Introduction
Cumulative impact claims are among the most challenging disputes in
construction law. Often called the “silent killer” of project
productivity, these claims allege that the combined effect of numerous changes,
not any single one, causes significant inefficiencies, disruption, and cost
growth.
While contractors may have little trouble showing that productivity
declined or costs escalated, the real difficulty lies in proving causation.
Dispute resolution forums require more than an assertion of widespread
disruption; they demand a disciplined demonstration that the inefficiencies
were caused by the accumulation of changes, were unforeseeable, and were not
attributable to other factors such as poor management, labor shortages, or
weather.
From a practitioner’s perspective, this article examines the unique
challenge of causation in cumulative impact claims and provides insights into
the analytical approaches attorneys and experts can leverage when these
disputes arise in arbitration, mediation, or litigation.
What Makes a Cumulative Impact Claim
Distinct
Unlike discrete claims tied to specific events, cumulative impact claims
argue that individually manageable changes, when combined over time, erode
productivity in ways no single change order captures. The argument is that
frequent owner-directed modifications, design clarifications, and scope
adjustments collectively fragment workflow, cause rework, stack trades, and
disrupt sequencing.
These claims are most often seen on large or complex projects where
constant change becomes the norm. Yet the very nature of these claims, which focus
on systemic disruption rather than isolated events, make them difficult to
prove.
The Burden of Causation
To succeed in a
cumulative impact claim, a contractor must meet three key burdens:[1]
- Establish a causal link between the accumulation of
changes and the alleged disruption.
- Show that the impact was
unforeseeable at the time of contracting or when changes were accepted.
- Demonstrate that the disruption
was not caused by other factors, including the contractor’s own shortcomings.
Each of these
burdens presents its own challenges.
Establishing the Causal Link
Courts and arbitral panels expect more than evidence of a high volume of
change orders. The claimant must demonstrate how the timing, frequency, and
interaction of changes disrupted workflow and reduced productivity. Simply
pointing to the number of changes is not enough.
The most effective claims weave together contemporaneous records, project
schedules, and productivity data to tell a compelling story of cause and
effect. Without this, even a project riddled with disruption may fail to meet
the evidentiary standard.
Demonstrating the Impacts Were Unforeseeable
Most contracts allocate risk for changes and disruptions to some extent.
To establish entitlement, the contractor must show that the cumulative impact
went beyond what the parties reasonably contemplated. If disruption is viewed
as an expected byproduct of the contract or if the contractor failed to raise
concerns in real time, the claim often collapses.
For attorneys and other dispute resolution professionals, the key
question becomes whether the alleged cumulative effect was an unexpected
consequence of the changes, or simply a foreseeable outcome the contractor
should have anticipated.
Isolating Cumulative Impact from Other
Causes
Even when disruption is proven, it must be distinguished from other
contributing factors. Poor planning, resource shortages, labor disputes,
weather events, or concurrent delays can all blur causation. Adjudicators are
especially wary of claims that appear to mask contractor inefficiencies under
the guise of cumulative impact.
Strong claims directly address and separate out these other factors,
demonstrating that while multiple causes may exist, the cumulative effect of
owner-directed changes was a substantial driver of productivity loss.
Analytical Approaches for
Demonstrating Causation
Attorneys representing contractors or owners in these disputes must rely
on expert analysis. Several methodologies are commonly used, each with
strengths and limitations.
System Dynamics Modeling
System dynamics is becoming one of the most comprehensive approaches for
cumulative impact claims. It simulates how projects evolve over time based on
interactions such as workforce efficiency, rework cycles, frequency of changes,
and schedule compression.
Unlike traditional methods, system dynamics captures the cause-and-effect
feedback loops, time delays, and nonlinear behavior that characterize
cumulative disruption. Forensically, it allows an expert to demonstrate not
just that productivity loss occurred, but how and why it occurred across the
life of the project.
For attorneys, this provides a transparent and compelling narrative, one
that helps decision-makers understand the mechanisms of cumulative impact in a
way that simple cost comparisons cannot.
Measured Mile and Modified Measured
Mile
The measured mile method compares productivity in an “unimpacted” portion
of the project to a disrupted portion. Where no fully undisturbed period
exists, a modified measured mile may be used.
These methods are widely accepted but have significant limitations in
cumulative impact disputes:
- On heavily
disrupted projects, no truly unaffected period may exist.
- Overlapping
disruptions make it difficult to isolate impacts.
- External events
such as weather or supply chain delays can confound results.
While useful as part of a broader evidentiary framework, measured mile
analyses rarely succeed on their own in proving entitlement to cumulative
impact claims.
Total Cost and Modified Total Cost
Approaches
In some cases, contractors present claims by comparing actual costs to
the original estimate, attributing the difference to disruption. These “total
cost” approaches are generally disfavored in dispute resolution. They are often
seen as blunt instruments that attempt to shift all overruns to the owner
without isolating causes.
