
In March of 2014, six employees of the Plaintiff filed
a lawsuit for unpaid wages in Massachusetts District Court and summary judgement
was issued on April 6, 2014 in favor of the employees. When the Defendant learned of this judgement,
it advanced funds to the Plaintiff to pay the back wages, but ultimately the Plaintiff’s
employees quit the project on April 23, 2014. The Defendant later found that
the funds it provided were not paid to the employees until three months later
in July 2014. On May 16, 2014, the Defendant
put the Plaintiff on notice of breach for failure to maintain schedule, and then
formally terminated the Plaintiff on June 10, 2014, citing the failure to pay
wages and to timely perform the contract schedule. At the time of termination, Plaintiff had only
completed 75% of the Phase I work and was 44% complete on the entire job.
In May of 2015, the Plaintiff filed suit against
the Defendant in federal district court for: 1) breach of contract; 2) quantum
meruit; 3) violation of the Miller Act; and 4) violation of the Massachusetts
unfair business practices act. Defendant counterclaimed for breach of contract
and violation of the unfair business practices act, plus a cross-complaint
against the Plaintiff’s owner for fraud.
The Court began its analysis of the Plaintiff’s
claim by simply stating that the Plaintiff’s failure to pay its employees in a
timely fashion, as required both by the Davis-Bacon Act and the subcontract,
was a material breach. That material
breach in turn relieved the Defendant of any duty to make payments on the
contract to the Plaintiff. The Court
then rejected the Plaintiff’s argument that the act of the Defendant paying the
employee’s back wages constituted waiver of that breach. The Court discounted this argument by stating
there was no “clear, decisive, and unequivocal conduct” indicating waiver by
the Defendant.
The Court next reviewed the Plaintiff’s claim in
quantum meruit for $158,823.14 in work it claimed to have performed before its
termination. To start this analysis, the
Court pointed to the maxim of Equity that, “a party coming before the court
seeking equitable relief must do so with clean hands.” The Court declared that the Plaintiff in this
instance not only failed to follow Federal law, it also failed to adhere the
terms of the subcontract by paying its tradesmen in a timely fashion, and it finally
then filed perjured certified payrolls, compounding the issues. As such, a claim in equity for “quantum
meruit…is a nonstarter.”
Based upon its ruling on the first two counts of
the complaint, the Court rejected the Miller Act and unfair business practices claims
outright and granted Summary Judgment in favor of the Defendant.
------------------
The author, Brendan Carter, is a contributor to The Dispute Resolver and a former Student Division Liaison to the Forum on Construction Law. He is an attorney and a Senior Consultant with Navigant’s Global Construction Practice based in Boston, MA. He may be contacted at 617.748.8311 or brendan.carter@navigant.com
No comments:
Post a Comment