COURTHOUSE REPORTER SERIES: Not Everything Is Bigger in Texas... Court of Appeals Reverses Trial Court’s Expansive Interpretation of Indemnity Clause


A recent decision by the Court of Appeals of Texas, RKI Exploration & Production, LLC v. Ameriflow Energy Services, LLC, highlights the perils of failing to properly assert a demand for contractual indemnity. No. 02-20-00384-CV, 2022 Tex. App. LEXIS 4331 (Tex. App. June 23, 2022).

In 2014, a piece of equipment, known as a sand separator, exploded at an oil well in Loving County, TX, killing two individuals and injuring three others. RKI Exploration & Production LLC operated the oil well. RKI contracted with Ameriflow Energy Services LLC and Crescent Services LLC through two master service agreements (MSAs) and a series of work orders.

Ameriflow supplied equipment and services to the wellsite, including the explosive sand separator. Crescent provided safety training and management services to Ameriflow. Notably, it was unclear whether Crescent supplied those services under a subcontract agreement with Ameriflow or whether the two entities were somehow affiliated. It was undisputed Crescent did not perform those services under its MSA with RKI or an associated work order.

The explosion and resulting dispute produced a “maze-like series of indemnity demands, settlements, and judgments” among the injured individuals, RKI, Ameriflow, and Crescent. The dispute culminated in tri-party litigation to determine RKI’s indemnity obligations to Ameriflow and Crescent under their respective MSAs. Broadly construing the indemnity language of the Crescent MSA, the trial court held that Crescent was entitled to indemnity from RKI and awarded Ameriflow and Crescent approximately $11 million.

The Court of Appeals considered, inter alia, whether the lower court had erred by broadly construing the Crescent MSA indemnity clause to encompass claims against Crescent, even though Crescent was not performing under the MSA at the time of the explosion.

RKI argued that because the MSA contemplated that Crescent would perform work pursuant to RKI work orders, and RKI had not issued any work orders at the time of the explosion, Crescent was not performing under the MSA, and therefore, it was not entitled to contractual indemnity from RKI.

Crescent argued that the MSA provided that RKI was to indemnify Crescent against all claims “arising in connection herewith” and a claim arising from Crescent’s supply of safety training and management services to Ameriflow “arose in connection with” — if not under — the Crescent MSA. According to Crescent, the phrase “arising in connection herewith” obligated RKI to indemnify Crescent for any claim arising from “all activities reasonably incident [to] or anticipated by the principal activity of the MSA, which is oil well operation.”

The court began with an extensive review of Texas and federal case law, interpreting the terms “arising” and “in connection herewith.” The court then reasoned that the phrase “arising in connection herewith” meant “originating from the document or writing in which the phrase is contained” rather than the broader view espoused by Crescent and adopted by the trial court. Applying this definition to the MSA, the court concluded that RKI’s indemnity obligations to Crescent were limited to Crescent’s performance under the MSA.

The court explained that the trial court’s interpretation was overly broad because it “untether[ed] the indemnity obligation from the contract containing the provision and [brought] activities independent of the contract within the scope of the indemnity provision simply because they relate to the general subject of the contract.” Such an interpretation would allow Crescent to perform “work for anyone at the wellsite, in as slipshod a manner as it wished, and still claim that RKI owed it indemnity.” The court concluded that because RKI’s indemnity obligation to Crescent was limited to Crescent’s performance under the MSA and because Crescent’s services to Ameriflow were not authorized by an RKI work order, Crescent was not entitled to indemnification from RKI.

The court noted that Crescent may have been entitled to contractual indemnity from RKI as an Ameriflow subcontractor under the terms of the Ameriflow MSA. But because Crescent did not raise this argument and because the precise relationship between Crescent and Ameriflow was unclear, the court could not rule on the issue. Thus, Crescent’s failure to assert its claim through the framework of its relationship with Ameriflow may have barred it from recovering contractual indemnity to which it would otherwise be entitled.


*This blog article was previously posted on Troutman Pepper Hamilton Sanders LLP's construction law blog, ConstructLaw.com.

Author Brendan Kirwin is an associate in Troutman Pepper's construction practice group. He focuses his practice on representing and counseling owners and developers in all manner of complex construction transactions.

Editor Jane Fox Lehman is an associate in Troutman Pepper's construction practice group. She has substantial experience representing a variety of construction industry players in disputes arising from industrial, commercial, and multifamily-residential construction projects. Jane is the co-editor of the firm’s construction law blog, ConstructLaw.com.