Such claims typically succeed only when no other method is feasible and when the contractor can show that its estimate and actual costs were reasonable and that it bore no responsibility for the overruns. In practice, this is a high bar that few claims can meet.
Case Study: J.A. Jones Construction
Co. – Limits of Measured Mile in Pervasively Disrupted Projects
Source: Appeal of J.A. Jones Construction
Co., ENGBCA No. 5528 (1995)
This case is directly relevant to the central themes of this article, particularly
the difficulty of proving causation, the challenge of identifying truly
“unimpacted” work, and the limitations of relying on single-method analyses
such as measured mile. J.A. Jones illustrates the precise evidentiary hurdles
that arise when cumulative disruption affects every phase of a project, making
traditional analytical techniques insufficient on their own.
Summary of the Dispute
The contractor was engaged in constructing a federal courthouse that
experienced continuous design revisions, late approvals, and owner-driven scope
adjustments. Although each individual change appeared modest, their frequency
and overlap disrupted sequencing, increased trade interference, and eroded
workflow stability. J.A. Jones sought recovery for cumulative impact, arguing
that the aggregation of owner-directed modifications caused substantial
productivity loss.
To demonstrate inefficiency, the contractor attempted a measured-mile
analysis. However, the Board found that the project had no period of unimpacted
performance, which rendered the measured-mile results non-applicable. Because
disruption permeated all phases of the work, there was no valid baseline
against which to measure labor productivity. The Board therefore rejected the
measured-mile approach, not because cumulative impact did not exist, but
because the analytic method was unsuited to the circumstances.
Rather than dismiss the claim outright, the Board examined
contemporaneous project documentation, including daily reports, manpower
records, evidence of resequencing, and patterns of workflow fragmentation.
These materials helped establish that owner-directed changes materially
contributed to productivity degradation, while also allowing the Board to
separate owner-caused disruption from contractor-driven inefficiencies.
Relevance to Causation and Expert
Analysis
J.A. Jones demonstrates that even when every available productivity
comparison is distorted by widespread disruption, cumulative impact may still
be recoverable if the claimant provides a clear, evidence-based causation
narrative. The case underscores that:
- measured mile is not universally
applicable;
- causation must be supported by
multiple forms of evidence; and
- contemporaneous project
documentation often becomes the most persuasive tool.
This case reinforces
the need to build cumulative impact claims around mechanisms of disruption, not
simply numerical comparisons.
Why This Matters for Attorneys in
Dispute Resolution
For those litigating or arbitrating cumulative impact claims, the
challenge is not proving that disruption occurred—most large projects
experience it. The challenge is proving causal entitlement: that the
disruption was caused by cumulative changes, was unforeseeable, and was not caused
by the contractor.
Attorneys must therefore focus their strategy on evidence that ties
productivity losses directly to the aggregation of changes. This often
requires:
- Contemporaneous
documentation such as daily reports, meeting minutes, and correspondence.
- Forensic
schedule and productivity analysis performed by qualified experts.
- A clear
narrative that distinguishes cumulative disruption from other project
challenges.
The most effective cases combine these elements into a story that is
accessible to arbitrators, judges, and mediators, many of whom may not have
technical construction backgrounds.
Practical Takeaways
- Document early
and often. Contractors who fail to flag concerns about cumulative disruption
during execution often undermine their own claims later.
- Build causation
step by step. Strong claims link specific clusters of changes to measurable
impacts, supported by contemporaneous records.
- Beware of
overreliance on formulas. No single method, including measured mile, total cost, or otherwise,
will suffice in isolation. Use multiple approaches to triangulate the
truth.
- Anticipate
skepticism. Dispute resolution forums are wary of cumulative impact claims,
viewing them as attempts to shift unanticipated costs. Expect to face
rigorous scrutiny on causation.
Conclusion
Cumulative impact claims represent one of the most difficult frontiers in
construction disputes. They ask courts, arbitrators, and mediators to look
beyond individual changes and recognize a systemic effect that is hard to
quantify. Success hinges on causation: proving that inefficiencies were caused
by the accumulation of changes, that they were unforeseeable, and that they
were not the contractor’s own doing.
For attorneys, the implication is clear: these cases require careful strategy, strong documentation, and expert analysis that can withstand cross-examination. Without that foundation, even genuine disruption may fail to result in recovery.
[1] AACE International’s Recommended Practice RP 130R-23, Demonstrating Entitlement to Cumulative Impact Claims in Construction, provides additional detail in this area from a practitioner’s perspective.
Author Stephen P. Warhoe, PhD, PE, CCP, CFCC, FAACE, is a Senior Director at Arcadis and an expert in delay, disruption, and productivity loss on complex projects. He has nearly four decades in the construction field, is a university professor in construction management, and has testified extensively as an expert witness in construction disputes.
Editor Thanh Do, PhD, PE, is a Director at BRG's Global Construction Practice. He specializes in root cause investigations of structural failures, standard of care evaluations, construction and design defect analysis, Design-Build delivery, early dispute resolution, and trial visualization.
No comments:
Post a Comment