This month's installment of the Toolbox Talk Series explored the use of Generative AI in document review, which as construction lawyers know can be voluminous. Jack Bandlow and Travis Olson from BRG provided an overview of how lawyers can use GenAI to make document review in construction litigation more efficient.
Articles on Construction Litigation & Dispute Resolution by Division 1 of the ABA Forum on Construction Law
Tuesday, November 25, 2025
Toolbox Talk Series: GenAI Document Review
This month's installment of the Toolbox Talk Series explored the use of Generative AI in document review, which as construction lawyers know can be voluminous. Jack Bandlow and Travis Olson from BRG provided an overview of how lawyers can use GenAI to make document review in construction litigation more efficient.
Monday, November 17, 2025
Consultant Corner: The Hardest Case to Prove: Causation in Cumulative Impact Claims
Introduction
Cumulative impact claims are among the most challenging disputes in
construction law. Often called the “silent killer” of project
productivity, these claims allege that the combined effect of numerous changes,
not any single one, causes significant inefficiencies, disruption, and cost
growth.
While contractors may have little trouble showing that productivity
declined or costs escalated, the real difficulty lies in proving causation.
Dispute resolution forums require more than an assertion of widespread
disruption; they demand a disciplined demonstration that the inefficiencies
were caused by the accumulation of changes, were unforeseeable, and were not
attributable to other factors such as poor management, labor shortages, or
weather.
From a practitioner’s perspective, this article examines the unique
challenge of causation in cumulative impact claims and provides insights into
the analytical approaches attorneys and experts can leverage when these
disputes arise in arbitration, mediation, or litigation.
What Makes a Cumulative Impact Claim
Distinct
Unlike discrete claims tied to specific events, cumulative impact claims
argue that individually manageable changes, when combined over time, erode
productivity in ways no single change order captures. The argument is that
frequent owner-directed modifications, design clarifications, and scope
adjustments collectively fragment workflow, cause rework, stack trades, and
disrupt sequencing.
These claims are most often seen on large or complex projects where
constant change becomes the norm. Yet the very nature of these claims, which focus
on systemic disruption rather than isolated events, make them difficult to
prove.
The Burden of Causation
To succeed in a
cumulative impact claim, a contractor must meet three key burdens:[1]
- Establish a causal link between the accumulation of
changes and the alleged disruption.
- Show that the impact was
unforeseeable at the time of contracting or when changes were accepted.
- Demonstrate that the disruption
was not caused by other factors, including the contractor’s own shortcomings.
Each of these
burdens presents its own challenges.
Establishing the Causal Link
Courts and arbitral panels expect more than evidence of a high volume of
change orders. The claimant must demonstrate how the timing, frequency, and
interaction of changes disrupted workflow and reduced productivity. Simply
pointing to the number of changes is not enough.
The most effective claims weave together contemporaneous records, project
schedules, and productivity data to tell a compelling story of cause and
effect. Without this, even a project riddled with disruption may fail to meet
the evidentiary standard.
Demonstrating the Impacts Were Unforeseeable
Most contracts allocate risk for changes and disruptions to some extent.
To establish entitlement, the contractor must show that the cumulative impact
went beyond what the parties reasonably contemplated. If disruption is viewed
as an expected byproduct of the contract or if the contractor failed to raise
concerns in real time, the claim often collapses.
For attorneys and other dispute resolution professionals, the key
question becomes whether the alleged cumulative effect was an unexpected
consequence of the changes, or simply a foreseeable outcome the contractor
should have anticipated.
Isolating Cumulative Impact from Other
Causes
Even when disruption is proven, it must be distinguished from other
contributing factors. Poor planning, resource shortages, labor disputes,
weather events, or concurrent delays can all blur causation. Adjudicators are
especially wary of claims that appear to mask contractor inefficiencies under
the guise of cumulative impact.
Strong claims directly address and separate out these other factors,
demonstrating that while multiple causes may exist, the cumulative effect of
owner-directed changes was a substantial driver of productivity loss.
Analytical Approaches for
Demonstrating Causation
Attorneys representing contractors or owners in these disputes must rely
on expert analysis. Several methodologies are commonly used, each with
strengths and limitations.
System Dynamics Modeling
System dynamics is becoming one of the most comprehensive approaches for
cumulative impact claims. It simulates how projects evolve over time based on
interactions such as workforce efficiency, rework cycles, frequency of changes,
and schedule compression.
Unlike traditional methods, system dynamics captures the cause-and-effect
feedback loops, time delays, and nonlinear behavior that characterize
cumulative disruption. Forensically, it allows an expert to demonstrate not
just that productivity loss occurred, but how and why it occurred across the
life of the project.