Tuesday, January 24, 2023

Meet D1’s Neutrals Series: JESSE HOWARD WITT

 

Company:
 Frascona, Joiner, Goodman & Greenstein
Location: Boulder, Colorado
Email: jesse@frascona.com
Webpage: https://frascona.com/jesse-witt/
Law School: University of Denver School of Law (JD 2001)
Types of ADR services offered: Mediation, arbitration, neutral evaluation
Areas served: Colorado, California, and others as requested


Q: Describe the path you took to becoming an ADR neutral.

A: As my career has progressed, I find myself more interested in helping parties find solutions than “winning.”

Q: What percentage of your current legal practice is spent on ADR work?

A: 10%. When not serving as a neutral, I work as an advocate and represent parties in litigation.

Q: Describe your background and experience mediating and arbitrating construction cases.

A: I worked in the construction field before and during law school. Since then, I have focused on construction law over the last twenty years as an attorney. I feel this gives me a helpful perspective when mediating disputes, with an understanding of the parties’ diverging perspectives and the realities of litigation.

Q: Mediators are oftentimes described as “facilitative,” “evaluative,” or “transformative.” Do you have a style?

A: I tend to be evaluative in my assessment of the parties’ claims and defenses.

Q: What should attorneys and their clients take into consideration when selecting a mediator?

A: Seeking someone with experience in the given area of law is always a good starting point. I feel that my experience both in the construction field and as a trial attorney makes me an effective mediator of construction disputes.

Q: What are your thoughts on requiring mediation as a contractual prerequisite to litigation or arbitration?

A: I think it is prudent to include such a term to encourage resolution, but parties must be committed to the process. If either side views mediation as a perfunctory requirement, the ADR process is unlikely to be successful. I recommend that parties attempt mediation as soon as they have a clear understanding of the claims at issue.

Q: What can attorneys do to best position their clients for a successful mediation outcome?

A: Provide their clients with a realistic assessment of their cases’ strengths and weaknesses.

Q: Are virtual mediations as effective as in-person mediations? What are their advantages/limitations?

A: I prefer in-person sessions, but virtual mediations can be effective as well, so long as the parties commit to the process. The advantages of virtual sessions are that they can be easier to schedule and feature reduced travel expenses, both of which may encourage earlier resolution. Disadvantages include the difficulty in building rapport with the parties and the risk that parties will be less committed to the process. In this regard, the ease and cost savings of a virtual session can ironically become a disadvantage.

Q: Do you think limits should be placed on discovery in the arbitration context?

A: Yes. When drafting arbitration clauses, I often adopt Colorado’s discovery parameters for simplified procedure cases (Rule 16.1) regardless of the amount in controversy. I have found that these strike a good balance for most disputes.

Q: What is the biggest problem you see with arbitration today?

A: Parties too often view arbitration as little more than a limitation on liability to consumers, under the belief that arbitrators will award less than juries. This leads to poorly drafted arbitration clauses that incorporate court rules and result in proceedings that amount to little more than private bench trials. Arbitration is most effective when used as a tool to facilitate resolution using expedited procedures, focused discovery, and neutrals with experience in a given field. Arbitration should not feel skewed against consumers; if done properly, arbitration can be beneficial to both sides and produce a just outcome for many construction disputes.

Q: What are some of your interests or hobbies outside of your ADR Neutral practice?

A: Tennis, running, film.

Thursday, December 22, 2022

What's Up With Division 1 (No. 18) -- Happy Holidays and Happy New Year!

Quite a bit has occurred since my last message from the Division 1 Chair, which was just before the Fall 2022 Meeting in Memphis, TN.  I will do my best to summarize the highlights but I wanted to start by saying HAPPY HOLIDAYS to all of Division 1's leaders and members.  I hope you are able to take some time off and enjoy the holidays with your family and friends.  I am very proud of what we have accomplished in 2022 and look forward to further collaboration with you all about construction litigation and dispute resolution into 2023 and beyond! 

Fall Meeting -- Memphis, TN (Sept. 28-30)

The Peabody Hotel was awesome!  The lobby was huge and very comfortable.  Full of southern charm.  The Forum Chair, Cary Wright, served as honorary duck warden (forget the real name).  A video of that is below:


We had a great dinner at Itta Benna, a hidden away restaurant located at the top floor of BB Kings.  Thanks to Mike Lane for scheduling this fabulous dinner and Breakwater Forensics LLC for sponsoring it.  Here are some photos:





We held the first of the 3-part trial advocacy practicums in Memphis.  They focused on jury selection.  Jason Rodgers-da Cruz led the planning effort for this program.  He was joined by Stu Sobel (last minute substitute due to Lu Prats having to deal with the Hurricane), Galina Davidoff, and Terry Brookie. 


