The underlying project was for the construction of a health and fitness center at the Virginia Tech campus in Blacksburg, Virginia. The general contractor entered into the $15 million contract with Virginia Tech, a Commonwealth agency. By law, no statute of limitations period can run against Virginia Tech. Va. Code section 8.01-231. By contract, the prime contract stated that: Except
as otherwise specified, all work shall be guaranteed by the [general contractor] against defects resulting from the use of inferior materials, equipment or workmanship for one (1) year from the date of final acceptance of the entire project by [Virginia Tech] in writing[.]
Nothing in this section shall be construed to establish a period of limitation with respect to any other obligation which the [general contractor] might have under the Contract Documents, including liability for defective work under [the Warranty provisions].In sum, besides the 1-year warranty, there was no statute of limitations applicable to claims or disputes under the prime contract.
The project undisputedly was finished in 2000. Twelve years later in April 2012, Virginia Tech found variety of construction defects, repaired them, and then brought a claim against the general contractor to recover over $7 million. The general contractor looked to its subcontractors for these repair costs. When they refused, the general contractor settled with Virginia Tech for $3 million, and then sued all its implicated subcontractors. The subcontractors invoked the statute of limitations, which in Virginia, is five years for an action on a written contract. Va. Code § 8.01-246(2).
In turn, the general contractor pointed to its subcontracts' flow-down provision, which stated that "[t]he subcontractor is bound to the [general contractor] by the same terms and conditions by which [the general contractor] is bound to [Virginia Tech] under the [prime] contract," and that the subcontractor's warranty period covers any time "prior to [the general contractor's] release from responsibility to [Virginia Tech] therefor as required by the Contract Documents." The general contractor argued that because the general contractor was obligated to Virginia Tech on its claims brought 12 years after the project concluded, the subcontractors too were subject to claims from the general contractor.
Virginia's highest court sided with the subcontractors holding that any waiver of a known right must be "express" in that it reflects both knowledge of the right and the clear intent to relinquish the right. It need not be in writing. Here, the Court continued, the subcontract incorporation by reference neither acknowledged the 5-year statute of limitation nor the clear intent to waive the benefit of the statute. Moreover, just because the prime contract was silent on the statute of limitations, the subcontract could not be held to incorporate a statute that existed outside the prime contract. As a result, the Court held that the statutory waiver of the statute of limitations was not incorporated into the subcontracts, the 5-year period had run, and therefore the general contractor had no claim against the subcontractors.
As an alternate argument, the general contractor focused on the accrual date for the claim. It argued that its claims against the subcontractors, which sounded in indemnification, did not accrue until it settled with Virginia Tech. But because Va. Code § 8.01-246(2) states that the accrual is "when the breach of contract occurs in actions ex contractu and not when the resulting damage is discovered," this too was a dead end for the general contractor. Another statute Va. Code § 8.01-249(5) for "actions for contribution or indemnification," established accrual when "the contributee or the indemnitee has paid or discharged the obligation." But, here, the indemnification provision in the subcontract was rendered void because it could be read as requiring indemnification for the general contractor's own negligence. The Court disagreed that other parts of the subcontract, cobbled together, could give rise to independent cause of action for indemnification. So again, the general contractor could not proceed with its lawsuit.
The lesson learned is that explicitness in a follow-down provision is necessary if a waiver of rights is involved.
--------------------------------------------------
The author, Katharine Kohm, is a committee member for The Dispute Resolver. Katharine practices construction law and commercial litigation in Rhode Island and Massachusetts. She is an associate at Pierce Atwood, LLP in Providence, Rhode Island. She may be contacted at 401-490-3407 or kkohm@PierceAtwood.com.