For attorneys, this provides a transparent and compelling narrative, one
that helps decision-makers understand the mechanisms of cumulative impact in a
way that simple cost comparisons cannot.
Measured Mile and Modified Measured
Mile
The measured mile method compares productivity in an “unimpacted” portion
of the project to a disrupted portion. Where no fully undisturbed period
exists, a modified measured mile may be used.
These methods are widely accepted but have significant limitations in
cumulative impact disputes:
- On heavily
disrupted projects, no truly unaffected period may exist.
- Overlapping
disruptions make it difficult to isolate impacts.
- External events
such as weather or supply chain delays can confound results.
While useful as part of a broader evidentiary framework, measured mile
analyses rarely succeed on their own in proving entitlement to cumulative
impact claims.
Total Cost and Modified Total Cost
Approaches
In some cases, contractors present claims by comparing actual costs to
the original estimate, attributing the difference to disruption. These “total
cost” approaches are generally disfavored in dispute resolution. They are often
seen as blunt instruments that attempt to shift all overruns to the owner
without isolating causes.
Such claims typically succeed only when no other method is feasible and when the contractor can show that its estimate and actual costs were reasonable and that it bore no responsibility for the overruns. In practice, this is a high bar that few claims can meet.
Case Study: J.A. Jones Construction
Co. – Limits of Measured Mile in Pervasively Disrupted Projects
Source: Appeal of J.A. Jones Construction
Co., ENGBCA No. 5528 (1995)
This case is directly relevant to the central themes of this article, particularly
the difficulty of proving causation, the challenge of identifying truly
“unimpacted” work, and the limitations of relying on single-method analyses
such as measured mile. J.A. Jones illustrates the precise evidentiary hurdles
that arise when cumulative disruption affects every phase of a project, making
traditional analytical techniques insufficient on their own.
Summary of the Dispute
The contractor was engaged in constructing a federal courthouse that
experienced continuous design revisions, late approvals, and owner-driven scope
adjustments. Although each individual change appeared modest, their frequency
and overlap disrupted sequencing, increased trade interference, and eroded
workflow stability. J.A. Jones sought recovery for cumulative impact, arguing
that the aggregation of owner-directed modifications caused substantial
productivity loss.
To demonstrate inefficiency, the contractor attempted a measured-mile
analysis. However, the Board found that the project had no period of unimpacted
performance, which rendered the measured-mile results non-applicable. Because
disruption permeated all phases of the work, there was no valid baseline
against which to measure labor productivity. The Board therefore rejected the
measured-mile approach, not because cumulative impact did not exist, but
because the analytic method was unsuited to the circumstances.
Rather than dismiss the claim outright, the Board examined
contemporaneous project documentation, including daily reports, manpower
records, evidence of resequencing, and patterns of workflow fragmentation.
These materials helped establish that owner-directed changes materially
contributed to productivity degradation, while also allowing the Board to
separate owner-caused disruption from contractor-driven inefficiencies.
Relevance to Causation and Expert
Analysis
J.A. Jones demonstrates that even when every available productivity
comparison is distorted by widespread disruption, cumulative impact may still
be recoverable if the claimant provides a clear, evidence-based causation
narrative. The case underscores that:
- measured mile is not universally
applicable;
- causation must be supported by
multiple forms of evidence; and
- contemporaneous project
documentation often becomes the most persuasive tool.
This case reinforces
the need to build cumulative impact claims around mechanisms of disruption, not
simply numerical comparisons.
Why This Matters for Attorneys in
Dispute Resolution
For those litigating or arbitrating cumulative impact claims, the
challenge is not proving that disruption occurred—most large projects
experience it. The challenge is proving causal entitlement: that the
disruption was caused by cumulative changes, was unforeseeable, and was not caused
by the contractor.
Attorneys must therefore focus their strategy on evidence that ties
productivity losses directly to the aggregation of changes. This often
requires:
- Contemporaneous
documentation such as daily reports, meeting minutes, and correspondence.
- Forensic
schedule and productivity analysis performed by qualified experts.
- A clear
narrative that distinguishes cumulative disruption from other project
challenges.
The most effective cases combine these elements into a story that is
accessible to arbitrators, judges, and mediators, many of whom may not have
technical construction backgrounds.
Practical Takeaways
- Document early
and often. Contractors who fail to flag concerns about cumulative disruption
during execution often undermine their own claims later.
- Build causation
step by step. Strong claims link specific clusters of changes to measurable
impacts, supported by contemporaneous records.
- Beware of
overreliance on formulas. No single method, including measured mile, total cost, or otherwise,
will suffice in isolation. Use multiple approaches to triangulate the
truth.