Our lunch program, planned by Brett Henson and Jade Davis, on early dispute resolution was postponed because they are both based out of Florida and were dealing with Hurricane Ian.  We split up into different division lunches.  

We held Division 1’s annual planning retreat in Memphis.  We came up with a ton of excellent ideas for the concepts book and discussed some new ventures to try out.  Thanks to everyone who attended!  

Here are some other photos from the meeting.





Division 1 — Extreme Winds Program

Speaking of natural disasters involving wind, shortly after my last message, we held a fantastic virtual program on wind events.  This was a technical program.  It was very interesting and is full of videos.  I recommend you watch it if you have not already done so.  Thanks to Mike Lane for coordinating this program!


Division 1’s Toolbox Talk Series Programs - Sept, Oct, Dec

Just before the Fall Meeting, on September 22, 2022, we held a Toolbox Talk Series program on Ethical Conduct for Advocates and Neutrals (Rules and Remedies for Mediation Misconduct).  Thanks to Patricia Thompson and Deborah Ballati for leading this discussion.  Check out the video here:


We held Toolbox Talks in October and December as well.  October’s was on the Design-Build Standard of Care and led by Thanh Do and Joel Heard (partnership with Division 4).  I tagged along with Catherine Delorey and Mark Johnson for the December TTS on Strategies to Defeat or Mitigate Attorney’s Fee Prevailing Party Provisions.  




Both were great programs.  Kanita Williams, our most recent steering committee member, is going to lead the 2023 Toolbox Talk Series of programs.  Thanks to all the volunteers who made these programs a success.  

Division 1’s Arbitration Program with Division 8 - Nov. 10th

Division 1 and Division 8 agreed to collaborate on some programs.  The first of the programs was a virtual program on arbitration comparing domestic vs. international practices.  Pasha Ameli has been the D8 leader/liaison working hard to make these programs a success.  He moderated the panel of speakers (R. Zachary Torres-Fowler, Marcus Salvatore Quintanilla, Merra Kurubalan, and Patricia H. Thompson).  Thanks to Pasha, the speakers, and Division 8 for this program! 

The Dispute Resolver Posts

I am assuming you know about the TDR posts if you are reading this message, but I would be remiss if I didn’t mention that the following has been posted on TDR since the Fall Meeting:
  • D1 Neutral Feature - Robbie MacPherson
  • View from the Field Part 5 - Field Labor Disruption
  • Jurisdiction - Employee Training, Alone, May Subject You to a Foreign State’s Jurisdiction 
  • Pennsylvania Superior Court Places Time Limit on Good Faith Withholding Under Prompt Pay Act
  • Contractual Claims Protection: A Checklist for Owners
  • D1 Neutral Feature - John Bulman
  • Twists and Turbines - A New York Case Highlights an Owner’s Risk When Not Using Full-Wrap EPC Delivery
I want to thank all of the authors, editors and contributors of TDR.  After serving as the editor in chief of TDR for the past years, Catherine Delorey is going to hand-off the lead editor role to Marissa Downs.  Thanks very much Catherine for your work for TDR.  We launched some fun and different series since you have served as editor.  Congrats Marissa and I look forward to working with you on TDR as well as the new editors we are bringing on board.  

If anyone has an interest in being published in The Dispute Resolver, please reach out to Marissa Downs (mdowns@lauriebrennan.com) or Tom Dunn (rtdunn@pierceatwood.com).  

Forum’s Midwinter Meeting — Feb 1-3, 2023 (Caribe Hilton Puerto Rico)

Join us at the midwinter meeting (just about 1 month away!).  REGISTER HERE.


Joe Imperiale is leading the second practicum in the trial advocacy series on openings and direct examination.  Arrive early so you can attend the practicum on Wednesday.  


Marissa Downs is planning our social event which will be at the Casa Bacardi on Wednesday afternoon.  Be on the lookout for the registration info for that program, but it will include a mixology class, a tour, and reception sponsored by our friends at Construction Discovery Experts.  

Have a great end of 2022!   

Tom Dunn, Division 1 Chair
rtdunn@pierceatwood.com
401-490-3418




 

Monday, December 19, 2022

COURTHOUSE REPORTER SERIES: Twists And Turbines: A New York Case Highlights an Owner's Risk When Not Using Full-Wrap EPC Delivery

 New York State Thruway Auth. v. CHA Consulting, Inc., 165 N.Y.S.3d 832 (Albany Co., Sup. Ct. 2022).

