
A “delay”
on a construction project is defined as the stretching out of the time for
completion of certain key milestone scopes of work which can impact the
completion date of an entire project, due to some circumstances or events that
were not reasonably anticipated when the project began. 2 Construction Law ¶ 6.01 (Matthew Bender,
2024). While delays can be caused by any number of events, the most common are
defective plans and specifications; design changes; severe weather and other,
similar unforeseeable events; unforeseen or differing site conditions; unavailability
of materials or labor; labor inefficiencies or stoppages; contractor negligence;
and owner influences, including construction changes or outright interference
by the owner or its agents. If the project schedule is not recovered following a
delay, then the project schedule will likely be extended, resulting in an
increase in the contractor’s costs of performance. A contractor that has experienced a delay on a
project can take certain actions to pursue recovery of any damages the
contractor may have incurred. However,
to do so it is important to understand the different types of delays and the
methods for establishing the delays.
I. Types of Delays
Delays
may be categorized as (1) critical versus non-critical
delays, (2) excusable versus non-excusable delays, and (3) compensable versus non-compensable
delays. A critical
delay is a delay that affects the project completion date and delays the entire
project. In essence, a critical delay is one that will extend the critical path
of a project. A non-critical delay is a
delay that has no effect on the project’s critical path. Courts have recognized
that delays to work not on the critical path will generally not delay the
completion of a project. G.M. Shupe,
Inc. v U.S., 5 Cl. Ct. 662, 728 (1984). Such a non-critical delay may affect the
completion of certain activities, but does not affect the completion date of
the entire project. In order for a delay to provide the basis for a claim for
additional time or money, the delay must impact critical path activities on the
project schedule.
In addition to determining if a
delay is a critical or non-critical delay, it is important to determine if a
delay is non-excusable or excusable. An excusable delay is a delay that is unforeseeable
and beyond the control of the contractor and often allows a contractor to
recover an extension of time, an increase in the contract sum, or both. In
contrast, a non-excusable delay is a delay that is foreseeable or within the
contractor’s control. Obviously, the distinction between these two is
significant in that it determines which party is liable for the delay and dictates
whether a contractor is entitled to additional time (and possibly money) or may
need to compensate the owner for the delay. To prove its entitlement to delay
damages, the contractor is typically required to maintain some form of reliable
schedules if the parties desire to hold one another accountable for delays and
ultimately determine the party responsible for the delays.
Contractor-caused delays typically
entitle the owner to recover damages, such as any liquidated damages, or to
terminate the contract for the contractor’s material breach in having delayed
the project. Likewise, because the contractor is responsible for the delay, the
contractor will not be entitled to either additional time or additional compensation
for its own costs or damages associated with the delay. In fact, a contractor
dealing with a non-excusable delay routinely will have to accelerate its work,
at its own expense, to avoid delaying the project.
Excusable delays are usually caused
by conditions that are reasonably unforeseen and not within the contractor’s
control. In other words, an excusable delay is usually one not due to the
contractor’s negligence. The most common example of an excusable delay usually
falls under a force majeure clause and may include fire, floods, earthquakes,
natural disasters, owner changes, errors or omission in the plans and
specifications, differing or unforeseen site conditions, and acts of
governmental bodies.
For a delay not set forth in or
addressed in the contract to be excused, it normally has to fall within one or
both of the following categories: “(1) the delay resulted from interference
with the contractor’s performance by the owner or those for whom the owner is
responsible; or (2) the risk of the delay was not expressly or impliedly
assumed by either party to the contract.” 2 Construction Law ¶ 6.09 (Matthew Bender,
2024).
After determining that a delay
is an excusable delay, you have to determine if it is a non-compensable or
compensable delay. A good place to start is to analyze the controlling contract
language as it will usually include terms as to whether a delay is compensable
or non-compensable. Non-compensable
delays are delays for which the contractor is entitled to a time extension but
not entitled to additional monetary compensation.Neither
party is responsible for the damages incurred by the other party. Thus, both
parties assume their own additional costs arising out of the delay. Such delays
are typically addressed in the context of force majeure clauses.