- Anticipate
skepticism. Dispute resolution forums are wary of cumulative impact claims,
viewing them as attempts to shift unanticipated costs. Expect to face
rigorous scrutiny on causation.
Conclusion
Cumulative impact claims represent one of the most difficult frontiers in
construction disputes. They ask courts, arbitrators, and mediators to look
beyond individual changes and recognize a systemic effect that is hard to
quantify. Success hinges on causation: proving that inefficiencies were caused
by the accumulation of changes, that they were unforeseeable, and that they
were not the contractor’s own doing.
For attorneys, the implication is clear: these cases require careful strategy, strong documentation, and expert analysis that can withstand cross-examination. Without that foundation, even genuine disruption may fail to result in recovery.
[1] AACE International’s Recommended Practice RP 130R-23, Demonstrating Entitlement to Cumulative Impact Claims in Construction, provides additional detail in this area from a practitioner’s perspective.
Author Stephen P. Warhoe, PhD, PE, CCP, CFCC, FAACE, is a Senior Director at Arcadis and an expert in delay, disruption, and productivity loss on complex projects. He has nearly four decades in the construction field, is a university professor in construction management, and has testified extensively as an expert witness in construction disputes.
Editor Thanh Do, PhD, PE, is a Director at BRG's Global Construction Practice. He specializes in root cause investigations of structural failures, standard of care evaluations, construction and design defect analysis, Design-Build delivery, early dispute resolution, and trial visualization.
Tuesday, November 11, 2025
Contracting Chaos? How Mid-America v. US Department of Transportation is Upending DBE Certifications
Many states have enacted similar requirements governing state and local projects. Recently, the presumption of disadvantaged status has come under attack in Mid‑America Milling Company v. U.S. Department of Transportation[i] pending in the U.S. District Court for the Eastern District of Kentucky. The results of Mid-America represents a drastic change to the DOT’s DBE program for federal DOT contracting.
Any contractors bidding and working on DOT and other federal and certain state projects are familiar with DBE programs and take them into account while bidding projects with DBE goals. Some have even lost contract awards to DBE firms due to not receiving the presumption of DBE status. While the long-term implications of Mid-America are not clear, it will impact DBE status and how certain federal projects are awarded.
The Mid-America case began in October 2023 when plaintiffs, Mid-America Milling, LLC and Bagshaw Trucking Inc. (Plaintiffs), who both regularly bid on DOT funded contracts impacted by DBE goals filed suit against the DOT seeking a preliminary and permanent injunction and a declaratory judgment seeking to end the DBE program. Plaintiffs claimed that the DBE program violated the equal protections afforded under the Fifth Amendment of the United States Constitution. Neither plaintiff had a presumption of disadvantage status and had lost out on federally funded contracts to DBE firms even when their bids were lower. The Plaintiffs argued that the DBE program discriminated against them.
The Court found that the DOT’s DBE program had carved out preferences for only some minority groups (race and gender), it was not tied to any foreseeable conclusion, and it failed to be narrowly tailored. For these reasons, the Court held that the Government had failed to justify its discriminatory policies and the Plaintiffs would likely prevail on the merits of their constitutional claims. Ultimately, the Court found that Plaintiffs were entitled to a preliminary injunction. Plaintiffs requested that the DOT be enjoined from implementing the DBE’s race and gender presumptions nationwide. However, the Court denied such broad request for relief and limited the injunction to the Plaintiffs and later clarified the injunction as being applicable to any DOT contracts impacted by DBE goals upon which Plaintiffs bid in any state in which Plaintiffs bid on such contracts.[ii] In essence, the Court held that race and gender classifications and the presumption of disadvantaged status violate the Constitution’s guarantee of equal protection.[iii]
In 2025, the Government had changed its position and began to agree with Plaintiffs. The Government and Plaintiffs then submitted a Joint Motion for Entry of a Consent Order asking the Court to enter an order finding that the use of DBE goals in a jurisdiction where any DBE in that jurisdiction was determined eligible based on race or sex-based presumption violates the equal protection component of the Due Process Clause of the Fifth Amendment.[iv] There has been no ruling on this Joint Motion as briefing on this issue is still ongoing.
In response to the rulings in the Mid-America case, the DOT issued a proposed Interim Final Rule (IFR) effective October 3, 2025, to ensure that the DOT operates its DBE program in a “nondiscriminatory fashion” and in line with the Constitution.[v] The IFR eliminates the presumption that a business is “disadvantaged” solely because of the owner’s race or gender. Similar changes are reflected in 49 CFR §26.67. DBE participation requirements are also temporarily suspended and payments will not count towards DBE participation goals until the recertification process is completed. Some states have followed the IFR by suspending DBE goals on various projects, including Missouri, Virginia, and California until recertification of DBE contractors based on the new standards is completed.
