In
Blois Construction, Inc. v. FCI/Fluor/Parsons, the defendant entered into a
contract in 2006 with Exposition Metro Line Construction Authority (owner) to
serve as the general contractor for a light-rail project that connected
downtown Los Angeles with Culver City. Defendant in turn subcontracted with
plaintiff for the associated underground work on the project. The prime
contract allowed the owner to withhold 10 percent of the progress payments in
retention and a subcontract provision allowed the defendant to withhold 10
percent of the plaintiff’s payments in retention. The retention provision in
the prime contract allowed for the 10 percent retention to be waived at the
sole discretion of the owner when the project was 50 percent complete. In December 2009, defendant requested that
the owner stop withholding retention and the owner agreed with the caveat that
it maintained the right to resume withholding at a later time. The owner
continued to withhold all previously collected retention and did so until May
30, 2014.
The
plaintiff completed its contract work in 2011 by which time $500,000 of its
progress payments had been held in retention by the defendant. In 2012, plaintiff filed suit against the
defendant and its sureties for 1) extra work on the project that it had not
been paid for and; 2) for the balance of the retention on the contract. The
suit was referred to a dispute review board by the courts for arbitration. In November 2013 while the case was still
pending before the board, the defendant released $534,909.89 in retention to
the plaintiff. The board ruled that all
retention the defendant withheld had been required to be paid by September 2011
under the terms of the subcontract. The
board left the issue of penalties for late payment to the courts. The trial
court decided that no penalties were to be incurred because the owner had not
released retained funds to the defendant until 2014 and the plaintiff had been
paid its full amount of retention by the end of 2013. The plaintiff appealed.
The
Court of Appeals of California, Second District, Division One started its
analysis by identifying the language in California’s ‘prompt payment’ statute.
California Public Contract Code Section 7107 states "within seven days
from the time that all or any portion of the retention proceeds are received by
the original contractor, the original contractor shall pay each of its
subcontractors from whom retention has been withheld, each subcontractor's
share of the retention received." The code further identifies penalties to
prime contractors who do not adhere to this this time frame by stating that
contractors who violate the code section, “shall be subject to a charge of 2
percent per month on the improperly withheld amount."
The
plaintiffs argued that as a result of the change in payment terms where
retention was no longer held on progress payments after December 2009, this
constituted the “retention proceeds [being] received by the original
contractor” and as a result defendant was required to pay the plaintiff its
share of retention proceeds within seven days.
Plaintiff argues that by allowing the defendant and similarly situated
prime contractors to continue to withhold retainage from subcontractors after
the owner stops withholding would run counter to the spirit of the ‘prompt
payment’ law.
The
Court states that the defendant’s argument fails because Section 7107 is not
applicable in this instance. The court points to the fact that even though the
owner did stop withholding retention funds starting in 2010, it still withheld
all previously withheld retention. The court then points to an alternate
‘prompt payment’ statute, Business and Professions Code section 7108.5, to
discount the plaintiff’s “spirit of the law” argument. Section 7108.5 requires a prime contractor to
pay its subcontractors “not later than seven days after receipt of each
progress payment, unless otherwise agreed to in writing, the respective amounts
allowed the contractor on account of the work performed by the
subcontractors." The court finds
that there is no evidence that the defendant did not adhere to this code
section post December 2009 retention agreement and both “prompt payment”
statutes “operated in tandem to ensure that there was no point at which
[defendants] could receive payments from [owner] without paying [plaintiff] and
other subcontractors their share of the proceeds.”
The
court found that as a result of the defendant not receiving retention proceeds
from the owner until at least May 30, 2014, its obligation to pay plaintiff its
share did not arise until that date and Section 7107 was satisfied when it paid the
plaintiff in November 2013. The ruling
of the trial court was affirmed.
------------------
The author, Brendan Carter, is a contributor to The Dispute Resolver and a former Student Division Liaison to the Forum on Construction Law. He is an attorney and a Senior Consultant with Navigant’s Global Construction Practice based out of Boston, MA. He may be contacted at 617.748.8311 or brendan.carter@navigant.com.
No comments:
Post a Comment