This case involved a dispute over a wind turbine project. The root cause of the dispute was a bust between the “wind turbulence” at the site, and the wind turbulence that the turbines installed could withstand. Once the project was completed and commissioned, the overworked turbines prematurely failed.

The New York State Thruway Authority (the owner) sued CHA Consulting, Inc. (the designer), the Kadney Company (the general contractor), Vergnet (the turbine supplier), and two different site engineers: Prudent Engineering, and Ravi Engineering and Land Surveying (the engineers). The New York Supreme Court (New York’s trial court) dispatched all of the owner’s claims on summary judgment.

The designer, which had specified the wrong type of turbine, invoked New York’s three-year statute of limitations to defeat the owner’s professional negligence claim. The owner argued that the statute should run from the date of its acceptance of the work and issuance of a final certificate. But the statute makes clear that it runs from the professional’s “completion of performance under the contract.” With the designer out of the picture based on the timing of its work, the owner’s creative attempts to hold others responsible fell flat.

The general contractor defeated the owner’s claims because the designer specified the exact make and model of turbine, and the general contractor procured and installed those exact turbines. It was not the general contractor’s responsibility to verify that the turbines were suitable for the site, therefore the general contractor could not be held responsible. Even if the general contractor was somehow responsible for the verification, the owner accepted the general contractor’s work during inspection, and found it in general conformance with the contract plans and specifications.

The turbine supplier defeated the owner’s warranty claim because its warranty contained an exclusion when the site conditions were the cause of the issue. The owner argued that the turbine supplier should be estopped from taking advantage of the exclusion because it did not verify that the turbines were suitable for the site conditions. The Court disagreed, finding that the warranty did not create any duty for the turbine supplier to independently verify suitability. The various disclaimers in its contract were a further backstop against this argument.

The engineers defeated the owner’s claims because the Court found that their obligations were limited to confirming that the turbines supplied were the same as the turbines specified. The Court made this ruling primarily because the specification at issue was a “closed proprietary specification, with no substitutions allowed.” Had a less-detailed and more traditional performance specification been used, the engineers would have had greater responsibility to verify conformance.

In conclusion — it is not uncommon for an owner to separately contract with the major players on a construction project, as opposed to entering a full-wrap EPC agreement, but such an arrangement presents certain risks. Two of the most notable risks are scope gaps, and as demonstrated in this case, liability gaps. The designer in this dispute was able to avoid liability because its work was complete long enough before the problem was discovered that the statute of limitations had run, which left the owner without a party to pursue. A full-wrap EPC agreement would likely have allowed the owner to avoid this situation.

*This blog article was previously posted on the Troutman Pepper website.

Author Todd Heffner is an Associate with Troutman Pepper in its Atlanta office.  His practice covers construction matters, including in federal court and arbitration.

Wednesday, December 7, 2022

Meet D1’s Neutrals Series: JOHN E. BULMAN


Company:
 Pierce Atwood LLP
Location: Providence, Rhodes Island
Email: jbulman@pierceatwood.com
Webpage:  https://www.pierceatwood.com

Law School: Georgetown University Law Center, J.D., cum laude;Editor, Law and Policy in International Business (1984)
Types of ADR services offered: Mediation, Arbitration, Dispute Review Boards, Online Dispute Resolution (ODR)
Areas served: Nationwide
Affiliated ADR Organizations:
        American Arbitration Association (AAA)
International Institute for Conflict Prevention & Resolution (CPR)
International Centre for Dispute Resolution (ICDR)
College of Commercial Arbitrators (CCA)
Chartered Institute of Arbitrators (CiArb)
Rhode Island Superior Court
Rhode Island Federal District Court
International Chamber of Commerce (ICC)


Q: Describe the path you took to becoming an ADR neutral.

A: Early in my career, I was an advocate in several AAA construction-related arbitrations.  The AAA saw fit to add me to its Panel of arbitrators around 1990.  Since then, I have served as an arbitrator or mediator in approximately twenty states.

Q: What percentage of your current legal practice is spent on ADR work?

A: 90% or more of my time is spent as a neutral.

Q: Describe your background and experience mediating and arbitrating construction cases.

A: I have served as a mediator in over 100 construction cases since 1990. I have served as an arbitrator and rendered awards in at least fifty arbitrations, ranging from $500,000 to $220,000,000 in controversy.   Most of the larger cases have been three-arbitrator panels; I have served as chair in the majority of those cases.

Q: Mediators are oftentimes described as “facilitative,” “evaluative,” or “transformative.” Do you have a style?

A: Each case calls for a specific emphasis and/or technique but I certainly lean toward facilitative negotiation.

Q: Do you have any practices that you find make you particularly effective as a mediator?