With respect to DBE certifications under the prior rules, the IFR immediately suspends existing DBE certifications and requires previously certified DBE firms to submit new applications proving that they are eligible for certification under the IFR. The IFR requires each Unified Certification Program (UCP) to re-evaluate any currently certified DBE, recertify any DBE under the new certification standards, and to decertify any prior DBE that does not meet the new certification standards.[vi]
Under the IFR, to achieve certification, all applicants (new and previously certified applicants) must demonstrate by a preponderance of the evidence a social and economic disadvantage based on their own experiences and circumstances within American Society.[vii] Specifically, the IFR provides the following guidelines for an applicant seeking DBE certification:
(1) to satisfy the social and economic disadvantage requirement and ensure such determination is not based in whole or in part on race or sex, an applicant must provide a personnel narrative that establishes the existence of disadvantage by a preponderance of the evidence based on individualized proof regarding specific instances of economic hardship, systemic barriers, and denied opportunities that impeded the applicant’s progress or success in education, employment, or business,
(2) the personal narrative must state how and to what extent the impediments caused the owner economic harm, and must establish that the owner is economically disadvantaged relative to similarly situated non-disadvantaged individuals and
(3) the applicant must attach to the personal narrative a current personal net worth statement and any other financial information he considers relevant. To succeed in the recertification process, applicants must collect and submit the required financial documentation and ensure that their personal narrative clearly outlines the specific barriers that they have faced that justify DBE status. Remember the IFR is new to all parties involved including contractors and the various certifying agencies and it is key to maintain an open line of communication.
While the IFR did not provide detailed information on how UCPs should reevaluate existing DBEs, it is presumed that UCPs will follow current standards applicable for firms that were not presumed to be disadvantaged. Currently, there is no specific deadline by which a UCP must complete its reevaluation process. In fact, 49 CFR § 26.111 simply states that a UCP must reevaluate each currently certified CBE firm “as quickly as practicable.”
There is still a great deal of uncertainty about how the new standards in the IFR will impact DBE programs at both the federal and state levels. For Unified Certification Programs (UCPs), the required reevaluation process is entirely new, and they must interpret and apply these revised rules without delay. As a result, many UCPs are facing challenges in understanding how to administer their reevaluation responsibilities in order to avoid inconsistency and compliance issues. Ultimately, some currently certified DBE firms may not meet the new standards. As a result, they may be unable to participate in certain projects so that the pool of eligible DBE firms may decrease leading to a decline in DBE participation rates.
There is no doubt that the Mid-America case and related IFR will cause disruption to contractors on certain DOT and federally funded projects, but in the long run, there could be more opportunities as the DBE participation goals will likely drop. But keep in mind that the Mid-America case will be appealed and the ultimate outcome could change. In the interim, contractors wanting to maintain or achieve DBE status for various DOT projects should start the process of seeking certification or recertification based on the new standards established by the IFR.
Wednesday, November 5, 2025
AI as Co-Counsel: How Litigators Can Leverage AI for Depositions, Experts, and Trial Preparation
Sharper Research, Stronger Cases
Building
a strong case starts with a solid grasp of the legal concepts, which often means
thorough legal research at the outset. We have all heard cautionary tales of
lawyers submitting AI-drafted motions to the court that cite hallucinated (fabricated)
cases for propositions of law that don’t exist. But if used properly, AI can
enhance—not replace—traditional research methods.
AI
can help you come up with better search terms to get to the cases you need.
Start by defining the issue and breaking it into core components like the cause
of action or doctrine you want to research, key contract language or clause
types, procedural posture, remedy sought, and any industry‑specific
terminology. Then ask AI to generate jurisdiction‑specific term variants and draft
Boolean strings designed to target cases addressing your issue. Ask it to
include or exclude terms that commonly create false positives, suggest how
courts in your venue typically frame the concept, and flag time filters
tied to rule/law changes that may impact your results. You can incorporate key fact
patterns you think are material to the case’s holding and ask for search terms to
help identify similar fact patterns in the results. As you review your initial
search results, prompt AI to refine the terms and strategy.
Once
you have identified the key cases, AI can quickly and efficiently summarize
holdings, extract controlling standards, and highlight fact patterns most
analogous to your case. AI can also help you distinguish cases cited by your
opponent to use in response to motions or at hearings. But remember, treat the AI outputs as starting points: you should always verify
the law, read the full opinion, and Shepardize or KeyCite before relying on or
citing them for any proposition.
