The U.S.
Court of Federal Claims shows contractors once again the dangers that can exist
when pricing a performance specification and the importance of giving owner’s
proper notice for change orders in CKYInc. v. Unites States of America.
In 2012,
the Government awarded CKY, Inc. a $6.4M contract to widen and rehabilitate the
Urban Presidio Levee located in Presidio, TX.
The work required CKY to excavate existing materials in a series of
benches and then infill the benches with new materials. The contract contained a material testing
specification which required the new fill material meet certain requirements. The existing “benched” materials was further
required to meet a performance specification as to moisture content and
compaction rates.
During the
bid process, the Government released Amendment 003 which contained questions
and answers from bidders to the Government.
Within that document, the Government stated:
- “Due to contamination in situ and the Contractor’s excavation processes, [the Government] cannot state that excavated material will meet…requirements. The Contractor is required to meet the embankment specification regardless of the source of the embankment material.”
- “Question: Will removal and disposal of any unsatisfactory material from the existing levee embankment be paid as a separate item, as it is unknown how much material will be unsuitable for use in the new embankment? Government Response: No.”
“The
data and report are not intended as a representation or warranty of continuity
of conditions between soil borings nor groundwater levels at dates and times
other than the date and time when measured. The [Commission] will not be
responsible for interpretations or conclusions drawn there by the Contractor.”
During
construction, CKY had difficulty achieving the subgrade requirements for moisture
and density which resulted in schedule delays. CKY alleged at this time it was
directed by the Government to place new suitable materials over the “unacceptable,
non-constructible subgrade.”
In August
of 2016, CKY filed a complaint in the U.S. Court of Federal Claims claiming
costs for: (1) differing site conditions; (2) defective specifications; (3)
constructive change; and (4) breach of an oral and implied-in-fact contract.
The Government
moved for summary judgement contending CKY’s interpretation of the contract and
specification were improper and CKY had not provided adequate notice of
differing site conditions. It then filed a counter claim for liquidated damages.
The Court
began its analysis by stating the primary issue in the dispute is the suitability
of the subgrade material and CKY’s entire claim is based upon its contract interpretation
that the subgrade was to be “acceptable and constructible.”
The Court
first examined the Government’s assertion CKY’s interpretation of the contract
documents and specifications were incorrect.
The Court reviewed the items contained within Addendum 003 and the geotechnical
report disclaimer and found that a reliable contractor could not have relied on
the subgrade soil to meet the requirements of the specifications. The Court elaborated that, “When all parts of
the contract are assigned meaning and understood in their entirety, CKY’s
reliance on its own interpretation of the constructability and suitability of
the subgrade material was unreasonable.”
The Court
next reviewed the differing site condition claim and CKY’s argument that “constructive
notice” had been given to the Government.
The Court noted constructive notice is allowed only if “the Government
is not prejudiced by a lack of written notice.”
The Court reasoned that since it took CKY over a year to submit a REA for
the subgrade materials, the Government was prejudiced because it could have
stopped construction to evaluate all options other than a $4.5M
change order.
Finally, the Court found that as a result of finding CKY had no basis for a claim and the project being 225
days late, liquidated damages as identified in the contract were appropriate in
the amount of $1,885 per day.
In
conclusion, the Government was granted summary judgement and awarded $424,125
in liquidated damages.
--------------------------------------------------
The
author, Brendan Carter, Esq., is the Director of Industry Advancement &
Labor Relations with the AGC of Massachusetts based in Wellesley, MA. He is a
monthly contributor to The Dispute Resolver and a former Student Division Liaison
to the Forum on Construction Law.
No comments:
Post a Comment