A: Asking open-ended questions to prompt each party to fully articulate not only the merits of the case but also how counsel expects to meet the other side’s defenses or counterclaim.

Q: Do you recommend individual preparatory meetings with the parties and counsel prior to the joint session?

A: Yes. Gaining a better understanding of the dispute background and prior settlement discussions saves time and energy at the mediation session itself.  It also preempts “going down the wrong road” at the mediation.

Q: What should attorneys and their clients take into consideration when vetting and/or selecting an arbitrator?

A: The arbitrator’s subject matter expertise and ability to manage the process efficiently.

Q: What advice do you have for parties when considering whether to choose a single arbitrator or a panel?

A: Cases with a large amount in controversy or where the technical expertise of a particular arbitrator is important are cases where a three-member panel is effective and appropriate.  Cases with several parties are also situations where a three-member panel is appropriate.

Q: Do you think limits should be placed on discovery in the arbitration context?

A: There should be limits since arbitration is not supposed to be a mirror image of litigation.

Q: What role should traditional rules of evidence play in the arbitration hearing?

A: By the time hearings take place, there should be a limited number of exhibits that are in controversy.  This is the only time when the “rules of evidence” have a bearing, and they have a limited bearing.

Q: What are some of your interests or hobbies outside of your ADR Neutral practice?

A: Furniture making and fly-fishing.

Monday, November 28, 2022

Contractual Claims Protection: A Checklist for Owners

More and more public owners have come to the realization that their general conditions and “front-end” documents are inadequately protecting them. Here is a checklist of clauses for owners to consider including in contracts for protection against potential construction issues. The following, in no particular order of importance, are brief summaries of some of the key clauses that owners should consider including in their contracts.


Notice Provisions – These provisions require the contractor to provide the owner with prompt notice of an alleged change, delay, claim for additional compensation, or differing site condition. A well-drafted clause will strive to bar claims that did not comply with the notice provisions because the owner can argue that there was a lack of notice to be able to respond. The purpose of such provisions is to give the owner an opportunity to adequately investigate the situation in order to verify (or rebut) the contractor’s contention and to actively participate in the resolution and monitoring of the work. In the case of an alleged differing site condition, the notice requirement should be one of immediate notice, since an owner investigation is likely essential to protect evidence of the condition and to determine how the affected work will proceed.

Differing Site Conditions – It is important to define what a differing site condition is and how it will be treated should one be encountered during construction.  This clause is particularly important in projects involving significant earthwork, tunneling, work in highly developed areas or renovation projects due to the increased likelihood of encountering susceptible conditions unknown to the designer and bidders.

Scheduling Requirements – Owners must take a more active role in monitoring the contractor’s schedule submittals in order to protect against potential improper schedule manipulation which could lead to inflated delay claims.  In order to achieve this, owners must first have a solid specification with a mandate that requires the contractor to submit regular and meaningful schedule data.  The areas which the specification should cover include, at a minimum:

·       Technical requirements for the initial baseline submittal and updates

·       Review/acceptance procedures and timeframes

·       Updating and revisions requirements

·       Treatment of “early completion” schedules

·       Inclusion of submittals and procurement activities in the overall schedule

·       Means of submitting requests for time extensions, i.e., fragnets

Audit Provisions – An owner can obtain extremely valuable information for evaluating or rebutting a contractor’s change orders and claims by gaining access to the full volume of the contractor’s records, including all cost records and correspondence with subcontractors.  General contractors almost always have access to the public owner’s records by virtue of public records statutes, but often an owner can only get access to a contractor’s records after a formal litigation process has been initiated.  A well-drafted audit or access to records clause can provide the owner with the contractual right to have access to all the contractor’s and subcontractors’ records at all stages of construction, thereby giving the owner much more information to utilize when assessing a request for change order or a claim demand.

Defined Mark-ups – Many disputes arise because contract provisions are not clear as to what is or what is not included within a contractor’s and subcontractor’s mark-ups and what is allowable under the contract.  Better defined provisions will take away the guesswork and arguments associated with this common problem and will decrease the chances that an owner pays for “double-dipped” overhead on extra or changed work.

Escrow of Bid Documents – This is a procedure used on large projects whereby the contractor is required to place all of its bid preparation materials into an escrow.  Then, if a change order or claim arises that brings the contractor’s bid or original plan of performance into question, the owner and contractor can jointly review the bid documents to determine whether they support the contractor’s performance.

Claim Submittal Requirements – Often, owners are frustrated at the end of a project when the contractor submits a disjointed omnibus claim or a claim with too sparse details that it is virtually “non-analyzable”. The addition of a claim submittal clause can formally specify the format, content and level of back-up documentation that is required within the contractor’s claim to be valid; otherwise, it will be rejected until it meets the contract requirements.  

