Wednesday, August 31, 2016

US Supreme Court False Claims Act Decision in Escobar Has Significant Implications for Contractors

Marion T. Hack, Partner, Pepper Hamilton LLP
John H. Conrad, Associate, Pepper Hamilton LLP

On June 16, 2016, the U.S. Supreme Court ruled in the matter of Universal Health Services, Inc. v. United States ex rel. Escobar, 136 S. Ct. 1989 (2016), changing the legal landscape for False Claims Act qui tam claims concerning the implied false certification theory of liability. This article will discuss the Escobar holding and examine relevant considerations for contractors in light of this ruling.

In Escobar, a teenage patient received counseling under Massachusetts’ Medicare program at a mental health facility, Arbour Counseling Services, which is owned and operated by a subsidiary of Universal Health Services, Inc. As part of the counseling process, the staff at Universal diagnosed the patient and prescribed medication. The patient had an adverse reaction to the mediation and subsequently died of a seizure. It was later determined that four out of the five Universal employees that treated the patient were not properly licensed to provide mental health counseling, prescribe medications or offer counseling services without supervision. Specifically, the person who diagnosed the patient had her psychologist license application rejected by Massachusetts, and the person who prescribed the medication was actually a nurse who lacked authority to prescribe medication without supervision, in violation of 130 Code Mass. Regs. § 429.22, et seq. Escobar, 136 S. Ct. at 1997-98.

During this time frame, Universal submitted requests for payment to the government for its personnel under Massachusetts’ Medicare program. Universal submitted these payment requests despite its knowledge that its personnel was improperly classified under the billing codes used by Universal.

The False Claims Act Claim

In 31 U.S.C. § 3730(b)(1) it states, “A person may bring a civil action for a violation of section 3729 for the person and for the United States Government. The action shall be brought in the name of the Government.” These suits are referred to as “qui tam” suits. Further, 31 U.S.C. § 3729(a) provides, “any person who knowingly presents, or causes to be presented, a false or fraudulent claim for payment or approval . . . is liable to the United States Government for a civil penalty of not less than $5,000 and not more than $10,000,[1] . . . plus 3 times the amount of damages which the Government sustains because of the act of that person.”

Under the above provisions, the respondents in Escobar brought a qui tam suit, alleging that Universal had violated the False Claims Act and defrauded the government in billing for services that were not properly rendered as described in the billings, while failing to disclose serious breaches related to Massachusetts’ Medicare program. The respondents asserted that the government would not have reimbursed the claims had it known that it was billed for mental health services that were performed by unlicensed and unsupervised staff. Escobar, 136 S. Ct. at 1997-98.

Universal filed a motion for summary judgment to dismiss the respondents’ claims. The district court granted Universal’s motion “because none of the regulations violated by Universal was a condition of payment.” The U.S. Court of Appeals for the First Circuit reversed, holding that “every submission of a claim implicitly represents compliance with relevant regulations, and that any undisclosed violation of a precondition of payment (whether or not expressly identified as such) renders a claim ‘false or fraudulent.’” The First Circuit also held that the “regulations themselves provided conclusive evidence that compliance was a material consideration of payment.” Id. at 1998.

The U.S. Supreme Court rejected both the holding of the district court and the holding of the First Circuit and remanded to the district court for further determination of the matter utilizing the new standard for implied certification claims under the False Claims Act. Id. at 2004.

New Standard for Implied False Certification Claims

The Court in Escobar held:

[T]he implied false certification theory can, at least in some circumstances, provide a basis for liability. By punishing defendants who submit “false or fraudulent claims,” the False Claims Act encompasses claims that make fraudulent misrepresentations, which include certain misleading omissions. When, as here, a defendant makes representations in submitting a claim but omits its violations of statutory, regulatory, or contractual requirements, those omissions can be a basis for liability if they render the defendant’s representations misleading with respect to the goods or services provided.

Id. at 1999 (emphasis added).

In Escobar, Universal knowingly submitted payment applications that listed specific billing codes corresponding to certified and licensed personnel, where those individuals were not certified or licensed, thus misleading the government into paying the invoices. Id. at 1997. The Escobar Court clarified that the claims in the matter related to more than just demands for payment and that “representations that state the truth only so far as its goes, while omitting critical qualifying information[,] can be actionable misrepresentations.” Id. at 2000.

A critical determination in the new Escobar standard is whether the statements made qualify as actionable misrepresentations. The Court in Escobar provided examples of some statements that create actionable misrepresentations to guide future litigation. When a seller of property reveals that there are two new roads near a property for sale, but fails to disclose that a third potential road might bisect the property, the seller has omitted key information that would “materially affect the value of the purchase.” Id. (citing Junius Const. Co. v. Cohen, 257 N.Y. 393, 400 (1931)). An applicant for a position at a college makes actionable misrepresentations when his résumé lists prior jobs and then retirement, but fails to disclose that his “retirement” involved time in prison for a $12 million bank fraud. Id. (citing Sarvis v. Vermont State Coll., 172 Vt. 76, 78, 80-82 (2001)). Both of these examples point to the need for the misrepresentation to affect the basic value of the goods or services to be provided in order to be an actionable misrepresentation.

