractor.
- Family and subcontractor exchanged emails. The emails dealt with the subcontractor's billings and statements.
The Court held "the trial justice was not incorrect as a matter of law in her analysis and conclusion that the third element of plaintiff's claim was met."
The family's counsel argued that this case could "render every property owner a de facto party to subcontracts executed by the general - the general and sub could substitute the homeowner as the obligor at their whim, at any time, without notice." McMahon, at *14. While recognizing this policy argument, the Court discounted it because an "unjust enrichment" claim involves a "fact-specific balancing process." McMahon, at *14. In so holding, the Court has substantially widened the "door" for such direct claims by subcontractors against owners and made it more challenging to dispose of such actions through the summary judgment process.
The Dispute Resolver editors look forward to hearing from you about this case. Please post your comments on our blog or LinkedIn Subgroup page. This case summary was prepared by Tom Dunn, a Partner at Pierce Atwood's Providence, Rhode Island office and Co-Editor of The Dispute Resolver. Tom can be reached at rtdunn@PierceAtwood.com or @rtomdunn.
Tuesday, June 2, 2015
Litigation tip: Read the Jury Instructions Before Filing Suit
So you're feeling great because you landed a new client, maybe a general contractor who builds the most expensive facilities in the world. That sounds like a good client. The client hires you to file a lawsuit against an owner who failed to pay millions of dollars in retainage at the end of a billion-dollar project. You start by digging up the last Complaint you filed for breach of contract, tweak the names, dates and dollars, and file the lawsuit. Right? Wrong.
Before filing a lawsuit, you should take a deep breath. While many of us file lawsuits frequently, they are a big deal and you want to do it right. As such, you should consider reviewing sample jury instructions and perhaps consulting a "causes of action" practice guide before you do so much as put a caption on your Complaint. Most courts have sample/pattern jury instructions, and there are countless practice guides out there that break down your potential claims.
Wait a minute, why would I start by looking at the jury instructions? Don't I just worry about them in the unlikely event my case actually goes to trial or arbitration? NO. Jury instructions will guide you to the claims which might apply to your dispute. For example, your review of the jury instructions might make you realize the strength of additional claims to be asserted for your client, such as claims for tortious interference with contract, unjust enrichment, quantum meruit, or even fraud. In addition, the jury instructions outline the specific elements of the claims that you will need to plead (which will help you avoid motions to dismiss, for example). The jury instructions can be used as a navigation guide through all phases of the lawsuit, from the pleadings, through discovery, and all the way through trial or arbitration.
Does anyone have other ideas on starting points for drafting complaints? Some attorneys suggest you should even draft your jury instructions before you draft the complaint. I don't personally go that far, but maybe I should.
There are also various ABA Forum publications that you can utilize. For example, check out the Construction Damages and Remedies book here. For some pattern jury instructions, click here (California) and here (8th Circuit).
Before filing a lawsuit, you should take a deep breath. While many of us file lawsuits frequently, they are a big deal and you want to do it right. As such, you should consider reviewing sample jury instructions and perhaps consulting a "causes of action" practice guide before you do so much as put a caption on your Complaint. Most courts have sample/pattern jury instructions, and there are countless practice guides out there that break down your potential claims.
Wait a minute, why would I start by looking at the jury instructions? Don't I just worry about them in the unlikely event my case actually goes to trial or arbitration? NO. Jury instructions will guide you to the claims which might apply to your dispute. For example, your review of the jury instructions might make you realize the strength of additional claims to be asserted for your client, such as claims for tortious interference with contract, unjust enrichment, quantum meruit, or even fraud. In addition, the jury instructions outline the specific elements of the claims that you will need to plead (which will help you avoid motions to dismiss, for example). The jury instructions can be used as a navigation guide through all phases of the lawsuit, from the pleadings, through discovery, and all the way through trial or arbitration.
Does anyone have other ideas on starting points for drafting complaints? Some attorneys suggest you should even draft your jury instructions before you draft the complaint. I don't personally go that far, but maybe I should.
There are also various ABA Forum publications that you can utilize. For example, check out the Construction Damages and Remedies book here. For some pattern jury instructions, click here (California) and here (8th Circuit).