Tuesday, May 27, 2025

Learning a Lesson by Sweating the Small Stuff

When negotiating contracts, it is sometimes difficult to properly assess the risks and rewards of certain terms. The idiom “that one can’t see the forest through the trees” comes to mind. At times, though, even determining which forest needs to be seen can be the bigger challenge. We are all informed by our experiences and “battle wounds” – sometimes to our own detriment.

Recently, my client and I considered a contract provision which many of our clients likely believe is an elementary exercise: the number of adverse weather days  that should be included in a prime contract. This exercise led us to some surprising conclusions and forced us to consider whether we were overlooking other seemingly routine contractual provisions.

Let’s assume that an owner and general contractor are negotiating a prime contract on a private project. Consider the following two options from the perspectives of each of these two stakeholders. The first perspective will be that of an owner who has experience writing “too many change orders” for weather days. The second perspective will be from a contractor who “never gets enough time for weather.” 

Option One 

The Contract Time is 15 months. The Contractor shall be allowed three (3) weather days per month. Each additional weather day in any month that delays the critical path of the schedule shall result in an extension of the Contract Time. The Contractor shall not receive compensation for additional weather days.

Option Two

The Contract Time is 16 months. The Contractor shall anticipate seven (7) weather days per month. Each additional weather day in any month that delays the critical path of the schedule shall result in an extension of the Contract Time. The Contractor shall not receive compensation for additional weather days.

What is your initial reaction to the above options if you are representing the owner? The general contractor? How would each party best mitigate risk and maximize possible earnings on the upcoming project?

Recently, my client and I were presented with a similar scenario. My client, a general contractor, much preferred Option One. This is because it would be easy to extend the schedule for weather delays – any month with four or more days of adverse weather would entitle them to a schedule extension. But after we further analyzed the options, we came to a different conclusion.

For purposes of discussing the hypothetical scenario, we will assume that my client determined:

  • The entirety of the project’s work would be on the schedule’s critical path.
  • They could complete the work in 15 months if there were three days or less of inclement weather each month.
  • However, they were likely to encounter five days of inclement weather each month. 
  • Thus, they believed the project would take 16 months to complete if they encountered the weather they expected.
From the contractor’s perspective, if Option One was utilized and their assumptions were accurate, the Contract Time would be adjusted by an extra two days for each of the contract’s 15 months – which would add 30 days to the Contract Time. The total adjusted Contract Time would then be 16 months. Thus, if the contractor had built a 15-month schedule and bid based on Option One, the contractor would receive payment for 15 months of general conditions, though it would have taken 16 months to build the project. In other words, the contractor would incur the costs of an extra month of general conditions without receiving compensation for those costs.

If Option Two was selected, the contractor would not receive any time for change orders. However, it would be expected to budget for a full 16-month contract duration. Thus, if the contractor entered the contract having budgeted for 16 months, they would receive compensated for all of their general conditions – not the 15 months as allowed by Option One.

Let’s change points of view and consider the owner’s perspective. If the owner does not want to issue change orders for weather-related time, it may initially favor Option Two. If, in the above scenario, Option Two was selected but it never rained more than five days in a month, there would not be weather-related change orders issued during the project and the Owner would presumably be satisfied because it would not have issued change orders for weather delays. However, the Owner would have paid to mitigate that risk, because the contractor would have accounted for the extra 1-2 months of contract time in its bid and proposal. The contractor would have carried at least 16 months of general conditions costs in its budget. These general conditions would not have been included if the contract included the terms outlined by Option One.

In summary, Option One initially appears to benefit the contractor (because weather days are easier to recover) and Option Two appears to benefit the owner (because the threshold to recover weather days is more onerous). In practice, the inverse may be true, because under Option One, the owner would not pay for the 16th month of general conditions, while under Option Two the owner would have paid for that 16th month. In our contract, the contractor and I negotiated toward the concept presented by Option Two so that they could recover more general conditions costs.

We were surprised by this analysis and glad we took the time considering both options. We should all try to keep this lesson in mind, to consider all possible “forests” when negotiating any contractual term on behalf of a client. Many terms that may appear to benefit one party on the surface could cause unneeded expense when the other party protects itself from the underlying risk. Consider how a contractor’s bid may increase if it is required to carry an extra-ordinarily low insurance deductible; or if it has to accept a broad definition of reasonably foreseeable conditions.

Of course, every contract contains a benefit of the bargain for both parties. As advocates for our clients, we should fully analyze how each party may benefit – or be harmed – when considering these types of risk-shifting provisions in construction contracts.


Author, Corey S. Lloyd, is of counsel with Riess LeMieux in New Orleans, practicing primarily in construction law. Before joining Riess LeMieux, he work as general counsel for at a large, regional design builder. Prior to his legal career, Corey obtained a degree in civil engineering and spent over two decades in commercial project management. 

Editor, Stu Richeson, is an attorney with Riess LeMieux in New Orleans, primarily focusing on commercial litigation with an emphasis on construction matters

No comments:

Post a Comment