The Escobar Court also held a critical factor was that the “misrepresentation about compliance with a statutory, regulatory, or contractual requirement must be material to the Government’s payment decision in order to be actionable under the False Claims Act.” Id. at 1996 (emphasis added). The Court also held that liability is not limited to cases where the requirements involved were expressly designated as conditions of payment. Id. at 2001. To assist in interpreting this standard, the Court provided an example of a material misrepresentation. When a contract involves the supply of guns, and the contract does not state that the guns must actually shoot, but the supplier knows that the government routinely rescinds contracts if the guns do not shoot, the supplier has “actual knowledge” of the materiality of that requirement. Further, the seller’s failure to appreciate the materiality of that condition would amount to “deliberate ignorance” or “reckless disregard” of the falsity of the information. Id. at 2001-02. The Court also cited to United States ex. rel. Marcus v. Hess, where two contractors violated a non-collusion bidding requirement and withheld that information. This was implicit false certification because the government would not have funded the subsequent payments had it known of the violation. Id. at 2003 (citing Marcus, 317 U.S. 5379, 543 (1943)).

In the construction context, misstatements concerning the types of materials supplied or the qualifications of the individuals whose labor is billed could implicate this implied false certification theory of the False Claims Act. For example, consider a construction contract that calls for a specific material or equipment that is required to meet specified quality or regulatory requirements. If the contractor knowingly supplies a different and lesser quality item and then bills for the government per the schedule of values including the originally specified item, then the contractor may be liable for implicitly submitting a false claim. Where a design/build contract calls for engineering or oversight services to be performed by a licensed engineer, or where a construction management contract calls for licensed or certified personnel to perform services, and where the contractor supplies unlicensed or uncertified personnel for the positions involved, an implied false certification claim is possible. Another example is a time and material construction contract that specifies categories of workers, depending on specific worker classifications and training levels. If the contractor provides labor that does not meet those specified classifications within the contract (e.g., supplying apprentice labor and billing for journeymen), and the contractor submits billing for personnel based on the classifications that do not match the personnel qualifications, the contractor is potentially liable for an implied false certification claim.

In all of these possible scenarios posed above, contractors need to be vigilant in verifying that the labor or materials supplied by the contractor or its subcontractors do in fact meet the specifications and/or regulatory requirements for any project. Otherwise, the contractor could be exposed to significant per act penalties and treble damages under the False Claims Act. Should any of these issues arise, a contractor should seek assistance in resolving the matter at the earliest time to avoid or minimize the potential penalties.

[1] The government revised the penalties in 2015 via 28 C.F.R § 85.3(a)(9) to a minimum of $10,781 and a maximum of $21,563 per occurrence.

Article originally posted August 26, 2016 on Constructlaw, an update and discussion of recent trends in construction law and construction, maintained and edited by Pepper Hamilton's Construction Law Practice Group. 

Tuesday, October 27, 2015

A Case to Watch: Highway Contractor Appeals $663M False Claims Act Judgment

Kristin H. Jones, Partner, Pepper Hamilton LLP
Thomas J. Madigan, Partner, Pepper Hamilton LLP

On August 31, 2015, highway contractors Trinity Industries, Inc. and Trinity Highway Products, LLC (collectively, Trinity) appealed to the U.S. Court of Appeals for the Fifth Circuit a $663,360,750 final judgment entered against them under the federal False Claims Act (FCA). At the conclusion of a six-day trial that commenced on October 13, 2014, the jury rendered a unanimous verdict, finding Trinity “knowingly made, used, or caused to be made or used, a false record of statement material to a false or fraudulent claim” in violation of the FCA. The jury unanimously found that the U.S. government suffered damages in the amount of $175,000,000 as the result of Trinity’s FCA violations.

After denying Trinity’s post-trial motions, the district court entered a final judgment on June 9, 2015 in which it (1) trebled the $175,000,000 damages award to $525,000,000 pursuant to 31 U.S.C. § 3729 and (2) assessed a civil penalty of $8,250 for each of the 16,771 false certifications that the jury found Trinity made in connection with false claims for payment, for a total penalty of $138,360,750. Of the final judgment amount of $663,360,750, 30 percent ($199,008,225) was awarded to the relator, who had proceeded with the prosecution of the FCA action without the participation of the U.S. government, which had declined to intervene in the case. In addition, the relator, as the prevailing party, was awarded attorney’s fees of $16,535,035.75, expenses of $2,300,000 and taxable costs of $177,830.

