Tuesday, May 20, 2025

Meet the Forum's In-House Counsel: AMANDA MESSA

Company: The Lemoine Company

Website: 1lemoine.com

Law School: LSU Paul M. Hebert Law Center (JD 2005)

States Where Company Operates/Does Business: LEMOINE is a Louisiana based ENR Top-400 Contractor since 2011 with a core practice in commercial construction as well as service lines in disaster services, program management services, infrastructure and fuel logistics.

Q: Describe your background and the path you took to becoming in-house counsel.

A: After law school, I was privileged to work under some great litigators and mentors at the law firms of Wiener, Weiss & Madison and later, Phelps Dunbar.  I ultimately spent the majority of my litigation career at Phelps where I focused my practice on construction litigation.  In early 2021, LEMOINE reached out about an opportunity to become their first general counsel that I could not pass up.  The last 4 years have been both rewarding and challenging. I’ve worked to build structure and process around our legal and contracts departments as we have experienced tremendous growth.

Q: How does working in-house compare or differ from firm life?  

A: I think the difference that surprises people the most is I definitely work more than I did when I worked at a law firm. I just don’t have the billables to prove it! Another key difference is I often don’t get the opportunity to collaborate and research issues comprehensively like I used to. The days of creating a research memo are certainly gone. My focus has to be on coming up with the best practical solution to help our project teams keep things moving forward.  

Q: How and when do you use outside counsel?   

A: While I still enjoy a healthy sparing match from time to time, a general rule of thumb for me is when something starts to escalate towards litigation (or I start to get aggressive emails), it’s time to call my litigator friends.  From a capacity standpoint, I can’t be tied up for extended periods of time with hearings or depositions, and I need those valuable extra resources a law firm has to offer.

Q: What are the work/business-related issues that tend to keep you up at night?  

A: It’s the unknowns that keep me up at night – i.e. what new legislation (or currently, executive order) is coming down the pipeline that we need to be aware of and take into consideration as we expand in new geographic areas and service lines.  I rely heavily on firm blogs/updates to keep leadership and our project teams up to speed on new industry issues.

Q: What qualities or characteristics do you look for in outside counsel? 

A: Responsive and practical – Because of the pace at which things move in-house and the number of emails I get each day, I truly value those outside lawyers we work with that timely respond with succinct, practical guidance and updates.  If I’ve gone to outside counsel it’s because I’ve likely already run through the pros and cons and I need a recommendation based on their experience.

Q: What advice would you give to outside counsel about how to meet or even exceed their client's expectations? 

A: Spend some extra time (even if it’s non-billable) getting to know your client’s business – the specific industry they operate within, their leadership structure and the way they approach litigation and business issues. If you’re giving legal advice in a vacuum without that background information, it’s not going to be as effective.

Q: What is the biggest problem that you see when working with outside counsel? 

A: I’m still only a few years removed from the litigation practice so I remember how easy it can be to go down a rabbit hole on a particular legal issue.  But from an in-house perspective, we often have a very limited budget to spend and countless issues that will come up throughout the year.  On occasion, outside counsel will spend a lot of time on an issue that doesn’t necessarily warrant that allocation of resources from our end. I’ve tried to be more intentional about communicating expectations/goals/budgetary restrictions at the outset, but it’s great to proactively address those issues as outside counsel even if in-house counsel doesn’t raise them.  

Q: What are some of your interests or hobbies? 

A: Baseball and books!  13U baseball consumes a LOT of our  weekends these days and gets me away from the computer screen.  It’s therapeutic for me to be outside watching our son (Wyatt) and his teammates compete in travel baseball tournaments. Our daughter (Jules) has even started to join in on the fun and is learning to record the plays in game changer. In the last 9 months, I’ve also taken up reading for the first time in over 20+ years. It’s been a great way to keep me on the elliptical machine longer and provides another escape from the constant flow of work emails.


Assistant Editor-in-Chief Jessica Knox is a Partner in the Minneapolis office at Stinson LLP. She represents owners, general contractors, and subcontractors in litigation disputes. Jessica can be contacted at jessica.knox@stinson.com. 

Tuesday, May 13, 2025

Discovery Channel: Categories of Documents Required for a Schedule Analysis

Effective schedule analysis in construction projects hinges on the discovery and examination of key documents, which provide insights into project timing, progress, and the causes of delays. This article identifies the types of discovery (i.e., documentation formally requested and exchanged between the parties to a dispute) required for a scheduling or delay expert to provide a robust schedule analysis. The discovery types are grouped as follows: Category 1: documents related to the timing of the project; Category 2: documents that corroborate the schedules; and Category 3: documents that help identify the causal link.  The above categories, which are required irrespective of which schedule analysis method is deployed, are also described in this article using a hypothetical example of a residential construction project.

Category 1: Documents Related to Project Timing

Category 1 documents are those that provide the schedule analyst with an understanding of the planned and actual timing of the project. The most important documents in Category 1 are contracts, the baseline or rebaseline schedules, and schedule updates. Other schedules or timing-related documents may include lookahead schedules and change orders.

The contract(s) will help the analyst establish the parameters of the schedule analysis, as contracts contain clauses related to the planned timing for project delivery (represented by a milestone date or dates), as well as the penalties applicable for failure of the Contractor to meet the planned completion date (i.e., liquidated damages, or “LDs”). Additionally, contracts may stipulate the preferred or required methodology and/or course of action for claims and disputes. Lastly, any contemporaneous extension of time (“EoT”) requests and awards (possibly executed change orders) should be requested, as these will provide the analyst with the updated milestone date(s).

