The Massachusetts
Appeals Court affirmed summary judgment in favor of a general contractor in the
matter Acme
Abatement Contractor, Inc. v. S&R Corporation. The general contractor, S&R Corporation,
hired an asbestos abatement subcontractor, Acme, to demolish and remove
materials from a water treatment plant and ball field. The linchpin issue was whether the
subcontract required the paint removed from a section of the bleachers at the ball
field.
The subcontractor claimed
that there was no asbestos in the paint therefore removing the paint was
outside the scope of its contract. It refused
to do that work. As a result, the
general contractor was forced to hire another contractor. When the subcontractor demanded payment for
the work it had completed, the general contractor refused and did not pay the
subcontractor anything. The subcontractor
sued.
The general contractor
proceeded to summary judgment on two bases.
First, it argued that the subcontract had assumed that all paint
contained asbestos and therefore the subcontract’s scope necessarily included
removing the subject paint. Then the general contractor argued if there were
disputes about scope, per the contract terms, the subcontractor was required to
do the work and then litigate the scope later:
"In
the event of any dispute, controversy or claim between the Contractor and the
Subcontractor, the Subcontractor agrees to proceed with the Work or extra work
without delay and without regard to such dispute, controversy, claim or the
tendency [sic] of any proceeding in relation to the same. The failure of the
Subcontractor to comply with the provisions of this paragraph shall constitute
a material breach of this agreement. . . ."
Because the
subcontractor refused to perform the disputed work, general contractor asserted
that the refusal was a material breach and it was justified in not paying the
subcontractor for any work. The
appellate court agreed with this second argument.
The subcontractor attempted
to counter that even if it breached by not doing the subject work, under a
theory of quantum meruit, it still was entitled to payment for the work it did
perform. The appellate court disagreed
holding that because the subcontractor "intentional[ly] depart[ed] from
the contract in a material matter without justification or excuse," its
claim for recovery under quantum meruit was precluded.
-----------------------------
The author, Katharine Kohm, is a committee member for The Dispute Resolver. Katharine practices construction law and commercial litigation in Rhode Island and Massachusetts. She is an associate at Pierce Atwood, LLP in Providence, Rhode Island. She may be contacted at 401-490-3407 or kkohm@PierceAtwood.com.