Compensable delays are delays to the
critical path that are unforeseeable and beyond the contractor’s control or
fault, for which the contractor is entitled to a time extension and additional
compensation. Determination of the critical path is necessary for determining
if a delay is compensable because only work on the critical path has an impact
upon the time in which the project is to be completed. LCC-MZT Team IV v United States, 155
Fed. Cl. 387, 458 (2021) (citing Ultimate Concrete, LLC v. United States,
141 Fed. Cl. 463, 480 (2019)).
Courts have held that a critical path
delay is compensable if it was entirely caused by events within the other
party’s control. Cobb Mech. Contrs.,
Inc. v. Morganti Grp. Inc., 2007 U.S. Dist. LEXIS 108103, *11 (S.D. Texas,
Aug. 4, 2007). However, if a general contractor is unable to prove that the
owner was responsible for the event(s) that caused the delay, then the delay is
excusable but normally non-compensable. Houston
v. R. F. Ball Constr. Co., 570 S.W.2d 75, 77 (Tex. Civ. App. – Houston
[14th Dist.] 1978, writ ref’d n.r.e. In
general, a compensable delay is caused by the owner or its agent, but could
also be caused by “no fault” events, such as acts of God and the like. Depending
upon the controlling contractual terms, compensable delays may include
circumstances, such as a changes to the design or the contract terms; a
suspension of work; inability to provide site access; untimely review of
submittals, shop drawings, or responses to RFIs; delayed issuance of the notice
to proceed; defective plans and specifications; and, differing site conditions.
II. Methods of Proving Delays
When a party experiences a delay and
has determined that the delay is an excusable and compensable delay, the party
must then determine how to properly analyze and quantify the damages associated
with the delay. There are multiple methods for proving delays and each has its
“pros” and “cons.” Attorneys must be sure that the method chosen is best for
the available facts and data surrounding the delay and that the analysis will
be accepted as reliable and credible by those that ultimately review the claim regarding
the delay (i.e. the court or the arbitrators). Some of the common
methods of delay analysis include (1) the Total Cost Method, (2) the Modified
Total Cost Approach, and (3) the Measured Mile Method.
A. Total Cost Method
In general, the Total Cost Method is a
process whereby you subtract the contractor’s bid estimate from the total of
all project costs incurred and seek recovery of the overrun as the damages
caused by the delay. While it is one of the simplest methods for calculating
delay damages, it carries the least amount of weight with those opposing delay
claims as it does not eliminate the fact that the party seeking the delay claim
may have been responsible for some of the delay. Additionally, it has also been disfavored due
to concerns about bidding inaccuracies. Servidone Constr. Corp. v. United
States, 931 F.2d 860, 861-62 (Fed. Cir. 1991) IMany courts, such as the one
in Servidone, are openly critical of the Total Cost Method and have even
noted that the Total Cost Method should be used with caution and as a last
resort.
B. Modified Total Cost Approach
The Modified Total Cost Approach is preferred
over the Total Cost Method as it eliminates the sole reliance on the
contractor’s original estimate by taking into account deficiency or performance
issues caused by the contractor and factoring in non-compensable delays such as
Acts of God. Courts have explained that when using the Modified Total Cost
Approach, safeguards must be used to ensure that the burden of excess expenses
falls on the party responsible for those expenses. Raytheon Co. v. White,
305 F.3d 1354, 1366 (Fed. Cir. 2002). In Raytheon, the Federal Circuit
has clarified that a plaintiff utilizing a Modified Total Cost methodology must
prove that (1) the nature of the losses make it impossible or highly
impracticable to determine them with a reasonable degree of accuracy; (2) the
plaintiff’s bid or estimate was realistic; (3) its actual costs were
reasonable; and (4) it was not responsible for the added expenses. If a
plaintiff is successful, the plaintiff may recover the total cost of the
contract minus the bid price with various adjustments for delays the contractor
caused or any miscalculations. Propellex Corp. v. Brownlee, 342 F.3d
1335, 1339 (Fed. Cir. 2003).
C. Measured Mile Method
The Measured Mile Analysis is the preferred method for
calculating lost productivity and delay damages. It is a technique whereby an
unimpacted period or area or activity of construction work is compared with
another period or area or activity of construction work that has been
disrupted, the assumption being that the difference between the labor or
equipment hours expended per unit of work performed in the unimpacted and
impacted periods represents the loss to the contractor due to the impact or
disruption for which another party is responsible. United States ex rel. Salinas Constr., Inc.
v. W. Sur. Co., No. C14-1963JLR, 2016 U.S. Dist. LEXIS 88267, at *9 (W.D.
Wash. July 7, 2016). It is often said to
be the preferred method of proving damages as it has the ability to isolate the
productivity loss during an impacted period from other project factors.
Contractors will eventually incur some type of delay on a
construction project. Thus, it is important to understand the different types
of delay and whether or not a delay is compensable. At the same time, it is also important to understand
the different delay claim methodologies to understand what information and
project documentation will assist in proving entitlement to recovery for damages
due to delays. While you may eventually have to retain a delay expert to assist
with the claim, it is important to understand delays and delay claims so that
you can proactively support any such claims.
Author Andrew G. Vicknair is an attorney with D'Arcy Vicknair, LLC in New Orleans, Louisiana. Andrew focuses his practice on construction litigation matters and regularly handles claims related to construction defects, payment disputes, design issues, and general disputes among subcontractors, owners, and general contractors.
No comments:
Post a Comment