Liquidated vs. Actual Delay Damages – When drafting contracts, owners are faced with a choice in deciding how they are going to address the possibility of contractor-caused delays that extend a project completion date. The Owner can elect to include a liquidated damages provision which is a pre-determined amount included in the bid documents that “fixes” the contractor’s daily exposure or liability for contractor-cause delays. The other option is for the owner’s contract to be silent regarding the amount of damages that the contractor would be liable for in the event of a delay.  In that case, the owner could claim all reasonable, foreseeable damages caused by the contractor’s delay.

Limitations on “Early Completion” Damages – Another damages-related area where an owner can protect itself is in limiting the types of damages a contractor can claim in the event of owner-caused delays or disruptions.  One type of claim that is quite prevalent is “early completion” whereby the contractor alleges that it would have finished the project earlier than the required contract completion, but the owner caused the delay, so the contractor is thereby entitled to the extended overhead costs. Owners can include clauses in their contracts that prohibit the recovery of damages based on missed early completion dates, forcing bidders to accept language that specifically acknowledges this premise.  A contractor may argue that in the public sector such a clause is rendered unenforceable under certain state-enacted statutes, which essentially makes wholesale no-damages-for-delay clauses difficult to sustain. However, the distinction that the clause only limits a contractor’s right to claim for early completion delays is not a wholesale denial of liability for all owner-caused delay similar to most typical no-delay-for-damages clauses.  Like any contract provision that restricts a contractor’s ability to recover, the mere potential for disagreement should not hinder an owner from including such a clause in its contracts.   

Defining Submittal Review Times – An area of frequent dispute and delay allegations involves the time taken by owner’s representatives to review required contractor submittals.  When a contract is silent about how long an owner’s representative has to review submittals, there is often a difference of opinion as to what a reasonable review period is. This can result in protracted arguments and even claims.  An easy way to address this from the outset is to simply specify in the bid documents the timeframe, (e.g., 20 calendar days) that the owner has to review submittals.  This forces the contractor to schedule its work accordingly based on the assumption that the owner contractually has “X” number of days for review.  Consideration should also be given in the specifications as to whether the review “clock” fully or partially starts over when a submittal is properly rejected and has to be resubmitted/re-reviewed.  In addition, owners should consider prohibiting the transmission of a large number of submittals simultaneously which could effectively overwhelm the owner’s project staff.  

Estimating Requests for Information (RFI) Times and Volume – Often, claims by contractors include allegations devoted to “untimely responses” or “excessive volume” of RFIs. Both of these subjects can be addressed by the owner in the contract.  The first, dealing with turnaround time, can be resolved by simply specifying a contractual turnaround time.  Many owners accuse contractors of failing to plan their work ahead and then demand instantaneous responses to RFIs.  To fairly set the turnaround time, the owner must take into consideration the complexity and duration of the project.  With regard to the volume of RFIs, a clause can be put into the contract stating that the contractor should expect “X” number of RFIs. This way, the owner can establish a reasonable baseline for denying “excessive” RFI-related claims and establish a baseline for contractor expectation.  The owner must also be on the lookout for contractors that may submit unnecessary RFIs to circumvent the baseline. 

The contract provisions discussed in this article are only a handful of the key clauses that an owner should consider to help protect against untimely or inflated claims. Because each project brings a different set of circumstances and complexities, it is always advised that owners engage a construction claims expert as early as possible to resolve potential issues arising on a project.


Mark Guevara, Esq., CFCC, PSP, PMP is a Principal Claims Analyst with ARCADIS and has over 35 years of experience in the areas of construction dispute and claims analysis and resolution.  He has appeared before dispute review boards, panels, mediations, trial and appellate courts, and has testified as an expert witness. He served as Chairman of the Certified Forensic Claims Consultant (CFCC) Certification Board, AACE International (AACEi) and currently serves as Chairman (Elect) of the Construction Law Section, Orange County Bar Association.

Tuesday, November 15, 2022

Pennsylvania Superior Court Places Time Limit on Good Faith Withholding Under Prompt Payment Act

Constructural Dynamics, Inc. v. Thomas P. Carney, Inc., No. 1104 EDA 2021, 2022 Pa. Super. Unpub. LEXIS 1500, 2022 WL 2390125 (Pa. Super. July 1, 2022), reargument denied (Sept. 8, 2022).