Crafting Case Themes That Stick
Once you have a solid legal foundation, you need a compelling narrative that resonates with a factfinder or judge. Every litigator knows that the most successful themes do more than summarize facts or legal issues—they evoke fairness, credibility, and common sense. AI can be a surprisingly effective sounding board for developing and refining your trial theme to one that sticks.
Start by giving AI a high-level overview of your case: the core claims and defenses (or include the pleadings), the key documents or facts, and your preliminary theory of the case. Then ask it to propose case themes from the perspective of your client, the opposing party, and even a neutral observer. By shifting perspectives, AI can help reveal which themes naturally align with the evidence and which sound forced or inconsistent. By anticipating the opposing party’s themes, you can create a strategy and develop evidence to counter that narrative.
Once you have several potential themes that support your case, use AI to suggest variations on the themes, test and strengthen them. For example:
- Support the theme with evidence: Ask AI to identify which documents, witnesses, or facts from your case best support each theme. If your message is that “the delay resulted from the general contractor’s failure to coordinate trades,” AI can flag the communications, reports, or schedules that most effectively illustrate that idea.
- Play
devil’s advocate: Ask how opposing counsel might frame the same facts
or what emotional counter-narrative a jury might find more compelling. The
exercise helps you anticipate and inoculate against those attacks at
hearings, in depositions, and ultimately, at trial.
- Sharpen
your messaging: AI excels at distilling complex ideas into concise,
impactful phrasing. You can prompt it to make your theme more memorable, approachable,
or emotionally resonant. For example, I recently used AI to help weave a trial
theme into an opening statement I drafted, and it suggested some memorable
one-liners to include throughout that reiterated the theme and drove
home the points I wanted the factfinders to remember.
Litigators should always treat AI outputs as brainstorming sessions. Critically analyze the results and decide which theme feels authentic to you and your client and aligns with the facts, tone, and posture of the case.
Depositions and Expert Reports with Fewer Blind Spots
Deposition preparation is one of the easiest ways to incorporate AI into your litigation practice. Lawyers can shave hours off their preparation by using AI tools to isolate a single issue or topic from voluminous discovery documents, summarize prior depositions, and create charts on key issues. AI can generate a timeline of key events or summarize a lengthy document for you to easily reference throughout a deposition or in witness preparation. For example, within seconds, it can extract and create a chart of all contract provisions on specific topics like change order requests or scheduling requirement; it can also breakdown each witness/party’s position on an issue like who they claim is responsible for the defective condition.
You can also use AI to prepare your fact or expert witnesses for their testimony. Ask AI to analyze prior deposition transcripts or reports and flag inconsistencies or vulnerabilities. Most of the outputs will be ones you’ve already identified and prepared for, but it will likely generate a few ideas you had not previously considered. Prep your client for how to handle those issues. AI can even create a mock cross-examination and generate questions in a variety of tones. This can be used by your colleagues to conduct a mock cross examination of your client.
Construction cases usually involve technical or data-heavy expert testimony. AI is an issue-spotting tool that you can use both offensively and defensively for expert reports and depositions. For example, before finalizing your expert’s report, ask AI to identify any analytical gaps or flag any inconsistencies within the report and challenge the conclusions from the opposing parties’ perspective. You can then address any shortcomings before finalizing the report—and before a Daubert challenge. AI also cuts down on the time it takes to synthesize CVs, expert publications and sources, prior Daubert rulings, and court opinions in order to identify impeachment angles. While AI cannot replace the expert (or lawyer’s) judgment, it accelerates the review process, helps lawyers ask sharper, more informed questions, and eliminates the element of surprise for your witnesses.
Ethics and Guardrails
As with any litigation tool, traditional ethical rules still apply. AI’s efficiency is no substitute for professional judgment, supervision, or confidentiality. Lawyers should never upload client materials to public systems and should only use secure, firm and client approved AI platforms to protect privileged and confidential data. And as mentioned above, you should always verify the results. AI can misinterpret nuances that lawyers know matter—words like “delay,” “impact,” or “notice” may carry specific legal significance that AI does not pick up on. Treat AI as a non-lawyer assistant that requires attorney oversight. Use it to expand your creativity, see the case from various perspectives, and make your advocacy more persuasive.
Debrán O’Neil is a litigation partner in Carrington, Coleman, Sloman & Blumenthal, L.L.P.’s construction practice group in Dallas, Texas. She primarily represents manufacturers and public and private owners and developers in connection with the construction of large commercial and infrastructure projects throughout Texas. She can be reached at doneil@ccsb.com.