Trinity’s appeal of this extraordinarily large damages award could set important precedent as to what constitutes the “knowing presentation” of a false or fraudulent claim, statement or record and how damages are calculated in FCA cases.

The FCA provides that any person who “knowingly presents, or causes to be presented, a false or fraudulent claim for payment or approval,” or who “knowingly makes, uses, or causes to be made or used a false record or statement material to a false or fraudulent claim” is liable to the U.S. government for damages and civil penalties. 31 U.S.C. § 3729(a)(1)(A) and (B). The FCA can be enforced either by the U.S. Department of Justice or by private individuals acting on behalf of the government, formally known as “relators,” but often referred to as “whistleblowers.” Generally, damages in an FCA case are measured under a “benefit of the bargain theory,” i.e., the difference between what the government actually paid and what the government would have paid absent the fraud. Under the statute, damages may be trebled. In addition, the FCA permits the United States to recover penalties, costs and attorneys’ fees in successful cases. Penalties can be between $5,500 and $11,000 for each false claim.

In the FCA case against Trinity, the relator alleged that Trinity violated the FCA by knowingly and falsely certifying that Trinity’s guardrail end terminals, known as “ET-Plus,” had been crash-tested and approved for federal reimbursement by the Federal Highway Administration (FHWA). According to the relator, in or around 2005, Trinity modified the properties and dimensions of ET-Plus that had been previously approved by the FHWA in 1999. The relator alleged that Trinity did not disclose its modifications of ET-Plus to the FHWA, the FHWA did not approve the modifications, and, therefore, Trinity falsely “certified” that the modified ET-Plus had been approved by the FHWA. According to the relator, these false certifications caused the government to pay money when it reimbursed individual states for the costs associated with installing ET-Plus on federally funded or subsidized highways.

At trial, Trinity presented evidence that, contrary to the relator’s contentions, the FHWA repeatedly affirmed that ET-Plus was compliant with all applicable federal rules and regulations. Trinity also presented evidence that the allegedly false certifications were not made to the government contracting agency and played no part in either the award of the contract or any payment decision thereunder. The allegedly false statements at issue were representations made by Trinity to its customers that ET-Plus was compliant with the applicable government rules and regulations. Trinity disputed the requisite FCA element of causation, pointing to the fact that there was no evidence that the federal government ever saw the customer certifications, let alone relied on them in making its payment decision. Trinity also argued that such statements were not material to the government’s payment decision because, once made aware of the statements, the government investigated and rejected the relator’s allegations and concluded that Trinity was entitled to payment.

Ultimately, the jury found for the relator and awarded damages using a “benefit of the bargain” calculation propounded by the relator’s expert. The relator’s expert estimated that, after the 2005 modification of ET-Plus, the government paid $218,003,273 to reimburse states for purchases of modified ET-Plus and, because modified ET-Plus had not been approved by the FWHA, it had no ascertainable value other than as scrap metal. Accordingly, the expert argued that the appropriate measure of damages was $218,003,273, reduced by the scrap value of the modified ET-Plus, which was $175,037,890. The jury awarded $175,000,000 in damages. The court then determined that there were 16,771 false claims and applied a $8,250 penalty for each claim.

Trinity is appealing the damages award as both excessive and based on speculation and conjecture. Trinity argues that the relator failed to prove how much the FHWA actually paid in reimbursements for ET-Plus, but instead merely presented an estimate prepared by its expert of the percentage of ET-Plus sales that were federally reimbursed. This estimate was derived by multiplying Trinity’s total ET-Plus sales revenue by the percentage of states’ total highway-related expenditures that were spent on federal highways, and then applying an 80 percent federal reimbursement rate. Trinity contends that these estimates fail to satisfy the requirements that damages awarded under the FCA be “just and reasonable and “based on relevant data.” Trinity is also challenging the relator’s expert’s assumption that ET-Plus has no value other than as scrap, pointing to, among other things, statements by the FHWA that Trinity  contends acknowledge that the government received value for the ET-Plus units supplied.

Trinity is appealing the district court’s determination of penalties as violating the Seventh Amendment because the court failed to submit its challenges to several of the claims to the jury for its consideration. Trinity is also challenging the award of damages and the assessment of penalties as violative of the Eighth Amendment’s Excessive Fines Clause.

The Fifth Circuit’s ruling on Trinity’s appeal has the potential to provide significant guidance on the contours of what constitutes a knowing false claim or assertion and the level of proof required to sustain an award of damages under the FCA, as well as the appropriate role of the district court in determining damages and when an FCA judgment crosses the line into being unconstitutionally excessive. In the meantime, the case against Trinity serves as a reminder of the extraordinary risk of taking an FCA case to trial, even when the government has declined to intervene.
Article originally posted October 26, 2015 on Constructlaw, an update and discussion of recent trends in construction law and construction, maintained and edited by Pepper Hamilton's Construction Law Practice Group.