Like many prompt payment acts, Pennsylvania’s Contractor and Subcontractor Payment Act (CASPA) permits owners and contractors to withhold payment for good faith claims — but not forever. Owners and contractors who wait too long could find themselves litigating prompt payment claims and paying the penalties those acts impose on procrastinating payors. A recent decision by the Pennsylvania Superior Court provides some guidance on how long is “too long” to withhold.

The decision arose from a breach of contract action by concrete supplier Silvi Concrete Products, Inc. (Silvi) against contractor Thomas P. Carney, Inc. (Carney). Silvi supplied concrete to Carney for the construction of a Philadelphia luxury hotel. Initial tests of Silvi’s concrete indicated that it broke at lower-than-expected compression strengths. Carney immediately terminated Silvi and hired a replacement supplier. Supplemental testing was conducted, during which Carney withheld payments to Silvi. The project engineer ultimately accepted Silvi’s concrete. Even after acceptance, Carney continued to withhold payment.

Silvi filed a complaint against Carney, alleging breach of contract, violation of CASPA, and unjust enrichment. Carney counterclaimed for breach of contract. A jury found in favor of Silvi on its breach of contract claim and awarded its unpaid $160,000 contract balance and $1 million in lost profits. In a subsequent bench trial, the court denied Silvi’s CASPA claim, finding that Carney had withheld payment in good faith. Carney appealed, and Silvi cross-appealed.

Silvi asserted that the trial court abused its discretion in denying its CASPA claim. It argued that in finding that Carney breached the parties’ contract, the jury implied that Silvi’s CASPA claim was valid. Silvi also argued that Carney did not prove that the amount it withheld was reasonably related to the value of its claim.

The appeals court concluded that the jury’s finding that Carney breached the contract was irrelevant to the validity of Silvi’s CASPA claim. Despite the breach, Carney had good faith basis for withholding payment — at least initially. And the amount withheld ($160,000) was reasonable since it was significantly outweighed by the potential cost to remove and replace the concrete ($13 million to $19 million). The court remanded for the trial court to reexamine whether Carney’s withholding after the project engineer accepted the concrete was in good faith, and whether Silvi could receive CASPA penalties as a result.

In its cross-appeal, Carney argued that the trial court erred by allowing Silvi to present evidence of its lost profits because its claim for lost profits was in essence a “lost volume seller” claim. Pennsylvania disallows “lost volume seller” claims because “[a]pplication of the doctrine would encourage the non-breaching party to do nothing to minimize its damages.”

The appeals court rejected Carney’s argument. Despite disallowing “lost volume seller” claims, “Pennsylvania permits a non-breaching party that has reasonably attempted to mitigate its damages to recover damages for lost profits.” The trial court specifically found that Silvi “made every reasonable effort to mitigate the lost sales and damages it suffered at the hands of Carney by reselling the material, thereby fulfilling the non-breaching party's duty to mitigate losses.” The trial court thus properly allowed the lost profits evidence.

Author Rachael Cain is an associate in the Litigation practice of Troutman Pepper Hamilton Sanders LLP, and a member of the Construction practice group. Prior to joining Troutman Pepper, Rachel served as Land Use and Real Estate General Counsel for Building & Land Technology. Her experience includes negotiating and drafting construction, design, architectural, and service contracts, as well as presenting zoning applications. Rachael has experience in both litigation and transactional matters and has appeared in state and administrative courts. 

 Author Jane Fox Lehman is an associate at Troutman Pepper Hamilton Sanders LLP, and a member of the Construction practice group. Jane has substantial experience representing a variety of construction project participants in disputes arising from industrial, commercial, and multifamily residential construction projects. In addition to representing clients in state and federal courts and alternative dispute resolution proceedings, Jane assists clients with bid protests, contract review and negotiation, project management issues, and risk assessments. She is the co-editor of the firm’s construction law blog, Constructlaw.com.

Friday, November 11, 2022

Jurisdiction – Employee Training, Alone, May Subject You to a Foreign State’s Jurisdiction

Turner Specialty Servs., LLC v. Horn, 2022 Tex. App. LEXIS 8139 (Tex. App.—Houston Nov. 3, 2022). 

Counsel have to analyze jurisdictional possibilities and understand that clients may be subject to jurisdiction in states not initially contemplated. Likewise, contractors need to understand that the location of certain activities, such as employee training, can lead to claims in the locale of those activities. Under certain circumstances, such training may subject contractors to foreign state jurisdiction that the contractor did not initially anticipate.

On November 3, 2022, the Court of Appeals for the First District of Texas ruled that the 55th District Court for Harris County, Texas has jurisdiction over a Louisiana-based limited liability company where the company’s employee, a Texas resident, passed away while working in Alabama. Turner Specialty Servs., LLC v. Horn, 2022 Tex. App. LEXIS 8139 (Tex. App.—Houston Nov. 3, 2022).