The other documents under Category 1 are the schedules themselves (baseline, rebaseline, and updates). While the contract may set out the high-level, planned timeline of the project, the schedules give the analyst a more detailed understanding of how the planned and actual sequences evolve over time. Schedules are typically prepared in Primavera P6 (“.xer” file type) or Microsoft Project (“.mpp” file type) but may only be available in PDF format. The native schedules are the preferred source to understand the parties’ contemporaneous intentions, as they enable the analyst to review and understand logic, criticality, resource information, and much more information that is not reflected in PDF format.

Other documents which are commonly produced and may provide additional time-related context are lookahead schedules and “Level 4” schedules (detailed schedules that depict granular tasks which are often prepared in Microsoft Excel). While not the primary time-related documents, these documents provide additional detail and further insight into the parties’ contemporaneous intentions. In summary, Category 1 documents arm the analyst with key information on the planned and actual timing of the project, and therefore, are foundational to the schedule analysis. 

Example:

To underpin the importance of Category 1 documents, imagine a hypothetical residential construction project. In this hypothetical, the Category 1 documents available are the contract, baseline schedule, and monthly schedule updates. The contract between the Owner and the Contractor provides an original planned completion date of August 14, 2025.  Additionally, the baseline and monthly schedule updates indicate that, amongst other activities, the design and construction of the kitchen are on the critical path; the figure below is an excerpt of the baseline schedule (in Primavera P6), showing the design and construction of the kitchen to be critical (see Activity Names “Design Kitchen” and “Construct Kitchen”).


Category 2: Documents Corroborating Category 1

An important aspect of any schedule analysis is corroborating the schedule to ensure accuracy and alignment with other contemporaneous records. These corroborating Category 2 documents include but are not limited to: progress reporting (monthly, weekly, daily), correspondence, manpower reports, procurement and equipment logs, requests for information (“RFI”) and logs, shop drawing logs, payment applications, and meeting minutes.

Typically, the most common corroborating document type is progress reporting (be it monthly, weekly, or daily), as these reports often contain granular progress information that assists in schedule analysis. For instance, the schedules may contain a summary-level activity titled “Prepare Shop Drawings”; progress reports may feature charts and tables that show how shop drawings have and are forecasted to advance, comparisons of the planned and actual production rates, and other useful information. Typically, these reports are viewed as the “official” progress information from the Contractor. Additionally, progress reporting may contain details about labor productivity, manpower, delaying issues, and more.

Meeting minutes, payment applications, and other logs may not contain the same types of charts and tables as progress reports and therefore can also be used to validate and supplement the schedules. For example, meeting minutes may record the timing of an owner-directed design change; this information may or may not be recorded in the schedule updates.

Example:

As explained above, the baseline schedule showed a single activity for the construction of the kitchen (which was critical), and the contract indicated the home construction would finish by August 14, 2025. Below is an example of a daily progress report dated August 15, 2025, which records drywall and tiling are ongoing in the kitchen, after the project should have finished according to the contract.  Also, the daily report highlights issues related to the tiling.  

In this example, by referencing the daily progress report, the schedule analyst can understand what work related to the construction of the kitchen is ongoing at a particular date, which cannot be determined by only examining the schedules (as they only contain a single activity representing the construction of the kitchen). In summary, Category 2 documents should always be reviewed to corroborate and supplement the available schedules.

Category 3: Documents that Establish a Causal Link

A requirement of any schedule delay analysis is demonstrating the causal link, also referred to as identifying the “cause” or “causes” of the critical delay that is measured.  Documents that help establish a causal link fall under the purview of Category 3. Causes of delay are unique to the challenges each construction project faces. Furthermore, unlike Category 1 and 2 documents, which are most likely in the Contractor’s possession, documents establishing causes of delay may be in the possession of both the Contractor and the Owner.

While Category 3 documents are unique to each project, some common examples of documents that describe or explain contemporaneous causes of delay include notices of delay, contemporaneously prepared claims, RFIs, potential change orders and executed change orders, Stop Work Orders, internal and external correspondence related to specific topics, witness testimony, and QA/QC reports.

Example:

Using the same example home construction project from above, the available Category 3 documents indicate that the Owner requested a larger kitchen via an executed change order dated June 14, 2025 (see figure below).

As mentioned previously, the baseline and schedule updates (Category 1) showed the kitchen design and construction on the critical path, and daily progress reports (Category 2), which were issued after the planned project completion date, recorded that the kitchen tiling works were experiencing extensive delays. Given the timing and scope, this change order (Category 3) likely explains some of the critical delays to the project. 

Conclusion

This article aimed to identify the types of discovery required for a scheduling or delay expert to complete a schedule analysis. The discovery types have been grouped into three categories: documents related to the timing of the project (Category 1), documents that corroborate the schedules (Category 2), and documents that help identify the causal link (Category 3). By analyzing these documents, a scheduling expert can effectively determine the critical path, understand the magnitude of the delays, and identify the causes of critical delays. 


Author Jordan Peponis is a Senior Director in Kroll’s Construction Expert Services practice. Based in Atlanta, Jordan has 13 years of experience in providing consultation on a variety of international and domestic projects. He serves most often as an independent delay expert, providing critical path delay and loss of productivity analyses. Jordan can be contacted at Jordan.Peponis@kroll.com.