Turner Specialty Services, LLC (“Turner Specialty”) is a Louisiana limited liability company headquartered in Baton Rouge, Louisiana. The company provides turnaround maintenance services at refineries and petrochemical facilities, including catalyst work. Catalyst work is highly specialized and “involves working in enclosed spaces, such as large tanks and reactors, in an inert atmosphere lacking oxygen.” Id. at 3.

In March of 2019, one of Turner Specialty’s employees reached out to Justin Horn, a Texas resident, seeking his catalyst services for one of their refineries in Alabama. After accepting the job offer, Turner Specialty directed Justin to a Beaumont personnel office; wherein, Justin filled out pre-employment paperwork, underwent drug testing, conducted a physical examination, and received basic online safety training with an accompanying eight-module safety test. Id. at 4. Importantly, nine other catalyst crew members also received training at the Beaumont personnel facility. Thereafter, Justin was transported to Alabama and received additional, more specific catalyst training covering confined spaces, air supply equipment, and emergency rescue procedures.

On March 26, 2019, Justin died while performing catalyst work at the Alabama facility. As a result, Justin’s wife and mother filed a wrongful death suit, asserting, among other things, gross negligence. Specifically, the Plaintiffs asserted that the Defendants “negligently trained, hired, and/or retained Texas residents. . .” and the “negligent training, hiring, and/or retention of Texas resident workers contributed to Justin Horn’s death.” Id. at 7. In response, Turner Specialty argued that the Texas district court lacked general and specific personal jurisdiction because Turner Specialty was not “doing business” or “essentially at home” in Texas. Particularly, Turner Specialty argued, among other things, that (1) the Texas safety training was fortuitous because all Turner Specialty employees received the generalized safety training at a location most convenient for the employee, (2) the Texas safety training does not have a “substantial connection” to the events that transpired in Alabama, and (3) the actionable conduct that is substantially related to the operative facts of the litigation concerns the training and supervision provided in Alabama, not Texas.

Addressing the fortuitous argument, the Court held that the training was not fortuitous. Turner Specialty representatives reached out to Justin and directed him to the Beaumont office for onboarding procedures, including safety training. There was no evidence to suggest that Justin decided where to receive the initial safety training.  Additionally, “sending Justin to the Beaumont office was not an anomaly” as two-thirds of the catalyst crewmates working in Alabama received safety training at the Beaumont facility. Finally, the court recognized that Turner Specialty benefited from training employees in Beaumont, as it “incentivized Texas residents to work for Turner Specialty. And, by doing so, Turner Specialty acquired workers, like Justin, who had skills that were in limited supply.” Id. at 19.

Next, the Court looked at whether alleged negligent training in Texas was substantially connected to Justin’s death, that is, whether the “relationship among the defendant, the forum, and the litigation – are sufficiently close to support specific jurisdiction.” Id. at 22. The Court, noting that the “relatedness inquiry does not require a strict causal relationship between the defendant’s in-state activity and the litigation” relying on the Plaintiff’s Complaint, stated that “the [Plaintiffs] allege that the improper training, at least in part, caused or contributed to Justin’s death. Thus, Turner Specialty’s liability, if any, arises directly from and relates to the Texas safety training.” Id. at 23.  

Finally, the Court disagreed with Turner Specialty that the more specific training in Alabama was the “actionable conduct.” The court, relying on Texas Supreme Court jurisprudence, stated that “just because Turner Specialty could be subject to personal jurisdiction in Alabama does not mean that it cannot be subject to jurisdiction in Texas.” Id. at 26.  Whether the training that occurred in Texas contributed to Justin’s death presented merit-based questions for the trial court to determine.

As a result, the Texas Court of Appeal concluded that “Turner Specialty purposely availed itself of conducting activities in Texas and that the [Plaintiff’s] gross negligence claim arises from or relates to those activities. . . . the allegations and the evidence establish that Turner Specialty had sufficient minimum contracts with Texas to be subject to specific personal jurisdiction.” Id. at 27.

The Texas Court of Appeals demonstrates why contractors need to be vigilant in where they conduct basic employee training. Under certain circumstances, a foreign state court may have jurisdiction over a corporation, even when the accident in question occurs outside that foreign state’s jurisdiction.

Author, Peter-Raymond Graffeo, is an attorney with D'Arcy Vicknair, LLC in New Orleans, Louisiana. As a former civil engineer, Peter-Raymond focuses his practice in construction and surety law, commercial litigation and business law.